Pisão dam and Crato multi-purpose hydraulic scheme

Location
Crato, Portalegre district, Alentejo, Portugal. See it on the map, in 3D
Stage
Under construction, as of September 24, 2025 (Agroportal (Lusa)). Works on the dam began about two weeks before the official visit reported on 24 September 2025.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerCIMAA, Comunidade Intermunicipal do Alto Alentejo
TypeDams and hydro
Headline amountEUR 222 million (EUR), as of September 24, 2025Agroportal (Lusa)
What it coversTotal project cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Dam height54 mmaximum height above foundationAgroportal (Lusa)
Crest length1,350 mtotal crest lengthAgroportal (Lusa)
Reservoir area726 haflooded areaAmbiente Online
Reservoir volume116.2 hm3total storageAmbiente Online
Full supply level248 mNPA (full supply level)Ambiente Online
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€222 MTotal project costglobal investment in the schemeSeptember 24, 2025Agroportal (Lusa)
€65 MContract valueprimary infrastructure works contract, VAT not statedOctober 8, 2024ECO
€141 MInvestment programmePRR funding, plus 10 million from the State BudgetOctober 9, 2024ECO
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
CIMAA, Comunidade Intermunicipal do Alto AlentejoOwnerapproved the award on 8 October 2024ECO
FCC ConstrucciónGeneral contractorconsortium with Alberto Couto AlvesECO
Alberto Couto AlvesGeneral contractorconsortium with FCC ConstrucciónECO
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
October 8, 2024CIMAA approves the award to FCC and Alberto Couto AlvesECO
September 2025Dam works beginAgroportal (Lusa)
December 2026 (planned)End of construction in the schedule submitted to the European CommissionECO
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

The Alto Alentejo intermunicipal community (CIMAA) is building the Pisão dam near Crato, a zoned earthfill dam 54 m high and about 1,350 m long that will create a 726 ha reservoir for irrigation, water supply and power. The village of Pisão will be submerged and rebuilt. FCC Construcción and Alberto Couto Alves won the primary works for 64.99 million euros; works began in September 2025 and the whole scheme is put at 222 million euros.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.