Reviewed record
Puente del Centenario (SE-30, Seville): stay-cable replacement and widening
- Location
- Seville, over the Canal de Alfonso XIII (port of Seville), Andalusia, Spain. See it on the map, in 3D
- Stage
- Suspended, as of July 23, 2026 (MetroSevilla). The contractor asked to terminate the contract over overruns above the 20% legal limit and works stopped in 2026; press reported the contract rescinded and the Ministry preparing a new tender, with none of the 88 original stay cables yet replaced.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Ministerio de Transportes y Movilidad Sostenible, Dirección General de Carreteras | |
| Type | Highways | |
| Headline amount | EUR 136 million (EUR), as of July 23, 2026 | MetroSevilla |
| What it covers | Budget. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Bridge length | 564 m | whole bridge | elDiario.es Andalucía |
| Main span | 265 m | cable-stayed main span | elDiario.es Andalucía |
| Pylon height | 102 m | two pylons | elDiario.es Andalucía |
| Stay cables | 88 cables | all replaced | elDiario.es Andalucía |
| Lanes | 6 lanes | after works, 3 per direction (before: 5, 2 per direction plus 1 reversible) | elDiario.es Andalucía |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €86 M | Contract value | award incl. VAT | 2021 | MetroSevilla |
| €88 M | Budget | estimated tender value, excl. VAT (27 months) | September 30, 2020 | Boletín Oficial del Estado |
| €136 M | Budget | current total after modifications (press) | July 23, 2026 | MetroSevilla |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Ministerio de Transportes y Movilidad Sostenible, Dirección General de Carreteras | Owner | Agreement with the Autoridad Portuaria de Sevilla for works on port land, extended in 2025 by four years | Boletín Oficial del Estado |
| Acciona Construcción, Tecade and Freyssinet (UTE Sustitución Tirantes Puente del Centenario) | General contractor | Shares not stated; termination requested 2026 | Boletín Oficial del Estado |
| Fhecor Ingenieros Consultores, Ideam and VSING Innova 2016 | Supervision | Control and surveillance, EUR 2,837,066.57, awarded 2021-06-16 | Boletín Oficial del Estado |
Milestones
| Date | Milestone | Source |
|---|---|---|
| September 30, 2020 | Urgent tender published (27 months) | Boletín Oficial del Estado |
| June 16, 2021 | Supervision contract awarded | Boletín Oficial del Estado |
| October 25, 2021 | Agreement with the Port Authority signed | Boletín Oficial del Estado |
| November 27, 2025 | Port agreement extended four years | Boletín Oficial del Estado |
| April 30, 2026 | Works stopped; contractor requests termination | El Español |
About the project
The Ministry of Transport contracted the replacement of all 88 stay cables of Seville's Puente del Centenario, on the SE-30 over the port channel, and the widening of the deck from five to six lanes using steel cross ribs that anchor the new cables outside the carriageway. Acciona, Tecade and Freyssinet won the work in 2021 for EUR 86.4 million including VAT. After overruns took the cost to about EUR 136 million, the contractor sought termination in 2026, the works stopped, and the Ministry said it would tender the rest again.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Licitación: tirantes del Puente del Centenario, SE-30 p.k. 10+000 a 12+000 (BOE-B-2020-32552), Boletín Oficial del Estado (government), 30 Sep 2020. Consulted 26 Nov 2026.
- Formalización: control y vigilancia, sustitución de tirantes del Puente del Centenario (BOE-B-2021-33944), Boletín Oficial del Estado (government), 24 Jul 2021. Consulted 26 Nov 2026.
- Prórroga del Convenio con la Autoridad Portuaria de Sevilla (BOE-A-2025-25485), Boletín Oficial del Estado (government), 12 Dec 2025. Consulted 26 Nov 2026.
- Autoridad Portuaria de Sevilla: concesión a UTE Sustitución Tirantes Puente del Centenario (BOE-B-2025-12095), Boletín Oficial del Estado (government), 2 Apr 2025. Consulted 26 Nov 2026.
- El puente del Centenario: cinco años de obras, contrato rescindido y un futuro incierto, MetroSevilla (press), 23 Jul 2026. Consulted 26 Nov 2026.
- El puente gigante que nació pequeño: Sevilla se prepara para dar el estirón definitivo, elDiario.es Andalucía (press), 2021. Consulted 26 Nov 2026.
- El alcalde de Sevilla pedirá el cese fulminante ... por el parón del puente del Centenario, El Español (press), 30 Apr 2026. Consulted 26 Nov 2026.