Minho line: Contumil-Ermesinde track quadrupling
- Location
- Contumil (Porto) to Ermesinde (Valongo), via Rio Tinto and Águas Santas, Norte, Portugal. See it on the map, in 3D
- Stage
- Under construction, as of May 2026 (Infraestruturas de Portugal). The works contract was consigned on 2026-05-08.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Infraestruturas de Portugal | |
| Type | Rail | |
| Headline amount | EUR 226 million (EUR), as of May 2026 | Infraestruturas de Portugal |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Length | 5.54 km | works section km 2.500 to km 8.040 | Infraestruturas de Portugal |
| Tracks | 4 | after works (existing double track duplicated) | Infraestruturas de Portugal |
| Level crossings removed | 4 | section | Infraestruturas de Portugal |
| Daily trains | 200 trains/day | corridor | Infraestruturas de Portugal |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €114 M | Contract value | civil works contract, VAT not stated | May 2026 | Infraestruturas de Portugal |
| €226 M | Total project cost | total investment of the scheme, VAT not stated | May 2026 | Infraestruturas de Portugal |
| €40 M | Investment programme | EU funds, Portugal 2030 | May 2026 | Infraestruturas de Portugal |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Infraestruturas de Portugal | Owner | Infraestruturas de Portugal | |
| Mota-Engil | General contractor | contract of about EUR 114M, 1,385 days | Essential Business |
Milestones
| Date | Milestone | Source |
|---|---|---|
| May 8, 2026 | Works contract consigned | Infraestruturas de Portugal |
| March 2030 (planned) | Completion planned for the first quarter of 2030 | Infraestruturas de Portugal |
About the project
Infraestruturas de Portugal is doubling the double track of the Linha do Minho to four tracks between Contumil and Ermesinde, on the northern edge of Porto, a section used by more than 200 trains a day. Mota-Engil holds the works contract of about EUR 113.5 million, consigned in May 2026, within a total investment of about EUR 226 million. Rio Tinto station and Águas Santas halt are rebuilt and four level crossings removed. Completion is planned for the first quarter of 2030.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Quadruplicação da Linha do Minho entre Contumil e Ermesinde: consignação, Infraestruturas de Portugal (owner), 8 May 2026. Consulted 26 Nov 2026.
- Mota-Engil signs €114 million contract to quadruple Minho line stretch, Essential Business (press), 13 May 2026. Consulted 26 Nov 2026.