ALDOT contract 20260828030 bid tabulation
ROADWAY IMPROVEMENTS/REALIGNMENT (GRADING, DRAINING, PAVEMENT, TRAFFIC SIGNS, TRAFFIC SIGNALS, AND TRAFFIC STRIPE) ON SR-3 (US-31) AT SPARKMAN STREET AND LANE ROAD, TO INCLUDE ACCESS MANAGEMENT AND TRAFFIC SIGNAL INSTALLATION IN HARTSE. Let by Alabama DOT on August 28, 2026, Morgan, 0202. 8 bids received; low bid $1,167,500 by Rogers Group, Inc..
- Owner
- Alabama DOT
- Letting
- 28 AUG 2026
- Pay items
- 91
- Data through
- 28 AUG 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rogers Group, Inc. | $1,167,500 | Low |
| 2 | Grayson Carter & Son Contracting, Inc. | $1,228,953 | +5.0% |
| 3 | Gillespie Construction, LLC | $1,323,315 | +13% |
| 4 | Wiregrass Construction Company, Inc. | $1,377,111 | +18% |
| 5 | Bulls Construction Group, LLC | $1,387,356 | +19% |
| 6 | CG Jones, LLC | $1,477,841 | +27% |
| 7 | MLMD, LLC | $1,712,452 | +47% |
| 8 | Temple J Electric, LLC | $2,180,945 | +87% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rogers Group, Inc. | 2. Grayson Carter & Son Contracting, Inc. | 3. Gillespie Construction, LLC | 4. Wiregrass Construction Company, Inc. | 5. Bulls Construction Group, LLC | 6. CG Jones, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Clearing and grubbing (maximum allowable bid $ 8,000.00 per acre) (approximately 1 acre) (201A002) | LS | 1 | $6,000.00 | $4,949.76 | $8,000.00 | $4,086.97 | $8,000.00 | $8,000.00 |
| 0020 | Removing pipe (206D000) | LF | 81 | $22.00 | $28.11 | $45.00 | $38.00 | $40.00 | $12.00 |
| 0030 | Removing curb (206D002) | LF | 188 | $15.70 | $16.58 | $45.00 | $24.58 | $20.00 | $12.00 |
| 0040 | Removing brick signs (206E021) | EACH | 1 | $550.00 | $1,201.80 | $850.00 | $2,879.75 | $4,000.00 | $1,300.00 |
| 0050 | Removing brick planter (206E036) | EACH | 1 | $550.00 | $1,248.70 | $500.00 | $1,659.15 | $1,500.00 | $3,700.00 |
| 0060 | Mailbox reset, single (209A000) | EACH | 2 | $400.00 | $630.04 | $400.00 | $644.95 | $1,500.00 | $400.00 |
| 0070 | Unclassified excavation (210A000) | CY | 1,649 | $18.50 | $29.12 | $25.00 | $46.09 | $30.00 | $26.00 |
| 0080 | Borrow excavation (loose truckbed measurement) (210D001) | CY | 489 | $38.50 | $37.04 | $45.00 | $65.00 | $50.00 | $35.00 |
| 0090 | Structure excavation (214A000) | CY | 135 | $8.80 | $22.83 | $110.00 | $10.00 | $75.00 | $40.00 |
| 0100 | Foundation backfill, commercial (214B001) | CY | 69 | $56.00 | $33.09 | $100.00 | $58.00 | $100.00 | $80.00 |
| 0110 | Crushed aggregate base course, type B, plant mixed, 6" compacted thickness (301A012) | SY | 2,258 | $17.00 | $19.26 | $21.00 | $29.00 | $23.00 | $23.00 |
| 0120 | Bituminous treatment A (401A000) | SY | 2,258 | $1.50 | $1.54 | $2.03 | $2.00 | $3.00 | $3.00 |
| 0130 | Tack coat (405A000) | GAL | 324 | $4.00 | $4.69 | $5.37 | $6.00 | $5.00 | $6.00 |
| 0140 | Micro-milling existing pavement (approximately 1.10" thru 2.00" thick) (408B001) | SY | 3,219 | $2.75 | $5.32 | $3.67 | $6.00 | $8.06 | $8.50 |
| 0150 | Superpave bituminous concrete wearing surface layer, 1/2" maximum aggregate size mix, esal range C/D (424A360) | TON | 396 | $130.00 | $156.42 | $175.15 | $200.00 | $190.00 | $190.00 |
| 0160 | Superpave bituminous concrete upper binder layer, 1/2" maximum aggregate size mix, esal range C/D (424B002) | TON | 142 | $150.00 | $178.40 | $202.27 | $212.00 | $246.00 | $260.00 |
