Temple J Electric, LLC: ALDOT bid record

Temple J Electric, LLC submitted 14 bids on Alabama DOT contracts in the data, from 28 JUL 2023 to 28 AUG 2026, and was the low bidder on 6 of them (43%). When it was not low, its total sat a median +27% above the low bid.

Owner
Alabama DOT
Low bid volume
$5,693,667
Latest bid
28 AUG 2026
Data through
28 AUG 2026
14Bids
6Low bids
43Win rate, percent
+27%Median gap to the low bid when not low, 8 bids

By year

YearBidsLow bidsWin rate
2023100%
20243267%
20255360%
20265120%
Temple J Electric, LLC, ALDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
0901300%
05022150%
0202200%
0103100%
050611100%
010511100%
090211100%
010411100%
08, 0802,100%
040511100%
Temple J Electric, LLC, ALDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Construction signs740B000SF144 (29%)$7.50$7.00
Electrical junction box,type 1750D200EACH74 (57%)$650.00$1,243.00
Conduit, 2 inch, rigid metallic750E127LF64 (67%)$18.00$23.90
Channelizing drums740D000EACH133 (23%)$70.22$33.00
Wattle665Q002LF73 (43%)$12.00$10.75
Temporary mulching665B001TON73 (43%)$1,500.00$545.62
Sand bags665G000EACH73 (43%)$10.00$10.00
6" electrical conduit, 1 line, type 5 installation756A028LF73 (43%)$75.00$85.65
Combined duct and cable,2 #6 AWG/ 1 #6 AWG GND750G010LF73 (43%)$11.67$14.07
Pole foundation,roadway750C010EACH73 (43%)$4,000.00$4,000.00
Filter blanket, geotextile610D003SY53 (60%)$4.79$5.47
Service pole750H005EACH62 (33%)$3,650.00$3,910.72
Temple J Electric, LLC, ALDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

FirmContracts in commonThat firm ranked ahead
Stone & Sons Electrical Contractors, Inc.50 of 5
Williams Power & Signal, LLC51 of 5
Stone Electric Company, Inc.41 of 4
Inline, LLC33 of 3
Bagby & Russell Electric Company, Inc.32 of 3
Shoals Electric Company, Inc.21 of 2
Ozark Safety Services, LLC21 of 2
J. Ranck Electric, Inc.20 of 2
Big River Electric, Inc.22 of 2
Vulcan Materials Asphalt and Construction,10 of 1
Temple J Electric, LLC, ALDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
28 AUG 2026202608280080502ROADWAY SAFETY IMPROVEMENTS (HIGHWAY LIGHTING UPGRADES) ON I-20/I-59 RAMPS AT THE INTERCHANGE OF MERCEDES DRIVE AND ACCESS ROAD (EXIT 89) IN3 of 6$550,548+22%
28 AUG 2026202608280300202ROADWAY IMPROVEMENTS/REALIGNMENT (GRADING, DRAINING, PAVEMENT, TRAFFIC SIGNS, TRAFFIC SIGNALS, AND TRAFFIC STRIPE) ON SR-3 (US-31) AT SPARKM8 of 8$2,180,945+87%
24 APR 2026202604240350901TRAFFIC SIGNAL UPGRADES AT SIGNALIZED INTERSECTIONS ON VARIOUS ROUTES AT VARIOUS LOCATIONS IN THE SOUTHWEST REGION (MOBILE AREA) AS INDICATE3 of 3$154,925+55%
27 FEB 2026202602270040405INTERSTATE LIGHTING INSTALLATION AND UPGRADES ON I-20 AT THE CR-207 (EXIT 165) INTERCHANGE EAST OF RIVERSIDE1 of 4$1,171,084Low, 27% under the second
30 JAN 20262026013001008, 0802,TRAFFIC SIGNAL UPGRADES (TRAFFIC SIGNAL BACKPLATE INSTALL) ON VARIOUS ROUTES AT VARIOUS LOCATIONS IN THE SOUTHWEST REGION (GROVE HILL AREA) 2 of 2$270,975+6.0%
05 DEC 2025202512050110202ROADWAY LIGHTING ON SR-24 FROM THE INTERSECTION OF 9TH STREET SOUTHWEST TO THE JUNCTION OF MCCARTHY DRIVE IN RED BAY2 of 4$765,120+8.0%
07 NOV 2025202511070170901TRAFFIC SIGNAL UPGRADES (DETECTION SYSTEM UPGRADES) ON VARIOUS ROUTES AT VARIOUS LOCATIONS IN MOBILE AS INDICATED IN THE PLANS2 of 2$534,310+167%
26 SEP 2025202509260150104INTERCHANGE LIGHTING ON I-65 AT THE CR-222 (EXIT 305) INTERCHANGE IN GOOD HOPE1 of 4$688,407Low, 13% under the second
27 JUN 2025202506270270902TRAFFIC SIGNAL INSTALLATION AND STRIPING ON SR-181 AT CORTE ROAD/AUSTIN ROAD1 of 2$638,952Low, 21% under the second
28 FEB 2025202502280440105RESURFACING AND TRAFFIC SIGNAL INSTALLATIONS ON CHURCH STREET FROM THE JUNCTION OF SR-77 TO THE JUNCTION OF SR- 25 (US-411) AND AT VARIOUS L1 of 3$1,075,442Low, 12% under the second
06 DEC 2024202412060640506ROADWAY SAFETY IMPROVEMENTS (ROADWAY LIGHTING INSTALLATION) ON SR-8 (US-80) AT SR-28 AND CR-25 WEST OF THE MARENGO COUNTY LINE1 of 5$483,969Low, 1.0% under the second
08 NOV 2024202411080100901ROADWAY SAFETY IMPROVEMENTS (TRAFFIC SIGNAL UPGRADES) ON VARIOUS ROUTES AT VARIOUS LOCATIONS IN THE SOUTHWEST REGION (MOBILE AREA) AS INDICA4 of 4$686,528+31%
29 MAR 2024202403290150502SAFETY IMPROVEMENTS (TRAFFIC LIGHTING INSTALLATION) ON I-20/I-59 AT THE EXIT 79 (SR-7/US-11) INTERCHANGE SOUTHEAST OF COTTONDALE TO INCLUDE 1 of 2$1,635,813Low, 13% under the second
28 JUL 2023202307280400103ROADWAY LIGHTING INSTALLATION ON SR-2 (US-72) FROM THE JUNCTION OF ADAMS STREET TO THE INTERSECTION OF CR-85 (BANK STREET) IN STEVENSON2 of 2$223,469+12%
Temple J Electric, LLC: latest ALDOT bids in the data

How this record was read

ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.

  • Every bid counted here matched its published total to within one dollar; ALDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy