Reviewed record
A-54 Lugo to Santiago motorway: Melide (south) to Arzúa (west)
- Location
- Melide, Santiso and Arzúa, A Coruña, Galicia, Spain. See it on the map, in 3D
- Stage
- Under construction, as of November 9, 2026 (El Debate). In November 2026 the section was still closed, with works continuing and no opening date; the planned early-2026 opening was missed.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Ministerio de Transportes y Movilidad Sostenible, Dirección General de Carreteras | |
| Type | Highways | |
| Headline amount | EUR 116.5 million (EUR), as of February 3, 2023 | Delegación del Gobierno en Galicia |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Length | 16.4 km | section | Delegación del Gobierno en Galicia |
| Junctions | 4 junctions | section | Delegación del Gobierno en Galicia |
| Structures | 25 structures | section | Delegación del Gobierno en Galicia |
| Viaducts | 9 viaducts | section | Delegación del Gobierno en Galicia |
| Overpasses | 10 overpasses | 2 for wildlife or multi-use | Delegación del Gobierno en Galicia |
| Underpasses | 6 underpasses | 4 for wildlife or multi-use | Delegación del Gobierno en Galicia |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €89 M | Contract value | award incl. VAT (net 73,216,407.19); tender base 157,580,670.05 incl. VAT | December 29, 2017 | Boletín Oficial del Estado |
| €117 M | Total project cost | total investment of the section | February 3, 2023 | Delegación del Gobierno en Galicia |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Ministerio de Transportes y Movilidad Sostenible, Dirección General de Carreteras | Owner | Boletín Oficial del Estado | |
| Construcciones Sánchez Domínguez Sando and Copisa Constructora Pirenaica (UTE) | General contractor | Awarded 2017-11-27; shares not stated | Boletín Oficial del Estado |
Milestones
| Date | Milestone | Source |
|---|---|---|
| December 29, 2017 | Works contract formalised | Boletín Oficial del Estado |
| February 3, 2023 | Government Delegate visits the works | Delegación del Gobierno en Galicia |
| November 9, 2026 | Still closed, no opening date | El Debate |
About the project
This 16.4 km section of the A-54 between Melide and Arzúa, in A Coruña, is the last missing link of the Lugo-Santiago motorway. It has four junctions and 25 structures, including nine viaducts such as Catasol, Boente and Ladrón. Sando and Copisa have been building it since a contract formalised in December 2017 for EUR 88.6 million including VAT; the Ministry put the total investment at EUR 116.5 million in 2023. It was still not open in November 2026.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Formalización: Autovía Lugo-Santiago, A-54. Tramo Enlace de Melide (Sur)-Enlace de Arzúa (Oeste) (BOE-B-2018-411), Boletín Oficial del Estado (government), 3 Jan 2018. Consulted 26 Nov 2026.
- Miñones supervisa la ejecución del tramo Melide-Arzúa de la A-54, Delegación del Gobierno en Galicia (government), 3 Feb 2023. Consulted 26 Nov 2026.
- La autovía Santiago-Lugo, una obra infinita: 30 años de esperas y plazos rebasados, El Debate (press), 9 Nov 2026. Consulted 26 Nov 2026.