Reviewed record
Madrid-Extremadura high-speed line: Talayuela-Plasencia section
- Location
- Talayuela, Navalmoral de la Mata, Casatejada, Toril, Malpartida de Plasencia and Plasencia, Cáceres, Extremadura, Spain. See it on the map, in 3D
- Stage
- Under construction, as of April 2025 (La Moncloa (Ministry of Transport)). In April 2025 the Ministry said the 70 km section was under works, with the platform completed on four of its eight subsections.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Adif Alta Velocidad | |
| Type | Rail | |
| Headline amount | EUR 38.6 million (EUR), as of May 2025 | BOE |
| What it covers | Contract value, tender estimated value, overhead contact line and associated systems, works and maintenance, 48 months. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Length | 68.8 km | section | La Moncloa (Government of Spain) |
| Length | 70 km | section | La Moncloa (Ministry of Transport) |
| Subsections | 8 | platform subsections | Vía Libre (Fundación de los Ferrocarriles Españoles) |
| Length completed platform | 39.1 km | four finished subsections | Vía Libre (Fundación de los Ferrocarriles Españoles) |
| Work base area | 140,000 m2 | Navalmoral de la Mata work base | Forbes España |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €1.21 bn | Investment programme | executed or in execution since 2018 across Plasencia-Cáceres and Talayuela-Plasencia combined (43% of 2,775 million planned for both); no figure for this section alone | April 2025 | La Moncloa (Ministry of Transport) |
| €39 M | Contract value | tender estimated value, overhead contact line and associated systems, works and maintenance, 48 months | May 2025 | BOE |
| €18 M | Contract value | tender estimated value, Casatejada traction substation and autotransformer centres, works and maintenance, 48 months | December 2024 | BOE |
| €8 M | Contract value | GSM-R mobile telecommunications equipment | November 2025 | Forbes España |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Adif Alta Velocidad | Owner | BOE | |
| Hitachi Rail and Sistemas y Montajes Industriales (Grupo CPS) | Contractor, one lot | signalling, ERTMS level 2 and fixed telecoms UTE, see ES-RAIL-011 | Forbes España |
| Nokia, Sociedad Ibérica and Syneox | Contractor, one lot | GSM-R UTE, EUR 8.2 million | Forbes España |
| FCC and Convensa | Contractor, one lot | 140,000 m2 work base at Navalmoral de la Mata | Forbes España |
Milestones
| Date | Milestone | Source |
|---|---|---|
| February 2022 | Platform works of subsection Arroyo de Santa María-Navalmoral de la Mata awarded, including the integration of the railway in Navalmoral and the remodelling of its station | La Moncloa (Government of Spain) |
| July 2022 | Platform finished on subsections Talayuela-Arroyo de Santa María and Navalmoral de la Mata-Casatejada | La Moncloa (Government of Spain) |
| December 11, 2024 | Tender for the Casatejada substation and autotransformer centres | BOE |
| April 14, 2025 | Platform completed on four of eight subsections | La Moncloa (Ministry of Transport) |
| May 12, 2025 | Tender for the overhead contact line | BOE |
About the project
The Talayuela-Plasencia section is the middle part of the Madrid-Extremadura high-speed line, about 70 km across the Campo Arañuelo in Cáceres province. Adif AV builds it in eight platform subsections, with the line integrated through Navalmoral de la Mata. By 2025 the platform was finished on four subsections (39.1 km), and the signalling, electrification and track-laying base contracts had been tendered or awarded.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Óscar Puente on the Badajoz-Madrid high-speed line, La Moncloa (Ministry of Transport) (government), 14 Apr 2025. Consulted 26 Nov 2026.
- Hitachi gana un contrato clave de 118 millones de euros para un tramo de la alta velocidad en Extremadura, Forbes España (press), 4 Nov 2025. Consulted 26 Nov 2026.
- Anuncio de licitación: línea aérea de contacto y sistemas asociados, LAV Madrid-Extremadura, tramo Talayuela-Plasencia, expediente 4.25/20830.0035, BOE (government), 12 May 2025. Consulted 26 Nov 2026.
- Anuncio de licitación: subestación y centros de autotransformación del área eléctrica de Casatejada, tramo Talayuela-Plasencia, expediente 4.24/20830.0237, BOE (government), 11 Dec 2024. Consulted 26 Nov 2026.
- Primera fase Alta Velocidad Extremadura, dossier, La Moncloa (Government of Spain) (government), 18 Jul 2022. Consulted 26 Nov 2026.
- Licitada la electrificación del tramo de alta velocidad Talayuela-Plasencia, Vía Libre (Fundación de los Ferrocarriles Españoles) (press), May 2025. Consulted 26 Nov 2026.