Reviewed record
Almería rail integration phase 2 and intermodal station
- Location
- Almería, Andalusia, Spain. See it on the map, in 3D
- Stage
- Under construction, as of September 2025 (Última Hora (Europa Press)). The works had passed half of their execution in September 2025; in August 2026 more than 2 km of the 8.7 km of planned track were laid.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owners | Adif and Adif Alta Velocidad, Junta de Andalucía, Ayuntamiento de Almería | |
| Type | Rail | |
| Headline amount | EUR 235 million (EUR), as of August 2026 | La Moncloa (Ministerio de Transportes) |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Tunnel length | 1.9 km | access tunnel | La Moncloa (Ministerio de Transportes) |
| Track length | 8.7 km | track planned on the access section | La Moncloa (Ministerio de Transportes) |
| Station tracks | 6 | three standard gauge, two Iberian gauge, one mixed | Forbes España |
| Rail building area | 2,775 m2 | rail building, two floors (Ministry 2026) | La Moncloa (Ministerio de Transportes) |
| Rail building area | 4,800 m2 | station enlarged, two floors (press 2023 and 2025) | Forbes España |
| Bus bays | 26 | bus station | La Moncloa (Ministerio de Transportes) |
| Bus station area | 2,250 m2 | bus station (Ministry); 2,265 m2 per press | La Moncloa (Ministerio de Transportes) |
| Car park spaces | 400 | underground car park | La Moncloa (Ministerio de Transportes) |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €170 M | Budget | works tender estimated value, 36 months | April 2023 | BOE |
| €137 M | Contract value | Sacyr award, excl. VAT (EUR 165M incl. VAT) | July 2023 | Forbes España |
| €185 M | Budget | works budget after approved modification, VAT not stated | September 2025 | Última Hora (Europa Press) |
| €235 M | Total project cost | phase 2 agreement total (Adif, Adif AV, Junta de Andalucía, Ayuntamiento de Almería), VAT not stated | August 2026 | La Moncloa (Ministerio de Transportes) |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Adif and Adif Alta Velocidad | Owner | with Junta de Andalucía and Ayuntamiento de Almería under the integration agreement | La Moncloa (Ministerio de Transportes) |
| Junta de Andalucía | Owner | co-funder, about 27% of the modified budget (press) | Última Hora (Europa Press) |
| Ayuntamiento de Almería | Owner | co-funder | Última Hora (Europa Press) |
| Sacyr | General contractor | sole contractor | Forbes España |
Milestones
| Date | Milestone | Source |
|---|---|---|
| April 10, 2023 | Works tender published in the BOE | BOE |
| July 21, 2023 | Works awarded to Sacyr | Forbes España |
| September 15, 2025 | Works more than 50% complete | Última Hora (Europa Press) |
| August 11, 2026 | More than 2 km of the 8.7 km of track laid | La Moncloa (Ministerio de Transportes) |
| December 2026 (planned) | End of works in Q4 2026, then AESF authorisation | La Moncloa (Ministerio de Transportes) |
About the project
The second phase of Almería's rail integration brings the Murcia-Almería high-speed line underground into the city through a 1.9 km access tunnel from El Puche to Avenida del Mediterráneo, and rebuilds the station as an intermodal hub with six tracks, a 26-bay bus station and a 400-space underground car park. Sacyr is the contractor, under an agreement between Adif, Adif AV, the Junta de Andalucía and Almería city council worth EUR 235 million. The Ministry expects the works to end in the fourth quarter of 2026.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Puente visita las obras del AVE en Almería, La Moncloa (Ministerio de Transportes) (government), 11 Aug 2026. Consulted 26 Nov 2026.
- Sacyr se adjudica las obras del AVE en Almería, Forbes España (press), 21 Jul 2023. Consulted 26 Nov 2026.
- El soterramiento de Almería rebasa la mitad de su ejecución y mantiene 2026 como plazo de finalización, Última Hora (Europa Press) (press), 15 Sep 2025. Consulted 26 Nov 2026.
- Anuncio de licitación: Integración del Ferrocarril en Almería. Fase 2, BOE (government), 10 Apr 2023. Consulted 26 Nov 2026.