Reviewed record
SE-40 Seville ring road: Valencina (A-8077) to Salteras (A-66)
- Location
- Valencina de la Concepción and Salteras, Sevilla, Andalusia, Spain. See it on the map, in 3D
- Stage
- Under construction, as of August 2025 (El Cronista (España)). Press reported in October 2026 that the works began in August 2025, with a 48-month term.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Ministerio de Transportes y Movilidad Sostenible, Dirección General de Carreteras | |
| Type | Highways | |
| Headline amount | EUR 125.4 million (EUR), as of June 27, 2024 | Boletín Oficial del Estado |
| What it covers | Budget. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Length | 8.4 km | section | elDiario.es Andalucía |
| Lanes | 3 lanes each way | 3.5 m lanes, 2.5 m outer shoulders | El Cronista (España) |
| Underpasses | 6 underpasses | section | El Cronista (España) |
| Overpasses | 5 overpasses | section | El Cronista (España) |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €96 M | Contract value | selected offer (BOE), excl. VAT | March 6, 2025 | Boletín Oficial del Estado |
| €116 M | Contract value | award as announced (consistent with the offer incl. 21% VAT) | March 10, 2025 | elDiario.es Andalucía |
| €125 M | Budget | estimated tender value, excl. VAT (48 months) | June 27, 2024 | Boletín Oficial del Estado |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Ministerio de Transportes y Movilidad Sostenible, Dirección General de Carreteras | Owner | Boletín Oficial del Estado | |
| Azvi and Martín Casillas (UTE) | General contractor | Shares not stated; 16 bids | Boletín Oficial del Estado |
| Cemosa and Lacer Ingeniería (UTE) | Supervision | Control and surveillance, EUR 2,438,675.51, awarded 2025-02-25 | Boletín Oficial del Estado |
Milestones
| Date | Milestone | Source |
|---|---|---|
| March 6, 2025 | Works awarded to Azvi-Martín Casillas | Boletín Oficial del Estado |
| August 2025 | Works begin | El Cronista (España) |
| 2029 (planned) | Completion expected around 2029 | El Cronista (España) |
About the project
The Ministry of Transport is building an 8.4 km section of Seville's SE-40 ring road from the A-8077 junction at Valencina de la Concepción to the A-66 at Salteras, with three 3.5 m lanes in each direction. Azvi and Martín Casillas won the contract in March 2025 with an offer of EUR 96.2 million excluding VAT (EUR 116.4 million announced by the Government) and started in August 2025. Completion is expected around 2029.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Formalización: SE-40, Tramo Enlace A-8077 Valencina-Enlace A-66 Salteras (BOE-B-2025-14027), Boletín Oficial del Estado (government), 15 Apr 2025. Consulted 26 Nov 2026.
- Licitación: SE-40, Tramo Enlace A-8077 Valencina-Enlace A-66 Salteras (BOE-B-2024-24014), Boletín Oficial del Estado (government), 27 Jun 2024. Consulted 26 Nov 2026.
- Adjudicado el nuevo tramo de la SE-40 de Sevilla, entre Valencina y Salteras, con el objetivo de acabarlo en 2029, elDiario.es Andalucía (press), 10 Mar 2025. Consulted 26 Nov 2026.
- La nueva autovía de 8,4 kilómetros que costará 116,4 millones de euros y conectará dos municipios de Sevilla, El Cronista (España) (press), 20 Oct 2026. Consulted 26 Nov 2026.
- Formalización: Control y vigilancia de las obras SE-40 Valencina-Salteras (BOE-B-2025-12062), Boletín Oficial del Estado (government), 2 Apr 2025. Consulted 26 Nov 2026.