Reviewed record

Navarra high-speed corridor: Tafalla-Campanas section

Location
Tafalla to Campanas (Tiebas-Muruarte de Reta), Navarra, Navarre, Spain. See it on the map, in 3D
Stage
Under construction, as of June 2025 (OKDiario Navarra). In June 2025 Adif reported the Artzareta tunnel excavated, the Catedral tunnel at 41% of its excavation and 60% of the cuttings done.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerAdif Alta Velocidad
TypeRail
Headline amountEUR 270.9 million (EUR), as of July 2023BOE
What it coversBudget.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Length15 kmsectionOKDiario Navarra
Municipalities7sectionOKDiario Navarra
Existing line relocated3.5 kmnear CampanasSystra
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€271 MBudgettender estimated value, excl. VAT, 30 monthsJuly 2023BOE
€238 MContract valueaward, VAT not statedNovember 2023Gobierno de Navarra
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Adif Alta VelocidadOwnerBOE
S.A. de Obras y Servicios CopasaGeneral contractorUTE Tafalla Campanas, 28.34%OKDiario Navarra
Puentes y Calzadas InfraestructurasGeneral contractorUTE Tafalla Campanas, 28.33%OKDiario Navarra
Constructora San JoséGeneral contractorUTE Tafalla Campanas, 28.33%OKDiario Navarra
Lurpelan TunnellingGeneral contractorUTE Tafalla Campanas, 15.00%OKDiario Navarra
SystraSupervisionworks controlSystra
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
July 12, 2023Works tender published in the BOEBOE
November 2023Works awardedGobierno de Navarra
March 22, 2024First tunnel holed through (both portals connected)Gobierno de Navarra
June 10, 2025Artzareta tunnel excavated, Catedral tunnel 41%, 60% of cuttings doneOKDiario Navarra
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

A 15 km section of the Navarra high-speed corridor between Tafalla and Campanas, south of Pamplona, through seven municipalities. It includes three tunnels and a 546 m viaduct over the Arroyo de La Majada. The joint venture of Copasa, Puentes y Calzadas, Constructora San José and Lurpelan Tunnelling won it in November 2023 for about EUR 238 million, with 30 months of works. By June 2025 the Artzareta tunnel was excavated and the Catedral tunnel was 41% excavated.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.