Reviewed record

Jaca bypass linking the A-21 and A-23 motorways

Location
Jaca, Huesca, Aragon, Spain. See it on the map, in 3D
Stage
Contract awarded, works not confirmed, as of August 7, 2026 (Nevasport). The Ministry awarded the works on 7 August 2026 to Sacyr and Papsa Infraestructuras; the supervision contract was formalised in August 2026. No start of works found.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerMinisterio de Transportes y Movilidad Sostenible, Dirección General de Carreteras
TypeHighways
Headline amountEUR 153.6 million (EUR), as of December 2025Delegación del Gobierno en Aragón
What it coversBudget.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Length8.05 kmbypassNevasport
Carriageways2 carriagewaysseparated by a median, 3.5 m lanesNevasport
Junctions3 junctionsJaca Este, Jaca Norte, Jaca OesteHoy Aragón
Viaducts3 viaductsbypassNevasport
Cut and cover tunnel length200 mnear the hospitalNevasport
Overpasses5 overpassesbypassHoy Aragón
Underpasses5 underpassesbypassHoy Aragón
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€135 MContract valueaward incl. VATAugust 7, 2026Nevasport
€154 MBudgettender (December 2025)December 2025Delegación del Gobierno en Aragón
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Ministerio de Transportes y Movilidad Sostenible, Dirección General de CarreterasOwnerBoletín Oficial del Estado
Sacyr and Papsa Infraestructuras (Grupo Romero Polo) (UTE)General contractorShares not statedHoy Aragón
Saitec and Investigación y Control de Calidad (INCOSA) (UTE)SupervisionControl and surveillance, EUR 3,782,249.90, awarded 2026-07-07Boletín Oficial del Estado
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
December 2025Works tenderedDelegación del Gobierno en Aragón
July 7, 2026Supervision contract awarded to Saitec-INCOSABoletín Oficial del Estado
August 7, 2026Works awarded to Sacyr-PapsaHoy Aragón
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

The Jaca bypass is an 8.05 km motorway north of Jaca, Huesca, that will join the A-23 from Sabiñánigo to the A-21 towards Navarre. It has three junctions, three viaducts including one over the river Aragón, and a 200 m cut-and-cover tunnel by the hospital. The Ministry awarded it in August 2026 to Sacyr and Papsa Infraestructuras for EUR 135.3 million including VAT; works had not been reported started.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.

Sources

See it on the map. How the map is made.