Seville Metro Line 3 North, subtramo II: Los Mares to San Lázaro

Location
Sevilla (Pino Montano, San Lázaro), Andalusia, Spain. See it on the map, in 3D
Stage
Under construction, as of September 25, 2024 (elDiario.es). Works started on 25 September 2024, after the May 2024 award, for about three years.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerJunta de Andalucía, Consejería de Fomento
TypeUrban transit
Headline amountEUR 131.9 million (EUR), as of July 17, 2023Junta de Andalucía (Portavoz del Gobierno)
What it coversBudget.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Length1,462.94 msubtramo IIJunta de Andalucía (Portavoz del Gobierno)
Stations2 stationsLos Carteros, San LázaroJunta de Andalucía (Portavoz del Gobierno)
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€106 MContract valueworks award, VAT not statedMay 2024elDiario.es
€132 MBudgettender budgetJuly 17, 2023Junta de Andalucía (Portavoz del Gobierno)
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Junta de Andalucía, Consejería de FomentoOwnerJunta de Andalucía (Portavoz del Gobierno)
Azvi, Dragados and Martín Casillas (UTE)General contractorshares not foundelDiario.es
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
July 17, 2023TenderJunta de Andalucía (Portavoz del Gobierno)
May 2024Award to Azvi, Dragados, Martín CasillaselDiario.es
September 25, 2024Works startelDiario.es
September 2027 (planned)About three years after startelDiario.es
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

Subtramo II of Seville's Line 3 North is a 1.46 km cut and cover tunnel from Los Mares in Pino Montano to Avenida Doctor Fedriani, with two underground stations, Los Carteros and San Lázaro. The Azvi, Dragados and Martín Casillas joint venture won it for about 105.6 million euros in May 2024 and started works in September 2024, for about three years.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.