Almería rail integration phase 2 and intermodal station

Location
Almería, Andalusia, Spain. See it on the map, in 3D
Stage
Under construction, as of September 2025 (Última Hora (Europa Press)). The works had passed half of their execution in September 2025; in August 2026 more than 2 km of the 8.7 km of planned track were laid.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnersAdif and Adif Alta Velocidad, Junta de Andalucía, Ayuntamiento de Almería
TypeRail
Headline amountEUR 235 million (EUR), as of August 2026La Moncloa (Ministerio de Transportes)
What it coversTotal project cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Tunnel length1.9 kmaccess tunnelLa Moncloa (Ministerio de Transportes)
Track length8.7 kmtrack planned on the access sectionLa Moncloa (Ministerio de Transportes)
Station tracks6three standard gauge, two Iberian gauge, one mixedForbes España
Rail building area2,775 m2rail building, two floors (Ministry 2026)La Moncloa (Ministerio de Transportes)
Rail building area4,800 m2station enlarged, two floors (press 2023 and 2025)Forbes España
Bus bays26bus stationLa Moncloa (Ministerio de Transportes)
Bus station area2,250 m2bus station (Ministry); 2,265 m2 per pressLa Moncloa (Ministerio de Transportes)
Car park spaces400underground car parkLa Moncloa (Ministerio de Transportes)
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€170 MBudgetworks tender estimated value, 36 monthsApril 2023BOE
€137 MContract valueSacyr award, excl. VAT (EUR 165M incl. VAT)July 2023Forbes España
€185 MBudgetworks budget after approved modification, VAT not statedSeptember 2025Última Hora (Europa Press)
€235 MTotal project costphase 2 agreement total (Adif, Adif AV, Junta de Andalucía, Ayuntamiento de Almería), VAT not statedAugust 2026La Moncloa (Ministerio de Transportes)
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Adif and Adif Alta VelocidadOwnerwith Junta de Andalucía and Ayuntamiento de Almería under the integration agreementLa Moncloa (Ministerio de Transportes)
Junta de AndalucíaOwnerco-funder, about 27% of the modified budget (press)Última Hora (Europa Press)
Ayuntamiento de AlmeríaOwnerco-funderÚltima Hora (Europa Press)
SacyrGeneral contractorsole contractorForbes España
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
April 10, 2023Works tender published in the BOEBOE
July 21, 2023Works awarded to SacyrForbes España
September 15, 2025Works more than 50% completeÚltima Hora (Europa Press)
August 11, 2026More than 2 km of the 8.7 km of track laidLa Moncloa (Ministerio de Transportes)
December 2026 (planned)End of works in Q4 2026, then AESF authorisationLa Moncloa (Ministerio de Transportes)
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

The second phase of Almería's rail integration brings the Murcia-Almería high-speed line underground into the city through a 1.9 km access tunnel from El Puche to Avenida del Mediterráneo, and rebuilds the station as an intermodal hub with six tracks, a 26-bay bus station and a 400-space underground car park. Sacyr is the contractor, under an agreement between Adif, Adif AV, the Junta de Andalucía and Almería city council worth EUR 235 million. The Ministry expects the works to end in the fourth quarter of 2026.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.

Sources