ALDOT letting results, December 5, 2025
28 contracts let by Alabama DOT on December 5, 2025, $125,374,591 in low bids, a median of 3 bidders per contract.
- Owner
- Alabama DOT
- Contracts
- 28
- Low bids, total
- $125,374,591
- Data through
- 28 AUG 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Source |
|---|---|---|---|---|---|---|---|---|
| 20251205021 | RECONSTRUCTION/REHABILITATION AND RESURFACING ON I-59 FROM A POINT 1.000 MILE NORTH OF THE SR-7 (US-11) INTERCHANGE IN FORT PAYNE TO THE GEORGIA STATE LINE | 0103 | 3 | Wiregrass Construction Company, Inc. | $47,544,197 | $49,525,000 | +4.0% | ALDOT |
| 20251205003 | BRIDGE REPLACEMENT ON SR-13 (US-43) OVER COLD CREEK NORTH OF CREOLA | 0901 | 4 | McInnis Construction, LLC | $8,628,811 | $9,864,534 | +14% | ALDOT |
| 20251205002 | BRIDGE REPLACEMENT (GRADE, DRAIN, PAVE, LIGHTING, & BRIDGE) ON SR-2 (US-72) OVER SR-20 IN FLORENCE | 0201 | 3 | Miller & Miller, Inc. | $7,247,268 | $7,788,353 | +7.0% | ALDOT |
| 20251205001 | BRIDGE PAINTING TO INCLUDE BRIDGE JOINT REPAIR (NBR ONLY) ON SR-1 (US-431) OVER THE TENNESSEE RIVER TO INCLUDE BRIDGE JOINT REPAIR ON THE NORTHBOUND ROADWAY | 0104 | 11 | Cekra, Inc | $6,692,309 | $7,772,988 | +16% | ALDOT |
| 20251205029 | PLANING, RESURFACING, AND TRAFFIC STRIPE ON SR-1 (US-431) FROM THE JUNCTION OF SPEIGNER STREET IN DOTHAN TO THE JUNCTION OF WILLIAM J. PARKER DRIVE IN HEADLAND | 0701 | 2 | Apac-Alabama, Inc. | $5,162,692 | $6,781,996 | +31% | ALDOT |
| 20251205048 | PLANING, RESURFACING, BRIDGE GUARDRAIL RETROFIT, AND STRIPE ON SR-17 FROM THE JUNCTION OF DESOTO ROAD IN BUTLER TO THE SUMTER COUNTY LINE | 0802 | 2 | S. T. Bunn Construction Company, Inc. | $4,730,609 | $5,319,565 | +12% | ALDOT |
| 20251205030 | PLANING, MICRO-MILLING, RESURFACING, AND TRAFFIC STRIPE ON SR-24 FROM A POINT 0.330 MILE WEST OF THE JUNCTION OF SR- 247 TO A POINT 0.260 MILE WEST OF THE INTER | 0202 | 3 | Rogers Group, Inc. | $4,677,199 | $4,972,327 | +6.0% | ALDOT |
| 20251205044 | PLANING, RESURFACING, AND TRAFFIC STRIPE ON SR-14 FROM THE MACON COUNTY LINE TO THE SR-147 (SHUG JORDAN PARKWAY) INTERCHAGNE IN AUBURN | 0606 | 1 | East Alabama Paving Company, Inc. | $4,461,197 | ALDOT | ||
| 20251205056 | MICRO-MILLING, RESURFACE, GUARDRAIL INSTALLATION, AND STRIPE ON SR-14 FROM THE MISSISSIPPI STATE LINE TO THE INTERSECTION OF CR-78 IN PICKENSVILLE | 1003 | 1 | S. T. Bunn Construction Company, Inc. | $3,956,329 | ALDOT | ||
| 20251205034 | RESURFACING, BRIDGE GUARDRAIL RETROFIT, AND TRAFFIC STRIPE ON SR-12 (US-84) FROM THE JUNCTION OF NORTH ENGLEWOOD AVENUE TO THE INTERSECTION OF SR-210 (US-431/RO | 0701 | 2 | Apac-Alabama, Inc. | $3,276,723 | $3,914,768 | +19% | ALDOT |
| 20251205051 | SAFETY WIDEN, MICRO-MILL, RESURFACE (SCRUB SEAL), AND STRIPE ON SR-14 FROM THE JUNCTION OF CR-119 TO THE JUNCTION OF SR-39 NORTHWEST OF EUTAW | 1003 | 1 | S. T. Bunn Construction Company, Inc. | $3,048,000 | ALDOT | ||
| 20251205047 | MICRO-MILLING, RESURFACING (SCRUB SEAL), AND TRAFFIC STRIPE ON SR-118 (US-43) FROM THE INTERSECTION OF SR-171 TO A POINT 0.430 MILE EAST OF THE INTERSECTION OF | 1009 | 2 | S. T. Bunn Construction Company, Inc. | $2,766,269 | $3,248,951 | +17% | ALDOT |
| 20251205031 | RESURFACING (SCRUB SEAL), GUARDRAIL INSTALLATION, AND STRIPE ON SR-35 FROM THE JUNCTION OF SR-9 TO THE JUNCTION OF SR-273 | 0105 | 2 | Wiregrass Construction Company, Inc. | $2,752,825 | $2,793,191 | +1.0% | ALDOT |
