Montcada i Reixac R2 undergrounding and new station

Location
Montcada i Reixac, Barcelona, Catalonia, Spain. See it on the map, in 3D
Stage
Under construction, as of July 2026 (Ara (English edition)). Works are under way: Adif's 2024 calendar set diaphragm walls and mined excavation for 2025 and 2026, and a shaft wall of the works partly collapsed on 22 July 2026.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerAdif
TypeRail
Headline amountEUR 621 million (EUR), as of December 5, 2022Nació Digital
What it coversBudget.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Tunnel length4 kmwhole tunnelNació Digital
Tracks3tunnelNació Digital
Design speed140 km/htunnelNació Digital
Bidders4offers receivedBOE
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€447 MContract valuevalue of the selected offer, VAT not stated (the 540 million reported by the press corresponds to it with VAT)September 26, 2023BOE
€540 MContract valuecontract as reported by the press, VAT not statedFebruary 11, 2025Ara
€516 MContract valuetender estimated valueDecember 15, 2022BOE
€621 MBudgettender authorised by the Council of MinistersDecember 5, 2022Nació Digital
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
AdifOwnerBOE
Ferrovial ConstrucciónGeneral contractorUTE Ferrovial-Comsa-FCC (MONTCADA UTE)BOE
ComsaGeneral contractorUTE memberBOE
FCC ConstrucciónGeneral contractorUTE memberBOE
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
December 15, 2022Works tender published (expediente 3.22/06110.0199)BOE
September 26, 2023Contract awarded to UTE Ferrovial-Comsa-FCCBOE
April 3, 2024Adif presents a three-year works calendar in four zonesAjuntament de Montcada i Reixac
February 10, 2025Machinery arrives and works start between Montcada and Bifurcació stations (Ara); Ara's English edition dates the start of works to January 2024Ara
July 22, 2026A shaft wall partly collapses at the Barcelona-Montcada boundary; R2, R2 Nord and R11 interruptedAra (English edition)
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

Adif is putting the R2 Rodalies line underground through Montcada i Reixac, north of Barcelona, in a tunnel of about 4 km with three tracks and a new underground station. The contract was awarded in September 2023 to a joint venture of Ferrovial, Comsa and FCC for EUR 446.6 million, about EUR 540 million with VAT. Works are under way, with a 1.2 km mined tunnel from Vallbona and a 3.2 km section between diaphragm walls. A shaft wall collapsed in July 2026 and cut the R2, R2 Nord and R11 lines.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.