Reviewed record
Hospital de Lisboa Oriental (Todos-os-Santos), Marvila
- Location
- Marvila, Lisboa, Lisbon, Portugal. See it on the map, in 3D
- Stage
- Under construction, as of November 19, 2026 (Saúde+ TV (Lusa)). On 19 November 2026 the Council of Ministers rescheduled the PPP spending and set 1 December 2029 as the date the hospital enters service; works under way after delays that lost 100 million euros of PRR funding.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owners | Portuguese State (Ministério da Saúde), Consortium of Hygeia Edifícios Hospitalares, InfraRed Infrastructure V Investments, Mota-Engil Engenharia e Construção, Mota-Engil Europa and Manvia | |
| Type | Hospitals | |
| Headline amount | EUR 380 million (EUR), as of February 5, 2024 | European Investment Bank |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Beds | 875 beds | inpatient, up to 1,075 in contingency | Quadrante |
| Gross floor area | 180,000 m2 | gross area (Quadrante); Lusa gives about 240,000 m2 | Quadrante |
| Buildings | 3 interconnected buildings | hospital | Quadrante |
| Parking | 2,945 spaces | at least 1,450 underground | Quadrante |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €380 M | Total project cost | construction project cost (EIB) | February 5, 2024 | European Investment Bank |
| €899 M | Budget | maximum PPP contract spending, plus VAT, at current prices (Council of Ministers resolution) | November 19, 2026 | Saúde+ TV (Lusa) |
| €190 M | Loan | EIB maximum contribution; 107 million signed first | February 5, 2024 | European Investment Bank |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Portuguese State (Ministério da Saúde) | Owner | PPP grantor | Saúde+ TV (Lusa) |
| Consortium of Hygeia Edifícios Hospitalares, InfraRed Infrastructure V Investments, Mota-Engil Engenharia e Construção, Mota-Engil Europa and Manvia | Concessionaire | DBFM consortium led by Mota-Engil | Governo de Portugal (XXIII Governo Constitucional) |
| Quadrante | Engineer | structures and foundations, networks, roads and external works, earthworks, traffic, acoustics, heliport | Quadrante |
| European Investment Bank | Lender | European Investment Bank |
Milestones
| Date | Milestone | Source |
|---|---|---|
| July 19, 2022 | Government signs the award of the PPP | Governo de Portugal (XXIII Governo Constitucional) |
| February 2, 2024 | PPP contract signed | ECO |
| October 7, 2024 | Works launched by the health minister (Lusa gives the start of construction as early 2025) | Observador |
| November 19, 2026 | PPP spending rescheduled after the loss of PRR funds | Saúde+ TV (Lusa) |
| December 1, 2029 (planned) | Hospital enters service | Saúde+ TV (Lusa) |
About the project
The Hospital de Lisboa Oriental is a new 875-bed hospital in Marvila, eastern Lisbon, that will replace six old hospitals of the city centre. A consortium led by Mota-Engil designs, builds, finances and maintains the three interconnected buildings under a public-private partnership; construction is put at about 380 million euros. After delays, the government set 1 December 2029 as its opening date.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Assegurado financiamento do novo Hospital Lisboa Oriental após retirada do PRR, Saúde+ TV (Lusa) (press), 19 Nov 2026. Consulted 26 Nov 2026.
- Portugal: EIB supports €380 million project to build new Hospital de Lisboa Oriental, European Investment Bank (lender), 5 Feb 2024. Consulted 26 Nov 2026.
- Hospital Lisboa Oriental (project page), Quadrante (company), Oct 2026. Consulted 26 Nov 2026.
- O que se sabe sobre o novo Hospital de Lisboa Oriental?, ECO (press), 2 Feb 2024. Consulted 26 Nov 2026.
- Novo hospital de Lisboa vai ser conquista assinalável para os utentes, Observador (press), 7 Oct 2024. Consulted 26 Nov 2026.
- Comunicado do Conselho de Ministros de 19 de novembro de 2026, Governo de Portugal (XXV Governo Constitucional) (government), 19 Nov 2026. Consulted 27 Nov 2026.
- Governo adjudica novo Hospital de Lisboa Oriental, Governo de Portugal (XXIII Governo Constitucional) (government), 19 Jul 2022. Consulted 27 Nov 2026.