Reviewed record

A-11 Autovía del Duero: Olivares de Duero to Tudela de Duero

Location
Olivares de Duero, Villabáñez and Tudela de Duero, Valladolid, Castile and León, Spain. See it on the map, in 3D
Stage
Partly in service, partly under construction, as of August 24, 2026 (elDiario.es Castilla y León). The section opened on 24 August 2026, nearly in full, with the connection at the Tudela junction pending.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerMinisterio de Transportes y Movilidad Sostenible, Dirección General de Carreteras
TypeHighways
Headline amountEUR 81.2 million (EUR), as of May 30, 2019Boletín Oficial del Estado
What it coversBudget.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Length20.2 kmmain carriagewayBoletín Oficial del Estado
Junctions2 junctionssectionBoletín Oficial del Estado
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€79 MContract valueoriginal contract (press); VAT not statedSeptember 2019Xataka
€81 MBudgetestimated tender value, excl. VATMay 30, 2019Boletín Oficial del Estado
€85 MBudgetestimated tender budget of the route project, excl. VATJuly 18, 2017Boletín Oficial del Estado
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Ministerio de Transportes y Movilidad Sostenible, Dirección General de CarreterasOwnerBoletín Oficial del Estado
TECOPY, S.A. and GETINSA (UTE)DesignerTechnical assistance for the route project (June 2016), author José Roberto García García (TECOPY)Boletín Oficial del Estado
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
July 18, 2017Route project approvedBoletín Oficial del Estado
December 2, 2019Works beginDiario de Valladolid
August 24, 2026Section opens, Tudela junction link pendingelDiario.es Castilla y León
June 2027 (planned)Whole Quintanilla-Tudela complete (first half 2027)elDiario.es Castilla y León
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

This 20.2 km section of the A-11 links Olivares de Duero and Tudela de Duero in Valladolid province, with two junctions. Works started in December 2019 with an original EUR 79.1 million contract and a 36-month term. It opened to traffic in August 2026, except the link at the Tudela junction, which the Ministry expects to finish with the rest of the Quintanilla-Tudela stretch in the first half of 2027.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.