Reviewed record
Lisbon Metro Circular Line: Rato to Cais do Sodré extension
- Location
- Lisbon (Estrela, Santos, Madragoa, Cais do Sodré; Campo Grande), Lisbon, Portugal. See it on the map, in 3D
- Stage
- Under construction, as of October 2026 (Time Out Lisboa). Tunnels are complete (Rato to Estrela May 2022, Estrela to Santos February 2023, Santos to Rato link March 2024). In October 2026 the works were reported to finish by March 2027.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Metropolitano de Lisboa, E.P.E. | |
| Type | Urban transit | |
| Headline amount | EUR 380 million (EUR), as of April 16, 2026 | Observador |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Length | 1.9 km | extension of the Green and Yellow lines | Metropolitano de Lisboa (projetos) |
| Length | 2 km | network added | Metropolitano de Lisboa |
| New stations | 2 stations | Estrela and Santos | Metropolitano de Lisboa |
| Station depth | 54 m | Estrela station below the surface | Lisboa Para Pessoas |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €210 M | Total project cost | initial estimate (2018), VAT not stated | April 2020 | ECO |
| €331 M | Total project cost | estimate before the April 2026 increase, VAT not stated | April 2026 | Observador |
| €380 M | Total project cost | total investment after Council of Ministers approved 48 million euros more, VAT not stated | April 16, 2026 | Observador |
| €49 M | Contract value | Lot 1, rough works (toscos) from the end of Rato station to Santos station, excl. VAT | April 9, 2020 | ECO |
| €70 M | Contract value | Lot 4, finishes and systems, excl. VAT | September 2023 | Jornal Económico |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Metropolitano de Lisboa, E.P.E. | Owner | Metropolitano de Lisboa | |
| Zagope, Construção e Engenharia | Contractor, one lot | Lot 1: tunnel and station shells, end of Rato station to Santos | ECO |
| Metro Santos Sodré ACE (Mota-Engil and Spie Batignolles International) | Contractor, one lot | Lot 2: Santos to Cais do Sodré, Santos station, Cais do Sodré remodelling | Lisboa Para Pessoas |
| Zagope and COMSA (ACE) | Contractor, one lot | Lot 4: finishes and systems, about 603 days | Jornal Económico |
Milestones
| Date | Milestone | Source |
|---|---|---|
| April 9, 2020 | Lot 1 awarded to Zagope | ECO |
| May 28, 2022 | Tunnel breakthrough Rato to Estrela | Metropolitano de Lisboa |
| February 28, 2023 | Tunnel breakthrough Estrela to Santos | Metropolitano de Lisboa |
| September 2023 | Tribunal de Contas visa for Lot 4 (finishes and systems) | Jornal Económico |
| March 13, 2024 | Santos station connected to the Rato-Santos tunnel | Metropolitano de Lisboa |
| April 16, 2026 | Government approves 48 million euros more; total 380 million | Observador |
| March 2027 (planned) | End of works and opening | Time Out Lisboa |
About the project
The Circular Line extends Lisbon's Yellow line about 2 km from Rato to Cais do Sodré, with two new underground stations, Estrela and Santos, so that the Yellow and Green lines form a ring through the city centre. Metropolitano de Lisboa split the works into four lots: tunnels and station shells (Zagope, then Mota-Engil), the Campo Grande viaducts, and finishes and systems (Zagope and Comsa). The tunnels are finished and the line is due to open by March 2027. Its cost has risen from 210 million euros in 2018 to 380 million euros.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Túnel da linha Circular já liga Santos ao Rato, Metropolitano de Lisboa (owner), 13 Mar 2024. Consulted 26 Nov 2026.
- Lote 4: empreitada de acabamentos e sistemas (anúncio), Metropolitano de Lisboa (owner). Consulted 26 Nov 2026.
- Conheça as novas estações da linha circular: Estrela e Santos, Metropolitano de Lisboa (projetos) (owner), Aug 2021. Consulted 26 Nov 2026.
- Metro de Lisboa: Santos-Cais do Sodré, Mota-Engil Engenharia (company). Consulted 26 Nov 2026.
- Metro de Lisboa adjudica primeira fase da Linha Circular, paga 48,6 milhões à Zagope, ECO (press), 12 Apr 2020. Consulted 26 Nov 2026.
- Linha Circular deve estar pronta até Março e expansão da Vermelha continua empatada, Time Out Lisboa (press), 22 Oct 2026. Consulted 26 Nov 2026.
- Governo aprova 48 milhões de euros para concluir Linha Circular do Metro de Lisboa, Observador (press), 16 Apr 2026. Consulted 26 Nov 2026.
- Tribunal de Contas aprova contrato do lote 4 da Linha Circular, Jornal Económico (press), 15 Sep 2023. Consulted 26 Nov 2026.
- Acesso à Estrela vai ser feito por super-elevadores. Viagem à estação mais funda do Metro de Lisboa, Observador (press). Consulted 26 Nov 2026.
- Linha Circular: Túnel do Metro de Lisboa já liga Estrela a Santos, Metropolitano de Lisboa (owner), 28 Feb 2023. Consulted 26 Nov 2026.
- Descemos ao túnel de Metro mais profundo da cidade, Lisboa Para Pessoas (press), 31 May 2022. Consulted 26 Nov 2026.