Reviewed record
A-11 Autovía del Duero: Quintanilla de Arriba (west) to Olivares de Duero
- Location
- Quintanilla de Arriba, Valbuena de Duero and Olivares de Duero, Valladolid, Castile and León, Spain. See it on the map, in 3D
- Stage
- Partly in service, partly under construction, as of August 24, 2026 (elDiario.es Castilla y León). The Minister opened the stretch from the San Bernardo junction to Olivares on 24 August 2026; the Duero viaduct and works towards Quintanilla de Arriba continue, with completion forecast for the first half of 2027.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Ministerio de Transportes y Movilidad Sostenible, Dirección General de Carreteras | |
| Type | Highways | |
| Headline amount | EUR 233 million (EUR), as of August 2026 | El Día de Valladolid |
| What it covers | Budget. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Length | 14.5 km | section | elDiario.es Castilla y León |
| Viaduct length | 500 m | viaduct over the Duero at Quintanilla de Arriba | El Día de Valladolid |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €81 M | Contract value | selected offer (BOE), excl. VAT; 97.99M incl. VAT | July 31, 2020 | Boletín Oficial del Estado |
| €112 M | Budget | estimated tender value, excl. VAT | July 23, 2019 | Boletín Oficial del Estado |
| €233 M | Budget | total of the two sections Tudela-Olivares and Olivares-Quintanilla | August 2026 | El Día de Valladolid |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Ministerio de Transportes y Movilidad Sostenible, Dirección General de Carreteras | Owner | Boletín Oficial del Estado | |
| UTE A11 Quintanilla-Olivares | General contractor | Member companies not named in sources read; 20 bids | Boletín Oficial del Estado |
Milestones
| Date | Milestone | Source |
|---|---|---|
| July 31, 2020 | Works awarded | Boletín Oficial del Estado |
| October 28, 2020 | Works begin | Diario de Valladolid |
| August 24, 2026 | San Bernardo-Olivares stretch opens | elDiario.es Castilla y León |
| June 2027 (planned) | Whole Quintanilla-Tudela open (first half 2027) | elDiario.es Castilla y León |
About the project
This 14.5 km section of the A-11 runs through the Ribera del Duero between Quintanilla de Arriba and Olivares de Duero, including a viaduct of about 500 m over the Duero. It was awarded in July 2020 to the UTE A11 Quintanilla-Olivares for EUR 80.98 million excluding VAT and started in October 2020. The part from the San Bernardo junction opened in August 2026; the Ministry expects to finish the viaduct and the rest in the first half of 2027.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Formalización: Autovía A-11, Tramo Quintanilla de Arriba (oeste)-Olivares del Duero (BOE-B-2020-34928), Boletín Oficial del Estado (government), 13 Oct 2020. Consulted 26 Nov 2026.
- Licitación: Autovía A-11, Tramo Quintanilla de Arriba (oeste)-Olivares del Duero (BOE-B-2019-32724), Boletín Oficial del Estado (government), 23 Jul 2019. Consulted 26 Nov 2026.
- La A-11 estrena 56 kilómetros en Valladolid y deja para 2027 el cierre del trazado hasta Quintanilla de Arriba, elDiario.es Castilla y León (press), 24 Aug 2026. Consulted 26 Nov 2026.
- 31 km más de la A-11 desde el lunes entre Tudela y Quintanilla, El Día de Valladolid (press), Aug 2026. Consulted 26 Nov 2026.
- El viaducto de la A-11 en Quintanilla (Valladolid), a punto de cruzar el Duero, Diario de Valladolid (press), 28 Feb 2026. Consulted 26 Nov 2026.