FGC Line 8 extension: Plaça Espanya to Gràcia

Location
Barcelona (Sants-Montjuïc, Eixample Esquerra, Sant Gervasi, Gràcia), Catalonia, Spain. See it on the map, in 3D
Stage
Under construction, as of 2026 (El Nacional). Civil works awarded in June 2023 and started in early 2024 (service diversions finished on 4 December 2023). The TBM was to start boring from the Gran Via shaft in June 2026; civil works are scheduled to finish in 2029 and the line to enter service in 2030.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerGeneralitat de Catalunya, Departament de Territori / Infraestructures de la Generalitat de Catalunya
TypeUrban transit
Headline amountEUR 412 million (EUR), as of December 20, 2023Generalitat de Catalunya / Ajuntament de Barcelona
What it coversTotal project cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Length3.5 kmroute lengthGeneralitat de Catalunya, Departament de Territori (Ifercat)
Length4 kmnew route as presentedGeneralitat de Catalunya / Ajuntament de Barcelona
Length4.1 kmunderground line per EIBEuropean Investment Bank
New stations3 stationsHospital Clínic, Francesc Macià, GràciaGeneralitat de Catalunya / Ajuntament de Barcelona
Ridership70,000 passengers per dayforecast; 19.5 million a yearGeneralitat de Catalunya / Ajuntament de Barcelona
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€300 MContract valueinfrastructure civil works (tunnel and main station structures), 58 months, VAT not statedJune 2023Generalitat de Catalunya / Ajuntament de Barcelona
€412 MTotal project costglobal estimate from the infrastructure award plus the remaining planned worksDecember 20, 2023Generalitat de Catalunya / Ajuntament de Barcelona
€435 MBudgettotal budget as reported in 20262026El Nacional
€300 MLoanEIB loan to the GeneralitatApril 22, 2026European Investment Bank
€7 MContract valueservice diversions (finished 2023-12-04)July 6, 2022Generalitat de Catalunya / Ajuntament de Barcelona
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Generalitat de Catalunya, Departament de Territori / Infraestructures de la Generalitat de CatalunyaOwnerFGC operatesGeneralitat de Catalunya, Departament de Territori (Ifercat)
Copcisa, Copisa Constructora Pirenaica, Ferrovial Construcción, Sacyr ConstrucciónGeneral contractorcivil works contract; shares not foundGeneralitat de Catalunya / Ajuntament de Barcelona
GPO Ingeniería y Arquitectura, META Engineering, Técnica y Proyectos (Typsa)Supervisiondirección de obraGeneralitat de Catalunya / Ajuntament de Barcelona
Euro GeotécnicaEngineermonitoring and controlGeneralitat de Catalunya / Ajuntament de Barcelona
DAC EnviroEngineerenvironmental assistanceGeneralitat de Catalunya / Ajuntament de Barcelona
Control y Geología, Ingeniería y Prevención de Riesgos, SGS Tecnos (UTE)Engineerhealth and safetyGeneralitat de Catalunya / Ajuntament de Barcelona
Cemosa and Labocat CalidadEngineerquality controlGeneralitat de Catalunya / Ajuntament de Barcelona
European Investment BankLender300 million euro loan, April 2026European Investment Bank
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
July 6, 2022Service diversion works start (finished 2023-12-04)Generalitat de Catalunya / Ajuntament de Barcelona
June 2023Civil works awarded to Copcisa, Copisa, Ferrovial, SacyrGeneralitat de Catalunya / Ajuntament de Barcelona
January 2024Planned start of the civil works (spring 2024 per the Generalitat leaflet)Generalitat de Catalunya / Ajuntament de Barcelona
April 22, 2026EIB loan of 300 million signedEuropean Investment Bank
June 2026 (planned)TBM starts boring from the Gran Via shaft (about 13 months of excavation)El Nacional
2029 (planned)End of civil worksEl Nacional
2030 (planned)L8 extension enters serviceEl Nacional
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

The Generalitat is extending FGC's Line 8 underground from Plaça Espanya to Gràcia, linking the Llobregat-Anoia and Barcelona-Vallès lines for the first time. The route is about 4 km in a single TBM tunnel with three new stations: Hospital Clínic, Francesc Macià and Gràcia. Copcisa, Copisa, Ferrovial and Sacyr build the civil works under a 300 million euro contract; the EIB lent 300 million euros in April 2026. Service is planned for 2030.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.