New port of Lajes das Flores
- Location
- Lajes das Flores, Flores Island, Azores, Portugal. See it on the map, in 3D
- Stage
- Under construction, as of October 2026 (Jornal Açores 9 (Governo dos Açores release)). The Azores government said on 29 October 2026 that EUR 42.7 million had been spent on the works, which were consigned on 17 April 2025.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Portos dos Açores, S.A. | |
| Type | Ports | |
| Headline amount | EUR 191.5 million (EUR), as of October 29, 2026 | Jornal Açores 9 (Governo dos Açores release) |
| What it covers | Budget. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Breakwater quay length | 540 m | new breakwater-quay | Tecnovia |
| Berthing front | 170 m | commercial quay | Tecnovia |
| Quay depth | -9 m (ZH) | commercial quay | Tecnovia |
| Curtain wall reinforcement | 145 m | existing curtain wall | Tecnovia |
| Platform width | 40 m | quay platform | Tecnovia |
| Antifer blocks | 8,222 blocks | armour layer | Tecnovia |
| Dredging volume | 180,530 m3 | dredging | Tecnovia |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €195 M | Contract value | works contract, excl. VAT | April 2025 | Tecnovia |
| €192 M | Budget | total project budget stated in the regional government's progress release | October 29, 2026 | Jornal Açores 9 (Governo dos Açores release) |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Portos dos Açores, S.A. | Owner | proponent and licensing entity | Direção Regional do Ambiente e Ação Climática (Açores) |
| Tecnovia Açores, Sociedade de Construções S.A. | General contractor | consortium leader, 35.5% | Tecnovia |
| Etermar, Engenharia e Construção S.A. | General contractor | consortium member, 34.5% | Tecnovia |
| Teixeira Duarte, Engenharia e Construções S.A. | General contractor | consortium member, 20% | Tecnovia |
| Marques S.A. | General contractor | consortium member, 10% | Tecnovia |
| Morim de Oliveira, Engenharia Civil | Designer | with MSW | Tecnovia |
| MSW, Estudos e Projetos de Obras Marítimas, Lda. | Designer | with Morim de Oliveira | Tecnovia |
| NRV, Norvia | Designer | wave agitation studies, physical model specifications, execution design, technical assistance | NRV Norvia |
| H2Arquitectos | Architect | named among the authors of the project's construction waste plan (2023) with Morim de Oliveira, MSW and NRV | Direção Regional do Ambiente e Ação Climática (Açores) |
| LNEC, Laboratório Nacional de Engenharia Civil | Engineer | 3D physical model tests at 1:58.9 | LNEC |
Milestones
| Date | Milestone | Source |
|---|---|---|
| August 29, 2024 | Regional environment directorate decides the project is not subject to environmental impact assessment | Direção Regional do Ambiente e Ação Climática (Açores) |
| April 17, 2025 | Works consigned to the Tecnovia Açores consortium | Tecnovia |
| May 19, 2025 | Groundbreaking ceremony | Tecnovia |
| October 29, 2026 | EUR 42.7 million spent by the end of Q2 2026 | Jornal Açores 9 (Governo dos Açores release) |
| April 2030 (planned) | End of the 60-month execution period | Jornal Açores 9 (Governo dos Açores release) |
About the project
Portos dos Açores is rebuilding the commercial port of Lajes das Flores, wrecked by Hurricane Lorenzo in 2019 and storm Efraim in 2022. A consortium led by Tecnovia Açores with Etermar, Teixeira Duarte and Marques builds a 540 m breakwater-quay armoured with Antifer blocks, a 170 m quay at -9 m and a new passenger terminal. Works were consigned in April 2025 for 60 months.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Tecnovia Açores leads the construction of the Azores' largest maritime-port investment: the New Port of Lajes das Flores, Tecnovia (company), Jun 2025. Consulted 26 Nov 2026.
- Decisão de não sujeição a AIA: Empreitada de reconstrução do Porto das Lajes das Flores, Direção Regional do Ambiente e Ação Climática (Açores) (government), 29 Aug 2024. Consulted 26 Nov 2026.
- Investidos 42,7 ME na construção do novo porto das Lajes das Flores, Jornal Açores 9 (Governo dos Açores release) (press), 29 Oct 2026. Consulted 26 Nov 2026.
- Porto das Lajes das Flores, NRV Norvia (company). Consulted 26 Nov 2026.
- Novo Porto das Lajes das Flores: ensaios de estabilidade, galgamentos e pressões, LNEC (state news agency (map)). Consulted 26 Nov 2026.
- Ficha de projeto Sustentável 2030 (FLW), Portos dos Açores (owner), Feb 2025. Consulted 26 Nov 2026.