Reviewed record

Sines Terminal XXI container terminal expansion, phase 3

Location
Sines, Setúbal district, Alentejo, Portugal. See it on the map, in 3D
Stage
Partly in service, partly under construction, as of July 1, 2022 (Rádio Sines). PSA Sines inaugurated stage 1 of phase 3 (204 m of quay) on 1 July 2022. No source read here confirms works on the later stages.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnersAPS, Administração dos Portos de Sines e do Algarve, PSA Sines
TypePorts
Headline amountEUR 300 million (EUR), as of July 1, 2022ECO
What it coversAnnounced investment. Not to be read as a construction cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Quay front final1,750 mterminal at completion of phase 3Rádio Sines
Quay front agreement1,950 m2019 agreement: 1,750 m plus 200 mGoverno de Portugal
First stage quay204 mstage 1, opened 2022Rádio Sines
Yard area60 hafinal, from 42 haGoverno de Portugal
Capacity4.1 million TEU/yearfinal installed capacity, from 2.3Governo de Portugal
Quay cranes19 cranesfinalECO
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€547 MAnnounced investmentglobal private investment of the 2019 expansion agreementJuly 18, 2019Governo de Portugal
€300 MAnnounced investmentphase 3 investment stated by PSA SinesJuly 1, 2022ECO
€17 MContract valuefirst stage works, 204 m of quayNovember 20, 2020Postal do Algarve
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
APS, Administração dos Portos de Sines e do AlgarveOwnergrantor of the concessionGoverno de Portugal
PSA SinesConcessionaireterminal operator and works clientGoverno de Portugal
Mota-Engil, Engenharia e Construção, S.A.General contractorfirst stage (204 m of quay), with EtermarPostal do Algarve
Etermar, Engenharia e Construção, S.A.General contractorfirst stage, with Mota-EngilPostal do Algarve
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
July 18, 2019Agreement between the State and PSA Sines for the phase 3 expansionGoverno de Portugal
November 20, 2020First stage awarded to Mota-Engil and EtermarPostal do Algarve
January 2021First stage works startECO
July 1, 2022Stage 1 of phase 3 inaugurated: continuous quay of 1,150 mRádio Sines
2028 (planned)Completion of phase 3 announced by PSA SinesECO
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

PSA Sines is expanding Terminal XXI, the container terminal of the Port of Sines, under a 2019 concession agreement with the State. The plan takes the quay to 1,750 m, the yards to 60 ha and capacity to 4.1 million TEU, with 19 quay cranes. A first 204 m of quay built by Mota-Engil and Etermar opened in July 2022; completion of phase 3 was announced for 2028.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.