Reviewed record
A-67 motorway widening to three lanes: Polanco to Santander
- Location
- Polanco, Miengo, Piélagos, Santa Cruz de Bezana and Camargo, Cantabria, Cantabria, Spain. See it on the map, in 3D
- Stage
- Under construction, as of December 3, 2025 (Delegación del Gobierno en Cantabria). The Ministry said on 3 December 2025 that it was still executing the works. Press reported in August 2026 that the contractor had asked on 16 June 2026 for a total temporary suspension and had withdrawn its machinery on the Santander-Torrelavega stretch; no official suspension was found.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Ministerio de Transportes y Movilidad Sostenible, Dirección General de Carreteras | |
| Type | Highways | |
| Headline amount | EUR 172.8 million (EUR), as of December 3, 2025 | Delegación del Gobierno en Cantabria |
| What it covers | Budget. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Length | 13 km | section | Delegación del Gobierno en Cantabria |
| Lanes | 3 lanes each way | after works (a third lane added to each carriageway) | Delegación del Gobierno en Cantabria |
| Junctions | 5 junctions | Polanco, Oruña, Boo, Mompía, Igollo, plus Gornazo service area | Delegación del Gobierno en Cantabria |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €143 M | Contract value | value of the selected offer (BOE formalisation notice), excl. VAT | December 14, 2023 | Boletín Oficial del Estado |
| €173 M | Contract value | contract formalised, incl. VAT | March 18, 2024 | Delegación del Gobierno en Cantabria |
| €203 M | Budget | project tender base budget, incl. 21% VAT | March 30, 2023 | Boletín Oficial del Estado |
| €173 M | Budget | whole works, incl. VAT | December 3, 2025 | Delegación del Gobierno en Cantabria |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Ministerio de Transportes y Movilidad Sostenible, Dirección General de Carreteras | Owner | Boletín Oficial del Estado | |
| Constructora San José and Aceinsa Movilidad (UTE) | General contractor | Shares not stated; 12 bids | Boletín Oficial del Estado |
Milestones
| Date | Milestone | Source |
|---|---|---|
| March 30, 2023 | Construction project approved | Boletín Oficial del Estado |
| December 14, 2023 | Contract awarded | Boletín Oficial del Estado |
| March 18, 2024 | Contract formalised | Delegación del Gobierno en Cantabria |
| June 16, 2026 | Contractor requests total temporary suspension (press) | elDiario.es Cantabria |
About the project
The Ministry of Transport is widening about 13 km of the A-67 between Polanco and Santander from two to three lanes each way, with wider curves, hard shoulders and median and safer junctions. The contract was signed in March 2024 with Constructora San José and Aceinsa Movilidad for EUR 172.9 million including VAT, and works began in April 2024. In 2026 the contractor sought a price revision and a temporary suspension, according to the press.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Anuncio de formalización: Autovía A-67. Ampliación de capacidad. Tramo Polanco-Santander (BOE-B-2024-9003), Boletín Oficial del Estado (government), 15 Mar 2024. Consulted 26 Nov 2026.
- Transportes formaliza por 173 millones de euros las obras para ampliar a tres carriles la autovía A-67 entre Polanco y Santander, Delegación del Gobierno en Cantabria (government), 18 Mar 2024. Consulted 26 Nov 2026.
- Transportes continúa con las obras de reubicación de líneas eléctricas en Piélagos para la ampliación de la A-67, Delegación del Gobierno en Cantabria (government), 3 Dec 2025. Consulted 26 Nov 2026.
- Aprobación definitiva del Proyecto de Construcción Autovía A-67, Polanco-Santander (BOE-B-2023-13533), Boletín Oficial del Estado (government), 8 May 2023. Consulted 26 Nov 2026.
- Casares advierte a la empresa que construye el tercer carril de la A-67 que hay un contrato que cumplir, elDiario.es Cantabria (press), 6 Aug 2026. Consulted 26 Nov 2026.