Reviewed record

A-23 Autovía Mudéjar: Sabiñánigo bypass (Sabiñánigo Este to Sabiñánigo Oeste)

Location
Sabiñánigo, Huesca, Aragon, Spain. See it on the map, in 3D
Stage
Suspended, as of October 17, 2026 (Delegación del Gobierno en Aragón). The Government said in April 2026 that the contractor halted the works unilaterally in winter 2025-26 with about 2% left and refused to sign the continuation under a third modification; in October 2026 the works were still stopped at 98% executed.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerMinisterio de Transportes y Movilidad Sostenible, Dirección General de Carreteras
TypeHighways
Headline amountEUR 108.4 million (EUR), as of April 21, 2026Delegación del Gobierno en Aragón
What it coversBudget.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Length8.6 kmsectionAragón Noticias (CARTV)
Lanes2 lanes each way3.5 m lanesAragón Noticias (CARTV)
Junctions3 junctionssectionAragón Noticias (CARTV)
Progress98 %execution when haltedMoncloa.com
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€59 MContract valueselected offer (BOE), excl. VATSeptember 25, 2019Boletín Oficial del Estado
€76 MBudgetestimated tender value, excl. VAT (40 months)June 1, 2019Boletín Oficial del Estado
€98 MBudgetinvestment as reported in November 2024November 21, 2024Aragón Noticias (CARTV)
€108 MBudgetcurrent budget of the worksApril 21, 2026Delegación del Gobierno en Aragón
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Ministerio de Transportes y Movilidad Sostenible, Dirección General de CarreterasOwnerBoletín Oficial del Estado
Aldesa Construcciones and Rover Infraestructuras (UTE)General contractorShares not stated; 21 bidsBoletín Oficial del Estado
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
September 25, 2019Works awarded to Aldesa-RoverBoletín Oficial del Estado
November 21, 2024More than 82% executedAragón Noticias (CARTV)
April 11, 2025Minister visits the viaduct, about 80% completeEl Pirineo Aragonés
November 2025Contractor halts the worksDelegación del Gobierno en Aragón
October 17, 2026Works still halted at 98%Moncloa.com
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

The Sabiñánigo bypass is an 8.6 km section of the A-23 in Huesca with three junctions and a 934 m viaduct over the Gállego and Aurín rivers, up to 50 m high, built with 90 m spans. Aldesa and Rover won it in 2019 for EUR 58.6 million excluding VAT; its current budget is EUR 108.36 million. The contractor stopped work in winter 2025-26 with about 2% left, and the works were still halted in October 2026.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.