Reviewed record

Madrid A-5 undergrounding, Lot 2: Batán to Avenida de Portugal

Location
Madrid (Latina district, by Casa de Campo), Community of Madrid, Spain. See it on the map, in 3D
Stage
Under construction, as of April 13, 2026 (Acciona). Acciona reported piles and the roof slab complete, with 1.3 km of the south tube and 0.73 km of the north tube excavated, in April 2026; the city reported both tubes excavated by end of May 2026.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerAyuntamiento de Madrid
TypeHighways
Headline amountEUR 141.7 million (EUR), as of February 2024Gobierto Contratos (PLACSP data, Ayuntamiento de Madrid)
What it coversBudget.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Tunnel length1.5 kmLot 2 tunnelAcciona
Lanes3 lanes each wayplus Bus-HOV lanesAcciona
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€124 MContract valueLot 2 award, appears excl. VATAugust 22, 2024Gobierto Contratos (PLACSP data, Ayuntamiento de Madrid)
€150 MContract valueLot 2 as stated by Acciona ('budget'; matches 124M incl. 21% VAT)October 15, 2024Acciona
€142 MBudgetLot 2 tender budget excl. VAT (171.5M incl. VAT per press)February 2024Gobierto Contratos (PLACSP data, Ayuntamiento de Madrid)
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Ayuntamiento de MadridOwnerGobierto Contratos (PLACSP data, Ayuntamiento de Madrid)
DragadosContractor, one lotLot 2, UTE Dragados-Acciona Construcción Soterramiento A-5; shares not statedGobierto Contratos (PLACSP data, Ayuntamiento de Madrid)
Acciona ConstrucciónContractor, one lotLot 2, UTE with Dragados; shares not statedGobierto Contratos (PLACSP data, Ayuntamiento de Madrid)
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
August 22, 2024Lot 2 awardedGobierto Contratos (PLACSP data, Ayuntamiento de Madrid)
October 15, 2024Works beginAcciona
April 13, 2026South tube sections connected; 1.3 km of south tube and 0.73 km of north tube excavatedAcciona
October 25, 2026 (planned)Contract end dateGobierto Contratos (PLACSP data, Ayuntamiento de Madrid)
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

The eastern lot of Madrid's A-5 undergrounding is a 1.5 km tunnel from Batán to the existing Avenida de Portugal tunnel, with three lanes per direction plus Bus-HOV lanes, linked to the M-30. Dragados and Acciona won it in August 2024 for EUR 124 million and began works in October 2024. Both tubes were excavated by May 2026; the city plans to open the tunnel at the end of 2026.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.

Sources

See it on the map. How the map is made.