Lorca rail integration: underground line and Lorca-Sutullena station

Location
Lorca, Murcia, Region of Murcia, Spain. See it on the map, in 3D
Stage
Under construction, as of June 2026 (Murcia Economía). Adif opened new expropriations in June 2026 to advance the tunnel and station works, after the contract was awarded to OHLA's UTE in 2024.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerAdif Alta Velocidad
TypeRail
Headline amountEUR 400.4 million (EUR), as of June 2023BOE
What it coversBudget.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Length3.2 kmintegration sectionMerca2
Tunnel length2.9 kmfalse tunnel under the GuadalentínMurcia Economía
Station tracks3two main tracks and one sidingMerca2
Station platforms3stationMerca2
Land expropriated55,000 m2June 2026 expropriation, about 83 plotsMurcia Economía
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€400 MBudgettender estimated value, 32 months (VAT excluded as estimated value)June 2023BOE
€327 MContract valueworks award for platform and station, VAT not statedDecember 2024La Moncloa (Ministerio de Transportes)
€270 MContract valueaward as reported by the press in March 2024, VAT not statedMarch 2024Merca2
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Adif Alta VelocidadOwnerBOE
OHLAGeneral contractorUTE leader, 54%Merca2
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
June 22, 2023Works tender published in the BOEBOE
March 7, 2024OHLA announces the award to its joint ventureMerca2
June 16, 2026New expropriations of about 83 plots for the tunnel and stationMurcia Economía
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

Adif AV is putting 3.2 km of the Murcia-Almería high-speed line underground through Lorca, mostly in a cut-and-cover false tunnel that passes under the Guadalentín river, with a new underground Lorca-Sutullena station. The works are built by a joint venture led by OHLA with Sando and Hormigones Asfálticos Andaluces, awarded in 2024. The scheme removes the rail barrier that divides the city.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.