Reviewed record

Bay of Biscay Spain-France HVDC interconnection

Location
Gatika and Lemoiz, Bizkaia; Cubnezais, Le Porge, Seignosse and Capbreton, France, Basque Country, Spain and France. See it on the map, in 3D
Stage
Under construction, as of August 3, 2026 (Red Eléctrica). Red Eléctrica said on 3 August 2026 that the interconnection was 60% executed overall and that submarine cable laying had begun from Lemoiz.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnersInelfe, Red Eléctrica de España, RTE
TypeEnergy
Headline amountEUR 3.129 billion (EUR), as of June 13, 2025European Investment Bank
What it coversTotal project cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Exchange capacity5,000 MWSpain-France, from 2,800 MWRed Eléctrica
Link capacity2,000 MWtwo HVDC links of 1,000 MWRed Eléctrica
Dc voltage400 kVlinksRed Eléctrica
Route length400 kmdouble circuit, of which 300 km submarineRed Eléctrica / RTE
Submarine section276 kmsubmarine routeRed Eléctrica
Intermediate land section27 kmunderground in France around the Capbreton canyonRed Eléctrica
Submarine cables4 cablesplus fibre opticRed Eléctrica
Max laying depth140 mseabed depth reached by NKT VictoriaRed Eléctrica
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€2.85 bnBudgetproject budget, plus a 250 million risk provisionMarch 10, 2023Red Eléctrica
€3.13 bnTotal project costEIB estimateJune 13, 2025European Investment Bank
€1.6 bnLoanEIB loans (1.5 billion signed by June 2025, a further 300 million signed July 2026 per the EIB page)July 2026European Investment Bank
€578 MInvestment programmeEU CEF grantMarch 10, 2023Red Eléctrica
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
InelfeOwner50% Red Eléctrica, 50% RTERed Eléctrica / RTE
Red Eléctrica de EspañaOwner50% of Inelfe; executes the Spanish sideRed Eléctrica
RTEOwner50% of InelfeRed Eléctrica / RTE
Hitachi Energy / VINCI consortiumGeneral contractorconverter stations at Gatika and CubnezaisRed Eléctrica / RTE
NKT HV CablesSuppliersubmarine cables, laid with the cable ship NKT Victoria (first 65 km off the Basque coast)Red Eléctrica
Prysmian PowerlinkSuppliersubmarine cablesRed Eléctrica / RTE
FASSET consortiumContractor, one lotunderground cablesRed Eléctrica / RTE
European Investment BankLenderEuropean Investment Bank
CINEA (European Commission)LenderCEF grantRed Eléctrica
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
2023Works beginRed Eléctrica / RTE
March 10, 2023Inelfe awards the main contractsRed Eléctrica
May 16, 2025First stone of the Cubnezais converter stationRed Eléctrica / RTE
June 13, 2025EIB loans signedEuropean Investment Bank
May 28, 202680% of the land sections executedRed Eléctrica
July 14, 2026Seven 315 t transformers moved from the Port of Bilbao to Gatika (July to October)Red Eléctrica
August 3, 2026Submarine cable laying starts from Lemoiz; project 60% executedRed Eléctrica
undefined 2027 (planned)End of the marine campaignsRed Eléctrica
2028 (planned)CommissioningRed Eléctrica / RTE
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

Inelfe, owned equally by Red Eléctrica and RTE, is building two underground and submarine direct-current links between Gatika near Bilbao and Cubnezais near Bordeaux. They will raise the exchange capacity between Spain and France from 2,800 to 5,000 MW. Hitachi Energy and VINCI build the two converter stations, NKT and Prysmian supply and lay the cables. Works began in 2023, were 60% done in August 2026 and commissioning is planned for 2028.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.