| 0170 | Superpave bituminous concrete upper binder layer, 3/4" maximum aggregate size mix, esal range C/D (424B650) | TON | 20 | $230.00 | $340.39 | $306.23 | $400.00 | $234.00 | $220.00 |
| 0180 | Superpave bituminous concrete upper binder layer, 1" maximum aggregate size mix, esal range C/D (424B651) | TON | 100 | $175.00 | $162.65 | $233.91 | $300.00 | $265.00 | $250.00 |
| 0190 | Superpave bituminous concrete upper binder layer, patching, 1" maximum aggregate size mix, esal range C/D (424B655) | TON | 75 | $218.00 | $263.06 | $291.54 | $300.00 | $327.00 | $320.00 |
| 0200 | Superpave bituminous concrete upper binder layer, leveling, 1" maximum aggregate size mix, esal range C/D (424B659) | TON | 75 | $193.00 | $187.17 | $257.64 | $275.00 | $227.00 | $215.00 |
| 0210 | Superpave bituminous concrete lower binder layer, 3/4" maximum aggregate size mix, esal range C/D (424B680) | TON | 100 | $152.00 | $168.74 | $202.27 | $300.00 | $325.00 | $305.00 |
| 0220 | Superpave bituminous concrete lower binder layer, 1" maximum aggregate size mix, esal range C/D (424B681) | TON | 100 | $175.00 | $162.65 | $233.91 | $185.00 | $265.00 | $240.00 |
| 0230 | Aggregate surfacing (aldot #57) (430B003) | TON | 99 | $30.00 | $68.97 | $75.00 | $100.00 | $75.00 | $57.00 |
| 0240 | 15" roadway pipe (class 3 R.C.) (530A000) | LF | 76 | $88.00 | $146.23 | $140.00 | $151.44 | $175.00 | $145.00 |
| 0250 | 18" roadway pipe (class 3 R.C.) (530A001) | LF | 189 | $80.00 | $109.81 | $130.00 | $150.72 | $200.00 | $148.00 |
| 0260 | 15" side drain pipe (class 3 R.C.) (535A078) | LF | 34 | $77.00 | $113.29 | $140.00 | $142.58 | $200.00 | $133.00 |
| 0270 | Mobilization (600A000) | LS | 1 | $120,000 | $121,872 | $31,000 | $136,000 | $84,066 | $170,322 |
| 0280 | Loose riprap, class 2 (610C001) | TON | 44 | $58.00 | $61.13 | $75.00 | $155.00 | $100.00 | $75.00 |
| 0290 | Filter blanket, geotextile (610D003) | SY | 126 | $5.50 | $6.41 | $10.00 | $15.57 | $20.00 | $6.00 |
| 0300 | Slope paving (614A000) | CY | 49 | $592.00 | $682.11 | $1,025.00 | $648.16 | $800.00 | $710.00 |
| 0310 | 15" roadway pipe end treatment, class 1 (619A001) | EACH | 1 | $2,200.00 | $1,202.48 | $2,500.00 | $2,136.94 | $2,500.00 | $950.00 |
| 0320 | 18" roadway pipe end treatment, class 1 (619A002) | EACH | 3 | $2,200.00 | $1,235.97 | $2,750.00 | $2,136.94 | $2,500.00 | $950.00 |
| 0330 | 15" side drain pipe end treatment, class 1 (619A100) | EACH | 2 | $2,200.00 | $1,202.48 | $2,500.00 | $2,136.95 | $2,500.00 | $1,070.00 |
| 0340 | Inlets, type E (621C008) | EACH | 2 | $10,000 | $10,800 | $6,000.00 | $10,263 | $10,000 | $11,300 |
| 0350 | Concrete curb, type N (623B000) | LF | 1,050 | $34.00 | $34.11 | $60.00 | $32.41 | $50.00 | $36.00 |
| 0360 | Concrete curb, type N special (623B001) | LF | 250 | $90.00 | $125.05 | $150.00 | $118.83 | $130.00 | $131.00 |
| 0370 | Topsoil (650A000) | CY | 441 | $54.00 | $58.86 | $45.00 | $52.00 | $50.00 | $40.00 |
| 0380 | Seeding (652A100) | ACRE | 2 | $2,500.00 | $3,353.70 | $1,200.00 | $1,042.74 | $1,500.00 | $4,500.00 |
| 0390 | Solid sodding (bermuda) (654A001) | SY | 786 | $12.00 | $7.16 | $10.00 | $11.00 | $20.00 | $8.00 |
| 0400 | Mulching (656A010) | ACRE | 2 | $2,500.00 | $1,565.07 | $1,200.00 | $1,042.74 | $1,736.00 | $1,900.00 |
| 0410 | Temporary seeding (665A000) | ACRE | 2 | $1,200.00 | $1,565.07 | $900.00 | $802.10 | $825.00 | $2,070.00 |
