Linha do Oeste: Meleças-Caldas da Rainha modernisation
- Location
- Mira Sintra-Meleças (Sintra) to Caldas da Rainha, via Malveira and Torres Vedras, Lisbon / Centro, Portugal. See it on the map, in 3D
- Stage
- Under construction, as of August 2026 (24notícias). In August 2026 repair contracts were being placed and trains were expected back on Torres Vedras-Caldas da Rainha at the end of 2026 and on Meleças-Torres Vedras in early 2027, with works running to April 2027.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Infraestruturas de Portugal | |
| Type | Rail | |
| Amount | Not found in the sources consulted |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Electrified length | 43 km | Mira Sintra-Meleças to Torres Vedras | Infraestruturas de Portugal |
| Double track length | 16 km | two passing sections of 10 and 6 km | Infraestruturas de Portugal |
| Grade separated crossings | 9 | first section | Infraestruturas de Portugal |
| Tunnels rehabilitated | 4 | Sapataria, Boiaca, Cabaço, Certã | Infraestruturas de Portugal |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €155 M | Investment programme | global investment of the Linha do Oeste modernisation, Mira Sintra to Caldas da Rainha, VAT not stated | Undated | Infraestruturas de Portugal |
| €62 M | Contract value | Mira Sintra-Meleças to Torres Vedras works contract, EU co-financed through Compete 2020, VAT not stated | November 2020 | Infraestruturas de Portugal |
| €40 M | Contract value | repair contracts signed June to July 2026 (supervision, four direct awards, Torres Vedras-Caldas repairs) | August 2026 | 24notícias |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Infraestruturas de Portugal | Owner | Infraestruturas de Portugal | |
| Construções Gabriel A. S. Couto | Contractor, one lot | Mira Sintra-Meleças to Torres Vedras, consortium member | Infraestruturas de Portugal |
| M. Couto Alves | Contractor, one lot | Mira Sintra-Meleças to Torres Vedras, consortium member | Infraestruturas de Portugal |
| Aldesa | Contractor, one lot | Mira Sintra-Meleças to Torres Vedras, consortium member | Infraestruturas de Portugal |
| Mota-Engil, Tecnovia, Teixeira Duarte, TPF, Convensa | Contractor, one lot | named among the firms of the 2026 repair and supervision contracts; which firm holds which contract not stated | 24notícias |
Milestones
| Date | Milestone | Source |
|---|---|---|
| November 6, 2020 | Mira Sintra-Meleças to Torres Vedras contract signed | Infraestruturas de Portugal |
| December 2026 (planned) | Trains back on Torres Vedras-Caldas da Rainha | 24notícias |
| 2027 (planned) | Runa traction substation in service, electric trains beyond Malveira | 24notícias |
| April 2027 (planned) | Works on Meleças-Torres Vedras to run to April 2027, trains back early 2027 | 24notícias |
About the project
Infraestruturas de Portugal is electrifying and modernising the Linha do Oeste between Mira Sintra-Meleças and Caldas da Rainha, a programme of EUR 155 million. The first works section to Torres Vedras, built by Gabriel Couto, M. Couto Alves and Aldesa under a EUR 61.5 million contract signed in November 2020, adds 16 km of double track and electrifies about 43 km. Trains are expected back on Torres Vedras-Caldas da Rainha at the end of 2026 and on Meleças-Torres Vedras in early 2027; electric trains beyond Malveira wait for the Runa substation, planned for 2027.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Modernização do troço Mira Sintra-Meleças - Torres Vedras, Infraestruturas de Portugal (owner). Consulted 26 Nov 2026.
- Comboios voltam ao Oeste em janeiro após arranjos de 40 milhões, 24notícias (press), 13 Aug 2026. Consulted 26 Nov 2026.