Porto Metro Pink line (G): São Bento to Casa da Música
- Location
- Porto (Baixa, Cedofeita, Massarelos, Boavista), Norte, Portugal. See it on the map, in 3D
- Stage
- Under construction, as of October 7, 2026 (Metro do Porto). Tunnels are finished. On 6 October 2026 Metro do Porto vehicles began gauge tests along the whole line; commercial service is planned for the end of the first quarter of 2027.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Metro do Porto, S.A. | |
| Type | Urban transit | |
| Headline amount | EUR 304.7 million (EUR), as of August 2024 | Executive Digest |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Length | 3 km | Casa da Música to São Bento | Metro do Porto |
| Stations | 4 stations | Casa da Música, Galiza, Hospital Santo António, São Bento | Metro do Porto |
| Tunnel length | 580 m | Hospital Santo António to Praça da Liberdade, under Rua dos Clérigos | ECO |
| Station depth | 25 m | Hospital Santo António station excavation | Viva Porto |
| Ridership | 10 million passengers per year | 2017 forecast | Metro do Porto |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €305 M | Total project cost | total project investment, VAT not stated | August 2024 | Executive Digest |
| €181 M | Total project cost | initial estimate (2017), VAT not stated | February 15, 2017 | Metro do Porto |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Metro do Porto, S.A. | Owner | Metro do Porto | |
| Ferrovial | General contractor | consortium with ACA (Alberto Couto Alves), shares not found | Executive Digest |
| ACA - Alberto Couto Alves | General contractor | consortium member | Executive Digest |
Milestones
| Date | Milestone | Source |
|---|---|---|
| October 2022 | Tunnel excavation began | ECO |
| May 8, 2024 | First tunnel (Hospital Santo António to Praça da Liberdade) completed | ECO |
| August 7, 2024 | Tunnel breakthrough Galiza to Hospital Santo António | Executive Digest |
| October 6, 2026 | Gauge tests of trains along the whole line | Metro do Porto |
| March 2027 (planned) | Start of commercial service (end of Q1 2027) | Metro do Porto |
About the project
The Pink line is a new underground line of about 3 km in central Porto, from a new São Bento/Liberdade station to Casa da Música, with intermediate stations at Hospital Santo António and Galiza. The Ferrovial and ACA consortium built it for Metro do Porto. Tunnelling finished in 2025 and test runs began in October 2026; passenger service is planned for the end of March 2027. The total cost was put at 304.7 million euros.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- O Metro já circula na Linha Rosa, Metro do Porto (owner), 7 Oct 2026. Consulted 26 Nov 2026.
- A Casa da Música vai ficar mais perto de São Bento, Metro do Porto (owner), 15 Feb 2017. Consulted 26 Nov 2026.
- Metro do Porto conclui túnel entre Galiza e Hospital Santo António, Executive Digest (press), Aug 2024. Consulted 26 Nov 2026.
- Metro do Porto conclui primeiro túnel da Linha Rosa para abrir em julho de 2025, ECO (press), 8 May 2024. Consulted 26 Nov 2026.
- Avanço da Linha Rosa condiciona trânsito na Praça Almeida Garrett, Metro do Porto (owner), 30 Jan 2025. Consulted 26 Nov 2026.
- Estação Hospital Santo António vai ganhando forma no Jardim do Carregal, Viva Porto (press). Consulted 26 Nov 2026.