| 0420 | Temporary mulching (665B001) | TON | 6 | $425.00 | $655.67 | $1,500.00 | $802.10 | $1,000.00 | $1,000.00 |
| 0430 | Sand bags (665G000) | EACH | 200 | $6.00 | $14.61 | $12.00 | $10.69 | $7.00 | $15.00 |
| 0440 | Temporary coarse aggregate,aldot number 1 (665N000) | TON | 38 | $42.50 | $55.77 | $75.00 | $162.38 | $100.00 | $63.00 |
| 0450 | Inlet protection, stage 3 or 4 (665P005) | EACH | 2 | $675.00 | $656.59 | $450.00 | $213.90 | $500.00 | $800.00 |
| 0460 | Wattle, 20 inch (665Q020) | LF | 200 | $12.50 | $16.26 | $18.00 | $19.25 | $10.00 | $11.00 |
| 0470 | Geometric controls (680A001) | LS | 1 | $15,147 | $12,887 | $45,000 | $34,939 | $17,785 | $26,700 |
| 0480 | Construction fuel (maximum bid limited to $ 55,578.00) (698A000) | LS | 1 | $0.00 | $0.01 | $0.00 | $0.00 | $0.00 | $1.00 |
| 0490 | Dotted, class 2, type A, traffic stripe (701B205) | LF | 569 | $4.00 | $3.24 | $2.26 | $2.18 | $2.50 | $3.50 |
| 0500 | Broken white, class 2, type A traffic stripe (701G240) | LF | 136 | $4.00 | $2.16 | $1.13 | $1.09 | $1.50 | $2.50 |
| 0510 | Solid white, class 2, type A traffic stripe (701G249) | LF | 2,134 | $4.00 | $2.16 | $2.26 | $2.18 | $2.50 | $2.50 |
| 0520 | Solid yellow, class 2, type A traffic stripe (701G263) | LF | 1,035 | $4.00 | $2.16 | $2.26 | $2.18 | $2.50 | $2.50 |
| 0530 | Traffic control markings, class 2, type A (703A002) | SF | 862 | $9.00 | $8.10 | $5.65 | $5.46 | $6.00 | $9.00 |
| 0540 | Traffic control legends, class 2, type A (703B002) | SF | 113 | $11.00 | $8.10 | $5.65 | $5.46 | $6.00 | $9.00 |
| 0550 | Pavement markers, class A-H, type 2-C (705A030) | EACH | 22 | $20.00 | $8.10 | $5.65 | $5.46 | $6.00 | $9.00 |
| 0560 | Pavement markers, class A-H, type 2-D (705A037) | EACH | 24 | $20.00 | $8.10 | $5.65 | $5.46 | $6.00 | $9.00 |
| 0570 | Class 9, aluminum flat sign panels (type XI background) (710A153) | SF | 7 | $30.00 | $26.15 | $36.16 | $24.97 | $26.00 | $36.00 |
| 0580 | Class 9, aluminum flat sign panels (type XI background, fluorescent) (710A154) | SF | 12 | $32.00 | $26.15 | $38.42 | $24.97 | $26.00 | $42.00 |
| 0590 | Class 4, aluminum flat sign panels (type IV background) (710A171) | SF | 96 | $29.00 | $23.88 | $27.12 | $22.80 | $24.00 | $30.00 |
| 0600 | Roadway sign post (#3 U channel, galvanized steel or 2 ", 14 GA square tubular steel) (710B021) | LF | 104 | $22.00 | $21.60 | $31.64 | $20.63 | $22.00 | $22.00 |
| 0610 | Removal of existing roadway signs (710C000) | LS | 1 | $604.00 | $397.89 | $500.00 | $380.01 | $400.00 | $4,150.00 |
| 0620 | Truck mounted impact attenuator unit (728A000) | EACH | 1 | $6,050.00 | $38,854 | $10,000 | $4,999.99 | $30,500 | $47,200 |
| 0630 | Furnishing and installing traffic control unit ( SR-3 (US-31) at sparkman street northwest) (730C000) | LS | 1 | $9,600.00 | $8,640.00 | $9,040.00 | $8,686.05 | $8,960.00 | $11,000 |
| 0640 | Metal traffic signal pole foundation (730E000) | EACH | 4 | $2,400.00 | $2,160.00 | $2,260.00 | $2,171.51 | $2,240.00 | $3,000.00 |
| 0650 | Metal traffic signal pole with 55' mast arm assembly (730F000) | EACH | 1 | $47,000 | $42,120 | $44,070 | $42,344 | $43,680 | $48,000 |
| 0660 | Metal traffic signal pole with 60' mast arm assembly (730F001) | EACH | 3 | $52,000 | $46,440 | $48,590 | $46,688 | $48,160 | $53,000 |
| 0670 | Traffic signal junction box type S2 (730K002) | EACH | 4 | $545.00 | $486.00 | $508.50 | $488.59 | $505.00 | $550.00 |
