Reviewed record
Bay of Biscay Spain-France HVDC interconnection
- Location
- Gatika and Lemoiz, Bizkaia; Cubnezais, Le Porge, Seignosse and Capbreton, France, Basque Country, Spain and France. See it on the map, in 3D
- Stage
- Under construction, as of August 3, 2026 (Red Eléctrica). Red Eléctrica said on 3 August 2026 that the interconnection was 60% executed overall and that submarine cable laying had begun from Lemoiz.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owners | Inelfe, Red Eléctrica de España, RTE | |
| Type | Energy | |
| Headline amount | EUR 3.129 billion (EUR), as of June 13, 2025 | European Investment Bank |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Exchange capacity | 5,000 MW | Spain-France, from 2,800 MW | Red Eléctrica |
| Link capacity | 2,000 MW | two HVDC links of 1,000 MW | Red Eléctrica |
| Dc voltage | 400 kV | links | Red Eléctrica |
| Route length | 400 km | double circuit, of which 300 km submarine | Red Eléctrica / RTE |
| Submarine section | 276 km | submarine route | Red Eléctrica |
| Intermediate land section | 27 km | underground in France around the Capbreton canyon | Red Eléctrica |
| Submarine cables | 4 cables | plus fibre optic | Red Eléctrica |
| Max laying depth | 140 m | seabed depth reached by NKT Victoria | Red Eléctrica |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €2.85 bn | Budget | project budget, plus a 250 million risk provision | March 10, 2023 | Red Eléctrica |
| €3.13 bn | Total project cost | EIB estimate | June 13, 2025 | European Investment Bank |
| €1.6 bn | Loan | EIB loans (1.5 billion signed by June 2025, a further 300 million signed July 2026 per the EIB page) | July 2026 | European Investment Bank |
| €578 M | Investment programme | EU CEF grant | March 10, 2023 | Red Eléctrica |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Inelfe | Owner | 50% Red Eléctrica, 50% RTE | Red Eléctrica / RTE |
| Red Eléctrica de España | Owner | 50% of Inelfe; executes the Spanish side | Red Eléctrica |
| RTE | Owner | 50% of Inelfe | Red Eléctrica / RTE |
| Hitachi Energy / VINCI consortium | General contractor | converter stations at Gatika and Cubnezais | Red Eléctrica / RTE |
| NKT HV Cables | Supplier | submarine cables, laid with the cable ship NKT Victoria (first 65 km off the Basque coast) | Red Eléctrica |
| Prysmian Powerlink | Supplier | submarine cables | Red Eléctrica / RTE |
| FASSET consortium | Contractor, one lot | underground cables | Red Eléctrica / RTE |
| European Investment Bank | Lender | European Investment Bank | |
| CINEA (European Commission) | Lender | CEF grant | Red Eléctrica |
Milestones
| Date | Milestone | Source |
|---|---|---|
| 2023 | Works begin | Red Eléctrica / RTE |
| March 10, 2023 | Inelfe awards the main contracts | Red Eléctrica |
| May 16, 2025 | First stone of the Cubnezais converter station | Red Eléctrica / RTE |
| June 13, 2025 | EIB loans signed | European Investment Bank |
| May 28, 2026 | 80% of the land sections executed | Red Eléctrica |
| July 14, 2026 | Seven 315 t transformers moved from the Port of Bilbao to Gatika (July to October) | Red Eléctrica |
| August 3, 2026 | Submarine cable laying starts from Lemoiz; project 60% executed | Red Eléctrica |
| undefined 2027 (planned) | End of the marine campaigns | Red Eléctrica |
| 2028 (planned) | Commissioning | Red Eléctrica / RTE |
About the project
Inelfe, owned equally by Red Eléctrica and RTE, is building two underground and submarine direct-current links between Gatika near Bilbao and Cubnezais near Bordeaux. They will raise the exchange capacity between Spain and France from 2,800 to 5,000 MW. Hitachi Energy and VINCI build the two converter stations, NKT and Prysmian supply and lay the cables. Works began in 2023, were 60% done in August 2026 and commissioning is planned for 2028.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Red Eléctrica inicia el tendido del cable submarino de la interconexión con Francia por el Golfo de Bizkaia, Red Eléctrica (owner), 3 Aug 2026. Consulted 26 Nov 2026.
- Red Eléctrica trasladará grandes equipamientos desde el Puerto de Bilbao a Gatika para la interconexión con Francia, Red Eléctrica (owner), 14 Jul 2026. Consulted 26 Nov 2026.
- Primera piedra de la estación conversora de Cubnezais, Red Eléctrica / RTE (owner), 16 May 2025. Consulted 26 Nov 2026.
- Inelfe awards main contracts for the electricity interconnection through the Bay of Biscay, Red Eléctrica (owner), 10 Mar 2023. Consulted 26 Nov 2026.
- Bay of Biscay interconnection (20230373), European Investment Bank (lender), 13 Jun 2025. Consulted 26 Nov 2026.
- Corredor y Jauregi destacan el papel estratégico de las inversiones en redes e interconexiones, Red Eléctrica (owner), 28 May 2026. Consulted 26 Nov 2026.