Reviewed record

Valencia North expansion: container quay and reclamation works

Location
València, Valencian Community, Spain. See it on the map, in 3D
Stage
Under construction, as of November 3, 2026 (Diario del Puerto). On 3 November 2026 the filling and the berthing line were reported well advanced; the works were reported 8 to 12 months behind the contract programme in July 2026.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerAutoridad Portuaria de València
TypePorts
Headline amountEUR 656.7 million (EUR), as of September 19, 2024Tribunal Administrativo Central de Recursos Contractuales
What it coversBudget.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Main quay length2 kmmain quay wallEuropean Investment Bank
Ancillary quays700 mancillary quaysEuropean Investment Bank
Paved area126 hanew paved terminal areas (Acciona); EIB gives 137 ha of reclamationAcciona
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€592 MContract valueaward amount reported by Valencia Plaza; VAT treatment not stated (equals 489 million plus 21% VAT)July 1, 2024Valencia Plaza
€489 MContract valuecontract value stated by Acciona, VAT not statedJuly 2024Acciona
€657 MBudgetestimated value of the tender (valor estimado, excl. VAT)September 19, 2024Tribunal Administrativo Central de Recursos Contractuales
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Autoridad Portuaria de ValènciaOwnerTribunal Administrativo Central de Recursos Contractuales
Acciona Construcción S.A.General contractorUTE leader; shares not publishedAcciona
Jan De Nul NVGeneral contractorUTE memberAcciona
Grupo Bertolín S.A.U.General contractorUTE memberAcciona
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
July 1, 2024Award by the Port Authority boardValencia Plaza
September 19, 2024TACRC dismisses the appeal by the Dragados-Rover joint ventureTribunal Administrativo Central de Recursos Contractuales
December 13, 2024First marine plant arrives, dredging beginsValencia Plaza
July 30, 2026Works reported 8 to 12 months behind programmeThe Objective
November 3, 2026Filling and berthing line well advancedDiario del Puerto
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

This is the Port Authority of Valencia's works contract for the North Terminal: the main quay, the ancillary quays and about 137 ha of reclaimed land. A joint venture of Acciona, Jan De Nul and Grupo Bertolín won it in July 2024; an appeal by a rival bidder was dismissed in September 2024. Caissons are cast in the floating dock Kugira; a first section of about 1 km of quay was due in autumn 2026.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.