Madrid Metro Line 11 extension: Plaza Elíptica to Conde de Casal

Location
Madrid (Carabanchel, Arganzuela, Retiro), Community of Madrid, Spain. See it on the map, in 3D
Stage
Under construction, as of June 24, 2026 (Comunidad de Madrid). The Comunidad de Madrid reported the Plaza Elíptica to Conde de Casal works at 45% in June 2026, after the TBM Mayrit broke through between Comillas and Madrid Río.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerComunidad de Madrid, Consejería de Vivienda, Transportes e Infraestructuras
TypeUrban transit
Headline amountEUR 671 million (EUR), as of December 20, 2025Comunidad de Madrid
What it coversTotal project cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Length6.7 kmPlaza Elíptica to Conde de CasalComunidad de Madrid
Length6.6 kmPlaza Elíptica to Conde de CasalComunidad de Madrid
Tbm tunnel length5.5 kmComillas to Conde de CasalComunidad de Madrid
Stations5 stations2 new, 3 interchangesComunidad de Madrid
Lifts29 liftsnew stations equipmentComunidad de Madrid
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€559 MBudgettender budget incl. VAT2022Comunidad de Madrid
€671 MTotal project costinvestment in the section (works, services, equipment), VAT not statedDecember 20, 2025Comunidad de Madrid
€104 MContract valuestation equipment (29 lifts, 60 escalators, fire protection, catenary), awarded 15% below a 123 million tender budget; contractor not namedJune 24, 2026Comunidad de Madrid
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Comunidad de Madrid, Consejería de Vivienda, Transportes e InfraestructurasOwnerComunidad de Madrid
Acciona Construcción, Dragados (ACS) and Rover Infraestructuras (UTE)General contractorprovisional award reported May 2022 among six bidders; shares not foundForbes España
Herrenknecht AGSupplierTBM Mayrit, built in Schwanau, GermanyComunidad de Madrid
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
November 2022Works startedComunidad de Madrid
March 26, 2026TBM Mayrit starts boring from ComillasComunidad de Madrid
June 2026TBM breakthrough at Madrid Río after crossing under the M-30 and the Manzanares; 1,116 m bored, 656 ringsComunidad de Madrid
June 24, 2026Works 45% complete; station equipment contract awarded (104 million)Comunidad de Madrid
2027 (planned)OpeningComunidad de Madrid
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

This first section of Madrid's Line 11 extension adds 6.7 km of underground line from Plaza Elíptica to Conde de Casal, with two new stations, Comillas and Madrid Río, and interchanges at Palos de la Frontera, Atocha and Conde de Casal. A joint venture of Acciona, Dragados and Rover is building it for the Comunidad de Madrid. Since March 2026 the TBM Mayrit has bored under the Manzanares from Comillas. Works were 45% complete in June 2026 and opening is planned for 2027.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.