Lisbon Metro Circular Line: Rato to Cais do Sodré extension

Location
Lisbon (Estrela, Santos, Madragoa, Cais do Sodré; Campo Grande), Lisbon, Portugal. See it on the map, in 3D
Stage
Under construction, as of October 2026 (Time Out Lisboa). Tunnels are complete (Rato to Estrela May 2022, Estrela to Santos February 2023, Santos to Rato link March 2024). In October 2026 the works were reported to finish by March 2027.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerMetropolitano de Lisboa, E.P.E.
TypeUrban transit
Headline amountEUR 380 million (EUR), as of April 16, 2026Observador
What it coversTotal project cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Length1.9 kmextension of the Green and Yellow linesMetropolitano de Lisboa (projetos)
Length2 kmnetwork addedMetropolitano de Lisboa
New stations2 stationsEstrela and SantosMetropolitano de Lisboa
Station depth54 mEstrela station below the surfaceLisboa Para Pessoas
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€210 MTotal project costinitial estimate (2018), VAT not statedApril 2020ECO
€331 MTotal project costestimate before the April 2026 increase, VAT not statedApril 2026Observador
€380 MTotal project costtotal investment after Council of Ministers approved 48 million euros more, VAT not statedApril 16, 2026Observador
€49 MContract valueLot 1, rough works (toscos) from the end of Rato station to Santos station, excl. VATApril 9, 2020ECO
€70 MContract valueLot 4, finishes and systems, excl. VATSeptember 2023Jornal Económico
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Metropolitano de Lisboa, E.P.E.OwnerMetropolitano de Lisboa
Zagope, Construção e EngenhariaContractor, one lotLot 1: tunnel and station shells, end of Rato station to SantosECO
Metro Santos Sodré ACE (Mota-Engil and Spie Batignolles International)Contractor, one lotLot 2: Santos to Cais do Sodré, Santos station, Cais do Sodré remodellingLisboa Para Pessoas
Zagope and COMSA (ACE)Contractor, one lotLot 4: finishes and systems, about 603 daysJornal Económico
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
April 9, 2020Lot 1 awarded to ZagopeECO
May 28, 2022Tunnel breakthrough Rato to EstrelaMetropolitano de Lisboa
February 28, 2023Tunnel breakthrough Estrela to SantosMetropolitano de Lisboa
September 2023Tribunal de Contas visa for Lot 4 (finishes and systems)Jornal Económico
March 13, 2024Santos station connected to the Rato-Santos tunnelMetropolitano de Lisboa
April 16, 2026Government approves 48 million euros more; total 380 millionObservador
March 2027 (planned)End of works and openingTime Out Lisboa
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

The Circular Line extends Lisbon's Yellow line about 2 km from Rato to Cais do Sodré, with two new underground stations, Estrela and Santos, so that the Yellow and Green lines form a ring through the city centre. Metropolitano de Lisboa split the works into four lots: tunnels and station shells (Zagope, then Mota-Engil), the Campo Grande viaducts, and finishes and systems (Zagope and Comsa). The tunnels are finished and the line is due to open by March 2027. Its cost has risen from 210 million euros in 2018 to 380 million euros.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.