Reviewed record
Raising of the Yesa dam and reservoir
- Location
- Yesa (Navarra); Sigüés, Artieda, Mianos, Undués de Lerda, Urriés, Los Pintanos and Salvatierra de Esca (Zaragoza), Navarre / Aragon, Spain. See it on the map, in 3D
- Stage
- Under construction, as of May 19, 2026 (Noticias de Navarra). The works began in 2001 and have not been completed; in May 2026 the opposing Asociación Río Aragón said they had been practically stopped for more than three years, and modification no. 4 was still pending.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Ministerio para la Transición Ecológica (Dirección General del Agua) / Confederación Hidrográfica del Ebro | |
| Type | Dams and hydro | |
| Headline amount | EUR 500 million (EUR), as of May 19, 2026 | Noticias de Navarra |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Dam height | 108 m | new embankment dam, 30 m above the existing crest | BOE (Secretaría de Estado de Cambio Climático) |
| Crest elevation | 520 m a.s.l. | new dam | BOE (Secretaría de Estado de Cambio Climático) |
| Crest length | 430 m | new dam | BOE (Secretaría de Estado de Cambio Climático) |
| Reservoir | 1,079 hm3 | at normal maximum level 511 m (existing 470 hm3 at 488 m) | BOE (Secretaría de Estado de Cambio Climático) |
| Reservoir area | 3,584 ha | at normal maximum level | BOE (Secretaría de Estado de Cambio Climático) |
| Dam volume | 3,377,440 m3 | total dam body | BOE (Secretaría de Estado de Cambio Climático) |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €113 M | Budget | initial budget, as stated by the Asociación Río Aragón | 2001 | Noticias de Navarra |
| €255 M | Budget | total current budget of the raising with price revision and VAT (CHE, April 2013) | April 5, 2013 | iAgua (CHE visit) |
| €500 M | Total project cost | current estimate cited by the opposing Asociación Río Aragón | May 19, 2026 | Noticias de Navarra |
| €10 M | Budget | additional amount from updating measurements under modification no. 4 (Government answer) | June 23, 2025 | Noticias de Navarra |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Ministerio para la Transición Ecológica (Dirección General del Agua) / Confederación Hidrográfica del Ebro | Owner | BOE (Secretaría de Estado de Cambio Climático) | |
| ACS | General contractor | UTE with Ferrovial and FCC | Noticias de Navarra |
| Ferrovial | General contractor | UTE member | Noticias de Navarra |
| FCC | General contractor | UTE member | Noticias de Navarra |
Milestones
| Date | Milestone | Source |
|---|---|---|
| May 18, 2001 | First stone laid by the environment minister | Noticias de Navarra |
| August 4, 2010 | Environmental impact statement for modification no. 3 (normal level lowered from 521 to 511 m) | BOE (Secretaría de Estado de Cambio Climático) |
| April 5, 2013 | 106.7 million of 255.2 million invested | iAgua (CHE visit) |
| March 10, 2025 | Irrigators report completion moved to 2029; modification no. 4 about to go to the Consejo de Estado | Noticias de Navarra |
| 2029 (planned) | Completion date reported by the irrigators' communities | Noticias de Navarra |
About the project
The State is raising the Yesa dam on the río Aragón, between Navarra and Aragón, to more than double its reservoir from 470 to 1,079 hm3 for the Bardenas irrigation area and Zaragoza's water supply. A joint venture of ACS, Ferrovial and FCC began the works in 2001; instability of the right-hand slope has delayed them for years and a fourth project modification is pending. Official completion has moved to 2029 or later.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Río Aragón exige poner fin al recrecimiento de Yesa, Noticias de Navarra (press), 19 May 2026. Consulted 26 Nov 2026.
- El Gobierno central desliga el recrecimiento de Yesa y evita dar cifras, Noticias de Navarra (press), 23 Jun 2025. Consulted 26 Nov 2026.
- Resolución de 4 de agosto de 2010, declaración de impacto ambiental de la Modificación n.º 3 del proyecto de recrecimiento del embalse de Yesa (BOE-A-2010-13154), BOE (Secretaría de Estado de Cambio Climático) (government), 4 Aug 2010. Consulted 26 Nov 2026.
- El presidente de la Confederación del Ebro y miembros del Parlamento navarro visitan las obras, iAgua (CHE visit) (press), 5 Apr 2013. Consulted 26 Nov 2026.
- El Ministerio dice que no contempla un escenario en el que no se recrezca Yesa, Noticias de Navarra (press), 10 Mar 2025. Consulted 26 Nov 2026.