Reviewed record

Barcelona Metro L9/L10 central section: Zona Universitària to La Sagrera

Location
Barcelona (Les Corts, Sarrià-Sant Gervasi, Gràcia, Horta-Guinardó, Sant Andreu), Catalonia, Spain. See it on the map, in 3D
Stage
Under construction, as of September 25, 2026 (Metrópoli Abierta). In September 2026 the TBM had bored more than 3 km since it resumed and was heading towards Lesseps, with stations under construction at Mandri, Sarrià, Sanllehy, Campus Nord, Manuel Girona and Guinardó-Hospital de Sant Pau.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnersGeneralitat de Catalunya, Departament de Territori, Transports Metropolitans de Barcelona (TMB)
TypeUrban transit
Headline amountEUR 926 million (EUR), as of June 15, 2022Ara
What it coversBudget.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Tunnel diameter12 msingle bore, two decksAra
Tunnel depth35 to 70 mbelow groundAra
Remaining tbm drive1.6 kmMandri to Lesseps after the 2024 stopAra
First stretch length3.6 kmSagrera TAV to Guinardó-Hospital de Sant PauAra
Shaft27 m diameter, 60 m deepManuel Girona stationbetevé
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€926 MBudgetcost to finish the line (central section), VAT not statedJune 15, 2022Ara
€946 MInvestment programmeIfercat economic and financial plan for the central section (2020)December 10, 2020TMB
€48 MContract valueworks of Manuel Girona and Campus Nord stations, VAT not stated; contractor not named in sourceUndatedbetevé
€12 MContract valuereplacement TBM cutting wheelDecember 27, 2024Ara
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Generalitat de Catalunya, Departament de TerritoriOwnercontracting through Infraestructures.cat (Ifercat)TMB
Transports Metropolitans de Barcelona (TMB)OwneroperatorAra
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
June 2022TBM restarts from Passeig de Manuel GironaAra
July 2024TBM reaches Mandri and stops to change its cutting wheelAra
September 25, 2026TBM has bored more than 3 km since restarting, heading for LessepsMetrópoli Abierta
2027 (planned)Sagrera TAV, La Sagrera, Plaça de Maragall, Guinardó-Hospital de Sant Pau openMetrópoli Abierta
2030 (planned)Lesseps and Camp NouMetrópoli Abierta
2031 (planned)Campus Nord, Sarrià, Mandri, SanllehyMetrópoli Abierta
2032 (planned)Manuel Girona and Putxet complete the lineMetrópoli Abierta
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

The central section of Barcelona's L9/L10 metro is the missing link of about 9.4 km between Zona Universitària and La Sagrera, in a deep bored tunnel with two track decks. The Generalitat restarted the tunnelling in 2022 after a decade-long halt and puts the cost of finishing the line at 926 million euros. The first four stations, from Sagrera TAV to Guinardó-Hospital de Sant Pau, are planned to open in 2027, Lesseps and Camp Nou in 2030, and the rest by 2032.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.