Hospital Central do Alentejo, Évora

Location
Évora, Alentejo, Portugal. See it on the map, in 3D
Stage
Under construction, as of March 20, 2026 (Governo de Portugal). The government said on 20 March 2026 that the works were about 80% complete, with completion of works in June 2027 and six more months of tests.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerULS do Alentejo Central (formerly ARS Alentejo), Ministério da Saúde
TypeHospitals
Headline amountEUR 237 million (EUR), as of 2025RTP
What it coversTotal project cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Beds351 bedssingle rooms, expandable to 487; plus 30 intensive or intermediate care and 15 palliative bedsObservador (Lusa)
Operating theatres11 theatres3 conventional, 6 ambulatory, 2 emergencySNS
Floors10 floorsbuildingOrdem dos Engenheiros, Região Sul
Footprint1.9 habuilding areaObservador (Lusa)
Parking1,560 spacescar parksImpais
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€237 MTotal project costcurrent estimated cost stated by the health minister, VAT not stated2025RTP
€180 MBudgetconstruction, plus about 30 million of equipment (210 million total)October 22, 2021SNS
€40 MInvestment programmeERDF (FEDER) fundingJanuary 30, 2025Ordem dos Engenheiros, Região Sul
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
ULS do Alentejo Central (formerly ARS Alentejo), Ministério da SaúdeOwnerGoverno de Portugal
AccionaGeneral contractorObservador (Lusa)
Eduardo Souto de MouraArchitectObservador (Lusa)
VHMSupervisionfiscalizaçãoOrdem dos Engenheiros, Região Sul
ImpaisSupplierwaterproofing (27,893 m2) and insulation (24,027 m2)Impais
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
July 30, 2021Works consigned by ARS Alentejo to AccionaObservador (Lusa)
October 22, 2021Works under way with site preparationSNS
March 20, 2026About 80% completeGoverno de Portugal
June 2027 (planned)End of works, then six months of testsGoverno de Portugal
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

Acciona is building the new Hospital Central do Alentejo on the edge of Évora, designed by the architect Eduardo Souto de Moura, with 351 beds in single rooms that can rise to 487 and 11 operating theatres. Works were consigned in July 2021 and were about 80% complete in March 2026. The health minister put the cost at about 237 million euros, 58% above the 2008 plan; works are due to finish in June 2027.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.