Porto Metro Pink line (G): São Bento to Casa da Música

Location
Porto (Baixa, Cedofeita, Massarelos, Boavista), Norte, Portugal. See it on the map, in 3D
Stage
Under construction, as of October 7, 2026 (Metro do Porto). Tunnels are finished. On 6 October 2026 Metro do Porto vehicles began gauge tests along the whole line; commercial service is planned for the end of the first quarter of 2027.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerMetro do Porto, S.A.
TypeUrban transit
Headline amountEUR 304.7 million (EUR), as of August 2024Executive Digest
What it coversTotal project cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Length3 kmCasa da Música to São BentoMetro do Porto
Stations4 stationsCasa da Música, Galiza, Hospital Santo António, São BentoMetro do Porto
Tunnel length580 mHospital Santo António to Praça da Liberdade, under Rua dos ClérigosECO
Station depth25 mHospital Santo António station excavationViva Porto
Ridership10 million passengers per year2017 forecastMetro do Porto
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€305 MTotal project costtotal project investment, VAT not statedAugust 2024Executive Digest
€181 MTotal project costinitial estimate (2017), VAT not statedFebruary 15, 2017Metro do Porto
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Metro do Porto, S.A.OwnerMetro do Porto
FerrovialGeneral contractorconsortium with ACA (Alberto Couto Alves), shares not foundExecutive Digest
ACA - Alberto Couto AlvesGeneral contractorconsortium memberExecutive Digest
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
October 2022Tunnel excavation beganECO
May 8, 2024First tunnel (Hospital Santo António to Praça da Liberdade) completedECO
August 7, 2024Tunnel breakthrough Galiza to Hospital Santo AntónioExecutive Digest
October 6, 2026Gauge tests of trains along the whole lineMetro do Porto
March 2027 (planned)Start of commercial service (end of Q1 2027)Metro do Porto
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

The Pink line is a new underground line of about 3 km in central Porto, from a new São Bento/Liberdade station to Casa da Música, with intermediate stations at Hospital Santo António and Galiza. The Ferrovial and ACA consortium built it for Metro do Porto. Tunnelling finished in 2025 and test runs began in October 2026; passenger service is planned for the end of March 2027. The total cost was put at 304.7 million euros.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.