Minho line: Contumil-Ermesinde track quadrupling

Location
Contumil (Porto) to Ermesinde (Valongo), via Rio Tinto and Águas Santas, Norte, Portugal. See it on the map, in 3D
Stage
Under construction, as of May 2026 (Infraestruturas de Portugal). The works contract was consigned on 2026-05-08.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerInfraestruturas de Portugal
TypeRail
Headline amountEUR 226 million (EUR), as of May 2026Infraestruturas de Portugal
What it coversTotal project cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Length5.54 kmworks section km 2.500 to km 8.040Infraestruturas de Portugal
Tracks4after works (existing double track duplicated)Infraestruturas de Portugal
Level crossings removed4sectionInfraestruturas de Portugal
Daily trains200 trains/daycorridorInfraestruturas de Portugal
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€114 MContract valuecivil works contract, VAT not statedMay 2026Infraestruturas de Portugal
€226 MTotal project costtotal investment of the scheme, VAT not statedMay 2026Infraestruturas de Portugal
€40 MInvestment programmeEU funds, Portugal 2030May 2026Infraestruturas de Portugal
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Infraestruturas de PortugalOwnerInfraestruturas de Portugal
Mota-EngilGeneral contractorcontract of about EUR 114M, 1,385 daysEssential Business
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
May 8, 2026Works contract consignedInfraestruturas de Portugal
March 2030 (planned)Completion planned for the first quarter of 2030Infraestruturas de Portugal
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

Infraestruturas de Portugal is doubling the double track of the Linha do Minho to four tracks between Contumil and Ermesinde, on the northern edge of Porto, a section used by more than 200 trains a day. Mota-Engil holds the works contract of about EUR 113.5 million, consigned in May 2026, within a total investment of about EUR 226 million. Rio Tinto station and Águas Santas halt are rebuilt and four level crossings removed. Completion is planned for the first quarter of 2030.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.