Reviewed record

Bilbao Metro Line 5, Aperribai to Galdakao section

Location
Galdakao, Bizkaia, Basque Country, Spain. See it on the map, in 3D
Stage
Under construction, as of January 29, 2026 (Última Hora (Europa Press)). In January 2026 the Olabarrieta gallery was finished with 287 m of main tunnel, the Abusu gallery about 92% excavated and Bengoetxe station 57% excavated.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerEuskal Trenbide Sarea (ETS)
TypeUrban transit
Headline amountEUR 91.3 million (EUR), as of June 28, 2023Gobierno Vasco, Dirección de Infraestructuras del Transporte (Sener Mobility)
What it coversBudget.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Length2.8 kmsectionAcciona
Length2.8 kmkm 1+540 to 4+340Gobierno Vasco, Dirección de Infraestructuras del Transporte (Sener Mobility)
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€91 MBudgettender budget, excl. VATJune 28, 2023Gobierno Vasco, Dirección de Infraestructuras del Transporte (Sener Mobility)
€88 MContract valuesection budget at award as reported by Acciona, VAT not statedJune 15, 2023Acciona
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Euskal Trenbide Sarea (ETS)OwnerÚltima Hora (Europa Press)
Metro Bengoetxe UTE (Acciona, Sacyr, Altuna y Uria, Bycam, equal shares)General contractor48 monthsAcciona
Sener MobilityDesignerModified Project No. 1 (2024); Bengoetxe station redesignGobierno Vasco, Dirección de Infraestructuras del Transporte (Sener Mobility)
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
June 15, 2023Award announcedAcciona
June 28, 2023Contract awarded to Metro Bengoetxe UTEGobierno Vasco, Dirección de Infraestructuras del Transporte (Sener Mobility)
July 24, 2024Report leading to Modified Project No. 1 (Bengoetxe in open excavation)Gobierno Vasco, Dirección de Infraestructuras del Transporte (Sener Mobility)
January 29, 2026Olabarrieta gallery done, Abusu 92%, Bengoetxe 57% excavatedÚltima Hora (Europa Press)
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

The Aperribai to Galdakao section is the 2.8 km middle part of Bilbao's new metro Line 5, in mined tunnel under Galdakao, with Bengoetxe and Galdakao stations. A joint venture of Acciona, Sacyr, Altuna y Uria and Bycam won it in June 2023 (tender budget 91.3 million euros before VAT); a modified project approved in April 2025 puts it at 115.1 million euros including VAT. In January 2026 the station at Bengoetxe was 57% excavated.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.