Reviewed record
A-63 Oviedo to La Espina motorway: Cornellana to Salas
- Location
- Salas (Cornellana to Salas), Asturias, Asturias, Spain. See it on the map, in 3D
- Stage
- Under construction, as of June 17, 2026 (La Voz del Trubia). The Government Delegate visited the works on 17 June 2026, when the main contract stood at 90% executed.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Ministerio de Transportes y Movilidad Sostenible, Dirección General de Carreteras | |
| Type | Highways | |
| Headline amount | EUR 158 million (EUR), as of June 18, 2026 | La Voz del Trubia |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Length | 6,015 m | section | Aquí Diario |
| Viaduct length total | 1,400 m | six viaducts together | Aquí Diario |
| Viaducts | 6 viaducts | section | Aquí Diario |
| Underpasses | 2 underpasses | section | Aquí Diario |
| Hillside length | 2,600 m | mid-slope alignment | Aquí Diario |
| Cutting length | 700 m | in cutting | Aquí Diario |
| Embankment length | 1,315 m | on embankment | Aquí Diario |
| Progress | 90 % | main works | La Voz del Trubia |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €109 M | Contract value | main works contract (VAT treatment not stated) | June 17, 2026 | Aquí Diario |
| €46 M | Contract value | emergency stabilisation works for the Casazorrina landslide, after two increases | June 17, 2026 | Aquí Diario |
| €3 M | Contract value | technical assistance contracts | June 17, 2026 | Aquí Diario |
| €158 M | Total project cost | works plus emergency measures | June 18, 2026 | La Voz del Trubia |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Ministerio de Transportes y Movilidad Sostenible, Dirección General de Carreteras | Owner | Boletín Oficial del Estado | |
| WSP Spain-Apia, S.A.U. | Supervision | Control and surveillance contract awarded 2020-08-04 (24 bids) | Boletín Oficial del Estado |
Milestones
| Date | Milestone | Source |
|---|---|---|
| July 24, 2006 | Construction project approved | Boletín Oficial del Estado |
| August 4, 2020 | Control and surveillance contract awarded to WSP Spain-Apia | Boletín Oficial del Estado |
| April 2021 | Casazorrina landslide on cutting D-11 | Aquí Diario |
| April 24, 2025 | Modification No.4 route project approved | Boletín Oficial del Estado |
| June 17, 2026 | 90% executed | Aquí Diario |
About the project
The Ministry of Transport is building a 6 km section of the A-63 between Cornellana and Salas in western Asturias, a hillside route with six viaducts totalling about 1.4 km. The main contract is worth EUR 109.3 million, and a landslide at Casazorrina found in 2021 added EUR 45.7 million of emergency stabilisation works. The section was 90% complete in June 2026; no opening date was given.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- El tramo Cornellana-Salas de la A-63, al 90% de ejecución, La Voz del Trubia (press), 18 Jun 2026. Consulted 26 Nov 2026.
- Adriana Lastra visita las obras estatales en Salas: el argayón de Casazorrina y la A-63 'con alto grado de ejecución', Aquí Diario (press), 17 Jun 2026. Consulted 26 Nov 2026.
- Aprobación definitiva del proyecto de trazado de la modificación nº 4, A-63 Cornellana-Salas (BOE-B-2025-15983), Boletín Oficial del Estado (government), 5 May 2025. Consulted 26 Nov 2026.
- Formalización: Control y vigilancia de las obras A-63, Cornellana-Salas (BOE-B-2020-30219), Boletín Oficial del Estado (government), 17 Sep 2020. Consulted 26 Nov 2026.
- Actas de ocupación, Modificado nº 4 A-63 Cornellana-Salas (BOE-B-2025-25006), Boletín Oficial del Estado (government), 2 Jul 2025. Consulted 26 Nov 2026.