Reviewed record
Porto-Lisbon high-speed line: Porto (Campanhã)-Oiã section
- Location
- Porto to Oiã (Oliveira do Bairro), through 10 municipalities, Norte / Centro, Portugal. See it on the map, in 3D
- Stage
- Under construction, as of October 2026 (Infraestruturas de Portugal). Infraestruturas de Portugal and AVAN started the works on 2026-10-12.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owners | Infraestruturas de Portugal, AVAN Norte - Gestão da Ferrovia de Alta Velocidade | |
| Type | Rail | |
| Headline amount | EUR 2 billion (EUR), as of October 2026 | Governo de Portugal |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Length | 71 km | section | Infraestruturas de Portugal |
| Design speed | 300 km/h | section | Infraestruturas de Portugal |
| Tunnels length | 8 km | section total | Infraestruturas de Portugal |
| Bridges viaducts length | 19 km | section total | Infraestruturas de Portugal |
| Link to linha do norte | 8.3 km | connection | Infraestruturas de Portugal |
| Municipalities | 10 | section | Infraestruturas de Portugal |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €1.66 bn | Contract value | concession award value | July 2025 | Observador |
| €2 bn | Total project cost | cost of the Porto-Oiã section as stated by the Government, basis not stated | October 2026 | Governo de Portugal |
| €875 M | Loan | EIB first tranche | July 2025 | European Investment Bank |
| €480 M | Investment programme | CEF grant for Phase 1 | July 2025 | European Investment Bank |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Infraestruturas de Portugal | Owner | Infraestruturas de Portugal | |
| AVAN Norte - Gestão da Ferrovia de Alta Velocidade | Concessionaire | 30-year concession, first 5 years design, construction and certification | Infraestruturas de Portugal |
| Mota-Engil | General contractor | consortium leader | Observador |
| Serena | General contractor | consortium member | Governo de Portugal |
| Teixeira Duarte | General contractor | consortium member | Governo de Portugal |
| Casais | General contractor | consortium member | Governo de Portugal |
| Alves Ribeiro | General contractor | consortium member | Governo de Portugal |
| Conduril | General contractor | consortium member | Governo de Portugal |
| Gabriel Couto | General contractor | consortium member | Governo de Portugal |
| European Investment Bank | Lender | EUR 875M first tranche | European Investment Bank |
Milestones
| Date | Milestone | Source |
|---|---|---|
| October 10, 2024 | Concession awarded to LusoLAV | Infraestruturas de Portugal |
| July 29, 2025 | Concession contract signed | European Investment Bank |
| December 22, 2025 | APA rejects the concessionaire's changes in Gaia and Porto | Observador |
| June 8, 2026 | Revised design for Espinho, Gaia and Porto in public consultation | Observador |
| October 12, 2026 | Works start, ceremony at Oiã | Infraestruturas de Portugal |
About the project
The first section of the Porto-Lisbon high-speed line: 71 km of new double track between Porto-Campanhã and Oiã, built for 300 km/h. It includes 8 km of tunnels, 19 km of bridges and viaducts, a new road and rail bridge over the Douro and a new underground station at Santo Ovídio in Vila Nova de Gaia. It is built under a 30-year concession by AVAN Norte, led by Mota-Engil, and works started in October 2026.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Arrancam as obras do primeiro troço da Linha de Alta Velocidade entre Porto (Campanhã) e Oiã, Infraestruturas de Portugal (owner), 12 Oct 2026. Consulted 26 Nov 2026.
- Governo arranca com alta velocidade Porto-Oiã, Governo de Portugal (government), 11 Oct 2026. Consulted 26 Nov 2026.
- Portugal signs concession and first tranche of financing for new Lisbon-Porto high-speed line, European Investment Bank (lender), 29 Jul 2025. Consulted 26 Nov 2026.
- Linha de Alta Velocidade Porto-Lisboa, Infraestruturas de Portugal (owner). Consulted 26 Nov 2026.
- Oito quilómetros de túneis, nova ponte no Douro e uma estação ainda polémica, Observador (press), 12 Oct 2026. Consulted 26 Nov 2026.
- Alta velocidade. Projeto revisto prevê ponte no Douro com carros por baixo do tabuleiro ferroviário e menos extensão em túnel, Observador (press), 5 Jun 2026. Consulted 26 Nov 2026.
- APA chumba alterações que o consórcio do TGV queria fazer em Gaia e no Porto, Observador (press), 22 Dec 2025. Consulted 26 Nov 2026.
- Ponte rodoferroviária no Douro terá ciclovia e estação TGV de Gaia será grande interface, ECO (press), 9 Jun 2026. Consulted 26 Nov 2026.