Reviewed record

A-68 Arrúbal to Navarrete (Ronda Sur de Logroño)

Location
Arrúbal, Agoncillo, Murillo de Río Leza, Logroño, Villamediana de Iregua, Lardero, Navarrete, La Rioja, La Rioja, Spain. See it on the map, in 3D
Stage
Partly in service, partly under construction, as of November 11, 2026 (Nuevecuatrouno). On 11 November 2026 the Government Delegation confirmed three of the six planned junctions open in both directions (Arrúbal, Villamediana and Fuenmayor/Navarrete); Lardero is expected at the end of 2026, Recajo and Agoncillo have no date.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerMinisterio de Transportes y Movilidad Sostenible, Dirección General de Carreteras
TypeHighways
Headline amountEUR 123.4 million (EUR), as of January 11, 2019Boletín Oficial del Estado
What it coversBudget.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Length29 kmArrúbal-NavarreteNuevecuatrouno
Junctions8 junctionsof which five newNuevecuatrouno
Traffic forecast40,000 vehicles per dayVillamediana de Iregua junctionNuevecuatrouno
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€112 MContract valueaward, incl. taxesSeptember 11, 2019Nuevecuatrouno
€149 MBudgettender base budget (incl. VAT)January 2019Nuevecuatrouno
€123 MBudgetestimated contract value, excl. VAT (BOE tender notice)January 11, 2019Boletín Oficial del Estado
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Ministerio de Transportes y Movilidad Sostenible, Dirección General de CarreterasOwnerBoletín Oficial del Estado
Acciona Construcción and Aquaterra (UTE Variante Logroño)General contractorShares not statedNuevecuatrouno
Técnica y Proyectos, S.A. (Typsa)SupervisionControl and surveillance of the works, awarded 2019-09-05 for EUR 1,495,082.98Boletín Oficial del Estado
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
September 11, 2019Works awarded to Acciona-AquaterraNuevecuatrouno
November 5, 2019Works begin in NavarreteNuevecuatrouno
February 13, 2026Over 90% executedNuevecuatrouno
November 11, 2026AP-68 toll-free; Arrúbal, Villamediana and Fuenmayor junctions openNuevecuatrouno
December 2026 (planned)Lardero junction openingNuevecuatrouno
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

The Ministry of Transport has turned about 29 km of the former AP-68 toll motorway between Arrúbal and Navarrete into a free southern ring road for Logroño, with eight junctions, five of them new. Acciona and Aquaterra won the works in 2019 for EUR 111.8 million and started in November 2019. The road became toll-free on 11 November 2026 and three of the new junctions opened that day; Lardero is due at the end of 2026.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.

Sources

See it on the map. How the map is made.