ALDOT contract 20251107017 bid tabulation

TRAFFIC SIGNAL UPGRADES (DETECTION SYSTEM UPGRADES) ON VARIOUS ROUTES AT VARIOUS LOCATIONS IN MOBILE AS INDICATED IN THE PLANS. Let by Alabama DOT on November 7, 2025, Mobile, 0901. 2 bids received; low bid $200,000 by Bagby & Russell Electric Company, Inc..

Owner
Alabama DOT
Letting
07 NOV 2025
Pay items
42
Data through
28 AUG 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Bagby & Russell Electric Company, Inc.$200,000Low
2Temple J Electric, LLC$534,310+167%
ALDOT contract 20251107017: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Bagby & Russell Electric Company, Inc.2. Temple J Electric, LLC
0010Mobilization (600A000)LS1$12,126$15,000
0020Construction fuel (maximum bid limited to $ 15,000.00) (698A000)LS1$0.00$5,000.00
0030Furnishing and installing traffic control unit ( old shell road at alverson drive) (730C000)LS1$4,000.00$15,000
0040Furnishing and installing traffic control unit ( university boulevard at overlook road) (730C001)LS1$4,000.00$15,000
0050Furnishing and installing traffic control unit ( university boulevard at bit and spur road) (730C002)LS1$3,000.00$10,000
0060Furnishing and installing traffic control unit ( cottage hill road at university boulevard) (730C003)LS1$3,000.00$10,000
0070Furnishing and installing traffic control unit ( mobile street at university hospital drive) (730C004)LS1$3,000.00$10,000
0080Furnishing and installing traffic control unit ( stanton road at pennington street) (730C005)LS1$3,000.00$10,000
0090Furnishing and installing traffic control unit ( stanton road at university hospital drive) (730C006)LS1$3,000.00$10,000
0100Furnishing and installing traffic control unit ( stanton road at pleasant avenue) (730C007)LS1$3,200.00$12,000
0110Furnishing and installing traffic control unit ( halls mill road at mcvay drive) (730C008)LS1$4,000.00$15,000
0120Furnishing and installing traffic control unit ( emogene street at springdale boulevard) (730C009)LS1$3,200.00$15,000
0130Furnishing and installing traffic control unit ( emogene street at sage avenue) (730C010)LS1$3,000.00$12,000
0140Furnishing and installing traffic control unit ( emogene street at florida street) (730C011)LS1$3,200.00$12,000
0150Furnishing and installing traffic control unit ( dauphin street at florida street) (730C012)LS1$3,200.00$15,000
0160Furnishing and installing traffic control unit ( dauphin street at fulton street) (730C013)LS1$3,000.00$12,000
0170Furnishing and installing traffic control unit ( dauphin street at carlen street) (730C014)LS1$4,000.00$20,000
0180Furnishing and installing traffic control unit ( dauphin street at houston street) (730C015)LS1$4,000.00$20,000
0190Furnishing and installing traffic control unit ( dauphin street at monterey street) (730C053)LS1$3,000.00$12,000
0200Furnishing and installing traffic control unit ( dauphin street at catherine street) (730C054)LS1$4,000.00$18,000
0210Furnishing and installing traffic control unit ( dauphin street at lafayette street) (730C100)LS1$3,000.00$12,000
0220Furnishing and installing traffic control unit ( dauphin street at ann street) (730C101)LS1$3,200.00$15,000
0230Furnishing and installing traffic control unit ( pleasant valley road at mcrae avenue) (730C102)LS1$3,000.00$12,000
0240Furnishing and installing traffic control unit ( holcombe avenue at halls mill road/fairway drive) (730C103)LS1$7,200.00$35,000
0250Furnishing and installing traffic control unit ( holcombe avenue at gosson street) (730C104)LS1$3,000.00$12,000
0260Furnishing and installing traffic control unit ( houston street at virginia street) (730C105)LS1$3,000.00$12,000
0270Furnishing and installing traffic control unit ( houston street at dublin street) (730C106)LS1$3,200.00$15,000
0280Furnishing and installing traffic control unit ( houston street at duval street) (730C107)LS1$3,000.00$12,000
0290Furnishing and installing traffic control unit ( michigan avenue at duval street) (730C108)LS1$3,000.00$12,000
0300Furnishing and installing traffic control unit ( michigan ave at texas street) (730C109)LS1$3,000.00$12,000
0310Furnishing and installing traffic control unit ( broad street at texas street) (730C110)LS1$3,200.00$12,000
0320Furnishing and installing traffic control unit ( broad street at baltimore street) (730C111)LS1$3,000.00$12,000
0330Furnishing and installing traffic control unit ( canal road at jackson street) (730C112)LS1$7,200.00$25,000
0340Furnishing and installing traffic control unit ( canal road at washington street) (730C113)LS1$3,200.00$25,000
0350Wood traffic signal strain pole (730G005)EACH2$9,000.00$2,000.00
0360Traffic signal junction box type S1 (730K001)EACH6$1,500.00$750.00
03702", non-metallic, conduit (730L005)LF270$100.00$12.00
0380Construction signs (740B000)SF678$1.00$15.00
0390Channelizing drums (740D000)EACH25$1.00$65.00
0400Cones (36 inches high) (740E000)EACH50$1.00$35.00
0410Portable sequential arrow and chevron sign unit (741C010)EACH1$1.00$2,400.00
04206" electrical conduit, 1 line, type 5 installation (756A028)LF165$128.00$125.00
ALDOT contract 20251107017: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ALDOT's tabulation for this contract. ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.

Every contract let that day: ALDOT letting of November 7, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy