Reviewed record
IP3 duplication and upgrade: Santa Comba Dão to Viseu
- Location
- Santa Comba Dão, Tondela and Viseu, district of Viseu, Centro, Portugal. See it on the map, in 3D
- Stage
- Under construction, as of March 24, 2025 (Infraestruturas de Portugal (consignação presentation)). Infraestruturas de Portugal signed the auto de consignação (handover of the site) on 24 March 2025; the Government said in December 2025 that the section was under construction.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Infraestruturas de Portugal, S.A. | |
| Type | Highways | |
| Amount | Not found in the sources consulted |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Length | 27.5 km | section km 90+200 to km 117+722 | Infraestruturas de Portugal (consignação presentation) |
| Lanes | 2x2 lanes | after works | Infraestruturas de Portugal (consignação presentation) |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €103 M | Contract value | VAT treatment not stated | March 24, 2025 | Infraestruturas de Portugal (consignação presentation) |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Infraestruturas de Portugal, S.A. | Owner | Infraestruturas de Portugal | |
| Ferrovial | General contractor | Reported as winning bidder at EUR 103 million (press, 2024-07); not named on the owner's pages read | Essential Business |
Milestones
| Date | Milestone | Source |
|---|---|---|
| July 1, 2024 | Press reports Ferrovial as winning bidder | Essential Business |
| March 24, 2025 | Auto de consignação signed (870-day term) | Infraestruturas de Portugal (consignação presentation) |
About the project
Infraestruturas de Portugal is widening 27.5 km of the IP3 trunk road between Santa Comba Dão and Viseu to two lanes in each direction, from km 90+200 north of the Vila Pouca junction to the A25/IP5 interchange at Viseu. The works contract, worth EUR 103.28 million, was handed over on 24 March 2025 with an 870-day term. Spanish press reported Ferrovial as the winning bidder in July 2024.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- IP3: consignação da empreitada de duplicação e requalificação entre Santa Comba Dão e Viseu, Infraestruturas de Portugal (owner), 24 Mar 2025. Consulted 26 Nov 2026.
- Auto de Consignação IP3 Viseu | Coimbra, Troço Santa Comba Dão | Viseu, Infraestruturas de Portugal (consignação presentation) (owner), 25 Mar 2025. Consulted 26 Nov 2026.
- Spain's Ferrovial wins tender for IP3 motorway enlargement project, Essential Business (press), 1 Jul 2024. Consulted 26 Nov 2026.
- IP3 cortado ao trânsito em noites desta semana entre Tondela e Santa Comba Dão, Observador (press), 20 Jul 2026. Consulted 26 Nov 2026.
- Governo investe 502 milhões na requalificação e duplicação do IP3, Governo de Portugal (government), Dec 2025. Consulted 26 Nov 2026.