| 20251205008 | ROADWAY AND SAFETY (PEDESTRIAN MODIFICATIONS) IMPROVEMENTS ON RICKWOOD ROAD FROM THE JUNCTION OF CHISHOLM ROAD TO THE INTERSECTION OF SR-17 (HELTON DRIVE) IN FL | 0201 | 5 | Grayson Carter & Son Contracting, Inc. | $2,628,140 | $2,687,695 | +2.0% | ALDOT |
| 20251205036 | MICRO-MILLING, RESURFACING (SCRUB SEAL), AND TRAFFIC STRIPE ON SR-74 (US-278) FROM THE WINSTON COUNTY LINE TO THE INTERSECTION OF CR-867 EAST OF CULLMAN | 0104 | 4 | Grayson Carter & Son Contracting, Inc. | $2,389,820 | $2,679,225 | +12% | ALDOT |
| 20251205041 | MICRO-MILLING, RESURFACING, AND TRAFFIC STRIPE ON SR-134 FROM THE DALE COUNTY LINE TO THE INTERSECTION OF SR-1 (US- 431) IN HEADLAND | 0701 | 3 | Wiregrass Construction Company, Inc. | $2,064,964 | $2,171,873 | +5.0% | ALDOT |
| 20251205055 | SAFETY WIDEN, MICRO-MILL, RESURFACE, GUARDRAIL, AND STRIPE ON SR-3 (US-31) FROM THE CULLMAN COUNTY LINE TO THE JUNCTION OF LACON ROAD SOUTH OF FALKVILLE | 0204 | 4 | Wiregrass Construction Company, Inc. | $1,907,791 | $2,166,830 | +14% | ALDOT |
| 20251205046 | RESURFACING, GUARDRAIL INSTALLATION, AND TRAFFIC STRIPE ON SR-109 FROM THE FLORIDA STATE LINE TO THE JUNCTION OF SR-1 (US-231) SOUTHEAST OF REHOBETH | 0701 | 3 | Wiregrass Construction Company, Inc. | $1,860,350 | $2,077,554 | +12% | ALDOT |
| 20251205065 | INTERSECTION IMPROVEMENTS ON SR-13 (US-43) AT ROSE BOULEVARD/MITT LARY ROAD IN NORTHPORT | 0502 | 7 | GFC Construction, Inc. | $1,858,695 | $2,031,385 | +9.0% | ALDOT |
| 20251205059 | ROADWAY IMPROVEMENTS (CHANGE TRAFFIC FLOW AND TURN RADIUS) ON SR-53 (US-231 AND US-411)/COURTHOUSE SQUARE AND SR-25 (US-411) IN ASHVILLE | 0302 | 5 | Bulls Construction Group, LLC | $1,263,317 | $1,337,337 | +6.0% | ALDOT |
| 20251205015 | ROADWAY/INTERSECTION SAFETY IMPROVEMENTS ON SR-12- (US-84) AT SR-141 SOUTHWEST OF ELBA | 0702 | 4 | Wiregrass Construction Company, Inc. | $1,184,779 | $1,351,460 | +14% | ALDOT |
| 20251205049 | RESURFACE, TRAFFIC SIGNAL UPGRADES, GUARDRAIL, AND STRIPE ON SR-215 (GREENSBORO AVENUE) FROM THE INTERSECTION OF SR-7 (US-11/SKYLAND BOLUVARD) TO THE INTERSECTI | 0502 | 2 | Apac-Alabama, Inc. | $1,081,095 | $1,184,197 | +10% | ALDOT |
| 20251205016 | INTERSECTION MODIFICATIONS (ROUNDABOUT INSTALLATION) ON CR-109 (EAST LIMESTONE ROAD) AT CR-36 (CAPSHAW ROAD) SOUTHEAST OF ATHENS | 0202 | 5 | Wiregrass Construction Company, Inc. | $936,511 | $972,912 | +4.0% | ALDOT |
| 20251205062 | INTERSECTION IMPROVEMENTS (GRADE, DRAIN, PAVE, AND STRIPE) ON SR-12 (US-84) AT BROADWAY STREET IN ASHFORD | 0701 | 4 | Apac-Alabama, Inc. | $821,926 | $1,014,892 | +23% | ALDOT |
| 20251205014 | ROADWAY SAFETY IMPROVEMENTS (SUPERELEVATION MODIFICATIONS) ON SR-10 FROM A POINT NEAR MP 130.881 TO A POINT NEAR MP 131.583 SOUTHEAST OF GREENVILLE | 0604 | 1 | Apac-Alabama, Inc. | $784,000 | ALDOT | ||
| 20251205011 | ROADWAY LIGHTING ON SR-24 FROM THE INTERSECTION OF 9TH STREET SOUTHWEST TO THE JUNCTION OF MCCARTHY DRIVE IN RED BAY | 0202 | 4 | Big River Electric, Inc. | $709,161 | $765,120 | +8.0% | ALDOT |
| 20251205018 | ROADWAY SAFETY IMPROVEMENTS (HORIZONTAL CURVE UPGRADES) ON I-20/59, I-65, AND I-359 AT VARIOUS LOCATIONS IN THE WEST CENTRAL REGION AS INDICATED IN THE PLANS | 0502, 0504, | 1 | Superior Traffic Control, LLC | $587,134 | ALDOT | ||
| 20251205026 | ROADWAY SAFETY IMPROVEMENTS ON CR-54 FROM THE MACON COUNTY LINE TO THE INTRERSECTION OF CR-146 (MOORE'S MILL ROAD) SOUTH EAST OF AUBURN | 0606 | 1 | East Alabama Paving Company, Inc. | $352,479 | ALDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ALDOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.
Your own bid history, read the same way