Reviewed record
Barcelona La Sagrera station: structure and rail accesses
- Location
- Barcelona (Sant Andreu and Sant Martí districts), Catalonia, Spain. See it on the map, in 3D
- Stage
- Under construction, as of October 2026 (Moncloa.com). In October 2026 the last 300 m of track were being finished; three of the eight high-speed tracks have carried trains through the site since March 2025. The station architecture and installations are still to be tendered.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Adif Alta Velocidad | |
| Type | Rail | |
| Headline amount | EUR 340 million (EUR), as of October 22, 2026 | Moncloa.com |
| What it covers | Budget. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Floor area | 260,000 m2 | station | Acciona |
| Levels | 3 | station | Acciona |
| Tracks | 8 | standard-gauge high-speed tracks (2026 description) | Moncloa.com |
| Tracks | 10 | train servicing zone (ZTTT) | Moncloa.com |
| Capacity | 100 million passengers per year | design | Acciona |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €1.26 bn | Investment programme | contracts awarded for the station to date, more than EUR 1,000 million executed, VAT not stated | February 21, 2026 | Ministerio de Transportes y Movilidad Sostenible |
| €589 M | Contract value | structure and accesses, two UTEs, 2010 award, VAT included (EUR 589,244,830.70) | May 2010 | Ministerio de Fomento |
| €340 M | Budget | architecture and installations, segregated roads and urbanisation of the access, to be tendered | October 22, 2026 | Moncloa.com |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Adif Alta Velocidad | Owner | Moncloa.com | |
| Dragados, Acciona, Comsa and Acsa (Sorigué) | General contractor | station structure UTE; shares not found | Acciona |
| Rubau, Copisa, FCC Construcción and Ferrovial Agromán | Contractor, one lot | rail and road accesses UTE; shares not found | Railway Gazette International |
| B720 Arquitectura (Fermín Vázquez) | Architect | station architecture | Ara |
Milestones
| Date | Milestone | Source |
|---|---|---|
| March 29, 2010 | Station structure and rail and road access contracts awarded | Ministerio de Fomento |
| June 22, 2023 | Acciona wins a 2023 Potencia award for the station structure works | Acciona |
| March 2025 | High-speed trains start running through the site without stopping | Moncloa.com |
| October 2026 | Last 300 m of track being finished; architecture and installations tender announced for autumn 2026 | Moncloa.com |
| 2032 (planned) | Passengers not expected before 2032 | Ara |
About the project
La Sagrera is a semi-buried station of about 260,000 m2 on three levels, being built on the old Sagrera rail yards in north-east Barcelona for high-speed trains, Rodalies, three Metro lines and buses. Its structure and rail accesses were awarded in 2010 to two joint ventures of eight companies. The railway structure is due to be complete around the end of 2026; the architecture and installations, more than EUR 340 million, were still to be tendered in October 2026, and passengers are not expected before 2032.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Acciona, winner of the 2023 Potencia awards for the Sagrera station in Barcelona, Acciona (company), 22 Jun 2023. Consulted 26 Nov 2026.
- Adif licitará el proyecto de la estación de La Sagrera, Moncloa.com (press), 22 Oct 2026. Consulted 26 Nov 2026.
- La Sagrera entra en su fase decisiva, Ara (press), 21 Feb 2026. Consulted 26 Nov 2026.
- La Sagrera contracts awarded, Railway Gazette International (press), 19 May 2010. Consulted 26 Nov 2026.
- Foment adjudica la construcció de l'estació de la Sagrera per 590 milions, betevé (press). Consulted 26 Nov 2026.
- Recta final para la puesta en servicio de todas las vías de alta velocidad de la estación de La Sagrera en Barcelona, Ministerio de Transportes y Movilidad Sostenible (government), 22 Oct 2026. Consulted 27 Nov 2026.
- Fomento adjudica por 589,2 millones de euros la construcción de la estructura y los accesos de la estación de La Sagrera (Barcelona), Ministerio de Fomento (government), 29 Mar 2010. Consulted 27 Nov 2026.