Reviewed record
Lisbon Metro Red line extension: São Sebastião to Alcântara
- Location
- Lisbon (Campolide, Amoreiras, Campo de Ourique, Estrela, Alcântara), Lisbon, Portugal. See it on the map, in 3D
- Stage
- Contract awarded, works not confirmed, as of November 2026 (Diário de Notícias). The design and build contract was signed on 2023-12-22 with Mota-Engil and Spie Batignolles. Works have not started: in November 2026 Metro de Lisboa was preparing to resubmit the supervision contract to the Tribunal de Contas for the visa needed to proceed.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Metropolitano de Lisboa, E.P.E. | |
| Type | Urban transit | |
| Headline amount | EUR 405.4 million (EUR), as of May 20, 2026 | ECO |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Length | 4 km | route length, mostly underground | Metropolitano de Lisboa (EIA, Resumo Não Técnico) |
| Length | 4.1 km | as stated in 2026 | ECO |
| Stations | 4 stations | three underground, one on viaduct | Metropolitano de Lisboa (EIA, Resumo Não Técnico) |
| Viaduct length | 380 m | Alcântara station and access viaduct | Metropolitano de Lisboa (EIA, Resumo Não Técnico) |
| Ridership | 11 million passengers in the first year (network-wide increase) | forecast | Metropolitano de Lisboa (projetos) |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €322 M | Contract value | design and build contract, VAT not stated in source read | December 22, 2023 | Executive Digest |
| €405 M | Total project cost | eligible budget: 304 million EU funding plus 101.4 million national | May 20, 2026 | ECO |
| €304 M | Investment programme | PRR grant originally allocated (later withdrawn) | 2021 | Metropolitano de Lisboa (projetos) |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Metropolitano de Lisboa, E.P.E. | Owner | Metropolitano de Lisboa (EIA, Resumo Não Técnico) | |
| Mota-Engil Engenharia e Construção | General contractor | consortium with Spie Batignolles Internacional; design and build | Executive Digest |
| Spie Batignolles Internacional | General contractor | consortium member | Executive Digest |
Milestones
| Date | Milestone | Source |
|---|---|---|
| December 22, 2023 | Design and build contract signed with Mota-Engil and Spie Batignolles | Executive Digest |
| March 2024 | Tribunal de Contas approves the works contract; suspension from FCC's legal challenge still pending | Executive Digest |
| July 2025 | Visa request for the supervision contract submitted to the Tribunal de Contas, returned in August 2025 | Jornal de Negócios |
| 2030 (planned) | Target for completion | Time Out Lisboa |
About the project
The Red line extension will take Lisbon's metro about 4 km west from São Sebastião to Alcântara, with three underground stations (Amoreiras/Campolide, Campo de Ourique, Infante Santo) and an elevated station at Alcântara reached by a 380 m steel truss viaduct across the Alcântara valley. Mota-Engil and Spie Batignolles signed the design and build contract in December 2023 for about 321.9 million euros. Works have not started: the project lost its EU recovery funding and is waiting for a Tribunal de Contas visa. Metro de Lisboa targets completion in 2030.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Resumo Não Técnico do Projeto do Prolongamento da Linha Vermelha entre São Sebastião e Alcântara, Metropolitano de Lisboa (EIA, Resumo Não Técnico) (owner), Jan 2022. Consulted 26 Nov 2026.
- Prolongamento da Linha Vermelha inclui construção de quatro novas estações, Metropolitano de Lisboa (projetos) (owner), May 2021. Consulted 26 Nov 2026.
- Contrato do prolongamento da Linha Vermelha obtém visto do Tribunal de Contas, Executive Digest (press), Mar 2024. Consulted 26 Nov 2026.
- OE2027: Governo admite conciliar Linha Circular do Metro de Lisboa com linha em laço, Diário de Notícias (press), 2 Nov 2026. Consulted 26 Nov 2026.
- Governo procura financiamento para Linha Vermelha do Metro de Lisboa. No limite será o OE, ECO (press), 20 May 2026. Consulted 26 Nov 2026.
- TdC nega responsabilidades no atraso da Linha Vermelha do Metro de Lisboa, Jornal de Negócios (press), 21 Oct 2026. Consulted 26 Nov 2026.
- Linha Circular deve estar pronta até Março e expansão da Vermelha continua empatada, Time Out Lisboa (press), 22 Oct 2026. Consulted 26 Nov 2026.
- Prolongamento da Linha Vermelha: conheça as futuras estações, Metropolitano de Lisboa (projetos) (owner). Consulted 26 Nov 2026.