Murcia-Cartagena high-speed link: Torre Pacheco-Cartagena section

Location
Torre Pacheco and Cartagena (Pozo Estrecho), Murcia, Region of Murcia, Spain. See it on the map, in 3D
Stage
Under construction, as of April 2025 (Grupo SANJOSE). SANJOSE and Sorigué announced on 10 April 2025 that they had started work on the platform.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerAdif Alta Velocidad
TypeRail
AmountNot found in the sources consulted
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Length8.96 kmsectionSorigué
Overpasses7sectionSorigué
Siding length750 msiding on the conventional line near Pozo EstrechoSorigué
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€128 MContract valueaward, VAT not statedApril 2025Grupo SANJOSE
€155 MContract valuefigure given by the Government in its 2024 review, VAT not stated (128.4 million plus 21% VAT is about 155 million)December 27, 2024La Moncloa (Ministry of Transport)
€138 MContract valuetender estimated valueJuly 18, 2024BOE
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Adif Alta VelocidadOwnerBOE
Constructora San José (SANJOSE)General contractorjoint venture member, share not statedGrupo SANJOSE
Acsa (Sorigué)General contractorjoint venture member, share not statedSorigué
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
July 18, 2024Works tender published (expediente 3.23/20830.0246)BOE
April 10, 2025SANJOSE and Sorigué announce the start of worksGrupo SANJOSE
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

This 8.96 km section of the Murcia-Cartagena high-speed link runs beside the conventional line from Torre Pacheco to Cartagena, across the irrigated Campo de Cartagena. It includes two 210 m viaducts over the Rambla del Albujón, a 750 m siding near Pozo Estrecho and seven overpasses. Adif AV awarded it for EUR 128.4 million to SANJOSE and Acsa (Sorigué), who started work in April 2025.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.