| 0680 | 1", non-metallic, conduit (730L003) | LF | 40 | $3.50 | $3.24 | $3.39 | $3.26 | $3.50 | $4.00 |
| 0690 | 2", non-metallic, conduit (730L005) | LF | 580 | $7.00 | $6.48 | $6.78 | $6.51 | $7.00 | $8.00 |
| 0700 | Luminaire extension assembly, 12' (730N000) | EACH | 4 | $2,600.00 | $2,376.00 | $2,486.00 | $2,388.66 | $2,464.00 | $2,800.00 |
| 0710 | Vehicular signal head, 12 inch, 3 (730P022) | EACH | 6 | $1,200.00 | $1,080.00 | $1,130.00 | $1,085.76 | $1,120.00 | $1,300.00 |
| 0720 | Vehicular signal head, 12 inch, 4 (730P023) | EACH | 2 | $1,500.00 | $1,404.00 | $1,469.00 | $1,411.48 | $1,456.00 | $1,600.00 |
| 0730 | Vehicular signal head, 12 inch, 5 (730P024) | EACH | 2 | $1,500.00 | $1,404.00 | $1,469.00 | $1,411.48 | $1,456.00 | $1,600.00 |
| 0740 | Controller assembly, type NEMA, 16 channels (730R041) | EACH | 1 | $21,500 | $19,440 | $20,340 | $19,544 | $20,160 | $21,921 |
| 0750 | Electrical power service assembly with wood pole (730T010) | EACH | 1 | $1,800.00 | $1,620.00 | $1,695.00 | $1,628.63 | $1,680.00 | $1,800.00 |
| 0760 | Video detection system ( SR-3 (US- 31) at sparkman street northwest) (730U015) | LS | 1 | $32,000 | $28,620 | $29,945 | $28,773 | $29,680 | $31,000 |
| 0770 | Construction signs (740B000) | SF | 1,100 | $7.00 | $6.83 | $7.91 | $6.51 | $7.00 | $6.50 |
| 0780 | Channelizing drums (740D000) | EACH | 500 | $19.50 | $27.28 | $39.55 | $26.06 | $50.00 | $65.00 |
| 0790 | Cones (36 inches high) (740E000) | EACH | 250 | $12.00 | $21.60 | $22.60 | $44.03 | $25.00 | $29.00 |
| 0800 | Barricades, type III (740F002) | EACH | 5 | $99.00 | $238.73 | $248.60 | $228.01 | $235.00 | $350.00 |
| 0810 | Portable sequential arrow and chevron sign unit (741C010) | EACH | 2 | $1,100.00 | $1,841.69 | $1,695.00 | $1,758.93 | $2,000.00 | $2,200.00 |
| 0820 | Roadway luminaire assembly with one, LED, 400 watt equivalent luminaire (750B602) | EACH | 7 | $12,000 | $10,800 | $11,300 | $10,858 | $11,200 | $11,866 |
| 0830 | Pole foundation,roadway (750C010) | EACH | 8 | $1,800.00 | $1,620.00 | $1,695.00 | $1,628.63 | $1,680.00 | $1,800.00 |
| 0840 | Electrical junction box,type 1 (750D200) | EACH | 2 | $450.00 | $405.00 | $423.75 | $407.16 | $420.00 | $450.00 |
| 0850 | Conduit,2 inch,rigid nonmetallic (750E115) | LF | 20 | $9.50 | $8.64 | $9.04 | $8.69 | $9.00 | $10.00 |
| 0860 | Combined duct and cable,2 #6 AWG/ 1 #6 AWG GND (750G010) | LF | 2,100 | $8.00 | $7.56 | $7.91 | $7.60 | $8.00 | $8.00 |
| 0870 | Remove & store roadway luminaire assembly (751G025) | EACH | 1 | $600.00 | $540.00 | $565.00 | $542.87 | $560.00 | $600.00 |
| 0880 | Install state property roadway luminaire assembly (751I000) | EACH | 1 | $600.00 | $540.00 | $565.00 | $542.87 | $560.00 | $600.00 |
| 0885 | Remove luminaire pole foundation, concrete (751J006) | EACH | 1 | $120.00 | $108.00 | $2,000.00 | $1,080.27 | $112.00 | $120.00 |
| 0890 | 5" electrical conduit, 1 line, type 5 installation (756A023) | LF | 755 | $54.00 | $48.60 | $113.00 | $43.21 | $50.00 | $53.00 |
| 0900 | 6" electrical conduit, 1 line, type 5 installation (756A028) | LF | 414 | $54.00 | $48.60 | $50.85 | $48.61 | $50.00 | $53.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ALDOT's tabulation for this contract. ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
Every contract let that day: ALDOT letting of August 28, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.