Barcelona La Sagrera station: structure and rail accesses

Location
Barcelona (Sant Andreu and Sant Martí districts), Catalonia, Spain. See it on the map, in 3D
Stage
Under construction, as of October 2026 (Moncloa.com). In October 2026 the last 300 m of track were being finished; three of the eight high-speed tracks have carried trains through the site since March 2025. The station architecture and installations are still to be tendered.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerAdif Alta Velocidad
TypeRail
Headline amountEUR 340 million (EUR), as of October 22, 2026Moncloa.com
What it coversBudget.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Floor area260,000 m2stationAcciona
Levels3stationAcciona
Tracks8standard-gauge high-speed tracks (2026 description)Moncloa.com
Tracks10train servicing zone (ZTTT)Moncloa.com
Capacity100 million passengers per yeardesignAcciona
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€1.26 bnInvestment programmecontracts awarded for the station to date, more than EUR 1,000 million executed, VAT not statedFebruary 21, 2026Ministerio de Transportes y Movilidad Sostenible
€589 MContract valuestructure and accesses, two UTEs, 2010 award, VAT included (EUR 589,244,830.70)May 2010Ministerio de Fomento
€340 MBudgetarchitecture and installations, segregated roads and urbanisation of the access, to be tenderedOctober 22, 2026Moncloa.com
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Adif Alta VelocidadOwnerMoncloa.com
Dragados, Acciona, Comsa and Acsa (Sorigué)General contractorstation structure UTE; shares not foundAcciona
Rubau, Copisa, FCC Construcción and Ferrovial AgrománContractor, one lotrail and road accesses UTE; shares not foundRailway Gazette International
B720 Arquitectura (Fermín Vázquez)Architectstation architectureAra
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
March 29, 2010Station structure and rail and road access contracts awardedMinisterio de Fomento
June 22, 2023Acciona wins a 2023 Potencia award for the station structure worksAcciona
March 2025High-speed trains start running through the site without stoppingMoncloa.com
October 2026Last 300 m of track being finished; architecture and installations tender announced for autumn 2026Moncloa.com
2032 (planned)Passengers not expected before 2032Ara
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

La Sagrera is a semi-buried station of about 260,000 m2 on three levels, being built on the old Sagrera rail yards in north-east Barcelona for high-speed trains, Rodalies, three Metro lines and buses. Its structure and rail accesses were awarded in 2010 to two joint ventures of eight companies. The railway structure is due to be complete around the end of 2026; the architecture and installations, more than EUR 340 million, were still to be tendered in October 2026, and passengers are not expected before 2032.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.