Reviewed record
Bilbao southern rail bypass, phase 1: Serantes connection section
- Location
- Ortuella, Bizkaia, Basque Country, Spain. See it on the map, in 3D
- Stage
- Under construction, as of July 30, 2026 (Gobierno Vasco (euskadi.eus)). Contract signed on 16 June 2025; the Basque Government said in July 2026 that the section was under works.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Euskal Trenbide Sarea (ETS) | |
| Type | Rail | |
| Headline amount | EUR 107.6 million (EUR), as of 2025 | Gobierno Vasco, contracting portal |
| What it covers | Budget. |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €100 M | Contract value | award, excl. VAT | April 16, 2025 | Gobierno Vasco, contracting portal |
| €122 M | Contract value | award, incl. VAT | April 16, 2025 | Gobierno Vasco, contracting portal |
| €108 M | Budget | tender budget, excl. VAT | 2025 | Gobierno Vasco, contracting portal |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Euskal Trenbide Sarea (ETS) | Owner | contracting authority for the Ministry of Transport | Gobierno Vasco, contracting portal |
| COMSA | General contractor | UTE COMSA-AZVI-IZA-CAMPEZO, share not stated | Gobierno Vasco, contracting portal |
| Azvi | General contractor | UTE member | Gobierno Vasco, contracting portal |
| Iza Obras y Promociones | General contractor | UTE member | Gobierno Vasco, contracting portal |
| Campezo Obras y Servicios | General contractor | UTE member | Gobierno Vasco, contracting portal |
Milestones
| Date | Milestone | Source |
|---|---|---|
| April 16, 2025 | Contract awarded to UTE COMSA-AZVI-IZA-CAMPEZO | Gobierno Vasco, contracting portal |
| June 16, 2025 | Contract signed | Gobierno Vasco, contracting portal |
| July 30, 2026 | Section reported under works | Gobierno Vasco (euskadi.eus) |
About the project
The Serantes connection is the first section of the Bilbao southern rail bypass, in Ortuella: it joins the existing Serantes tunnel, which brings port freight trains from the Port of Bilbao, to the new tunnel of the bypass. Euskal Trenbide Sarea awarded it in April 2025 to a joint venture of COMSA, Azvi, Iza and Campezo for EUR 100.5 million excluding VAT, signed the contract in June 2025 and set 38 months of works.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Obra del proyecto constructivo de la variante sur ferroviaria de Bilbao. Fase 1. Tramo: Conexión Serantes, Gobierno Vasco, contracting portal (government), 23 Jul 2025. Consulted 26 Nov 2026.
- Euskal Trenbide Sarea licita las obras del tercer tramo de la Variante Sur Ferroviaria, Gobierno Vasco (euskadi.eus) (government), 30 Jul 2026. Consulted 26 Nov 2026.
- Estudio informativo de la Variante Sur Ferroviaria de Bilbao. Fase 1. Variante de Ortuella, memoria, Ministerio de Transportes y Movilidad Sostenible (government), Sep 2021. Consulted 26 Nov 2026.