McInnis Construction, LLC: ALDOT bid record
McInnis Construction, LLC submitted 28 bids on Alabama DOT contracts in the data, from 25 MAR 2022 to 27 MAR 2026, and was the low bidder on 11 of them (39%). When it was not low, its total sat a median +17% above the low bid.
- Owner
- Alabama DOT
- Low bid volume
- $271,789,750
- Latest bid
- 27 MAR 2026
- Data through
- 28 AUG 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 7 | 2 | 29% |
| 2023 | 5 | 2 | 40% |
| 2024 | 8 | 2 | 25% |
| 2025 | 6 | 4 | 67% |
| 2026 | 2 | 1 | 50% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| 0602 | 3 | 2 | 67% |
| 0301 | 3 | 2 | 67% |
| 0202 | 2 | 0 | 0% |
| 0901 | 2 | 1 | 50% |
| 0606 | 2 | 1 | 50% |
| 1008 | 1 | 0 | 0% |
| 0201 | 1 | 0 | 0% |
| 0802 | 1 | 0 | 0% |
| 0903 | 1 | 1 | 100% |
| 05 | 1 | 0 | 0% |
| 0502 | 1 | 0 | 0% |
| 0605 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Steel reinforcement | 502A000 | LB | 27 | 17 (63%) | $1.39 | $2.00 |
| Trainee hours at 80 cents per hour | 999 000 | HR | 15 | 15 (100%) | $0.80 | $0.80 |
| Reinforced cement concrete bridge end slab | 450B000 | SY | 27 | 12 (44%) | $260.65 | $264.40 |
| Grooving concrete bridge decks | 510E000 | SY | 26 | 11 (42%) | $5.93 | $5.92 |
| Cones (36 inches high) | 740E000 | EACH | 23 | 11 (48%) | $22.61 | $20.47 |
| Topsoil | 650A000 | CY | 25 | 10 (40%) | $34.65 | $45.00 |
| Bridge barrier rail, type 36” single slope | 510J000 | LF | 21 | 10 (48%) | $106.09 | $105.00 |
| Bridge substructure concrete | 510A007 | CY | 28 | 9 (32%) | $1,664.93 | $1,377.50 |
| Removing guardrail | 206D001 | LF | 22 | 9 (41%) | $4.11 | $4.37 |
| Construction signs | 740B000 | SF | 28 | 8 (29%) | $7.67 | $7.00 |
| Structural steel | 508A000 | LB | 28 | 7 (25%) | $10.12 | $8.00 |
| Barricades, type III | 740F002 | EACH | 23 | 7 (30%) | $258.30 | $252.14 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| The Bridge Builders of Alabama, LLC | 11 | 8 of 11 |
| Murphree Bridge Corporation | 9 | 6 of 9 |
| Wright Brothers Construction Company, Inc. | 7 | 1 of 7 |
| Scott Bridge Company, Inc. | 6 | 0 of 6 |
| Newell & Bush, Inc. | 6 | 5 of 6 |
| Miller & Miller, Inc. | 4 | 4 of 4 |
| Ikaros, LLC | 4 | 0 of 4 |
| Riley Bridge Company, Inc. | 3 | 3 of 3 |
| Dement Construction Company, LLC | 3 | 0 of 3 |
| Century Construction Group, Inc. | 2 | 1 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 27 MAR 2026 | 20260327001 | 0606 | BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE REMOVAL) ON I-85 OVER CHOCTAFAULA CREEK SOUTHWEST OF AUBURN | 2 of 2 | $22,676,768 | +22% |
| 30 JAN 2026 | 20260130003 | 0504 | BRIDGE REPLACEMENT (GRADE, DRAIN, PAVE, ITS, AND BRIDGE) ON I-65 (DUAL BRIDGES) OVER WALNUT CREEK IN CLANTON | 1 of 3 | $22,203,640 | Low, 3.0% under the second |
| 05 DEC 2025 | 20251205003 | 0901 | BRIDGE REPLACEMENT ON SR-13 (US-43) OVER COLD CREEK NORTH OF CREOLA | 1 of 4 | $8,628,811 | Low, 14% under the second |
| 07 NOV 2025 | 20251107053 | 0301 | BRIDGE REPLACEMENT AND BRIDGE REHABILITATION ON OLD BROOK TRAIL OVER LITTLE SHADES CREEK (SITE 1) AND ON CANTERBURY ROAD OVER WATKINS CREEK | 1 of 2 | $3,989,333 | Low, 3.0% under the second |
| 26 SEP 2025 | 20250926005 | 1003 | BRIDGE REPLACEMENT (GRADE, DRAIN, PAVE, AND BRIDGE REMOVAL) ON SR-14 OVER THE SIPSEY RIVER | 1 of 3 | $8,191,559 | Low, 2.0% under the second |
| 27 JUN 2025 | 20250627001 | 03 | BRIDGE REPLACEMENT AND APPROACHES (GRADE, DRAIN, PAVE) ON SR-53 OVER THE BLACKBURN FORK OF THE LITTLE WARRIOR RIVER | 4 of 4 | $4,323,204 | +17% |
| 28 MAR 2025 | 20250328001 | 0301 | BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE) ON SR-119 OVER SHEPHARD BRANCH | 4 of 4 | $5,905,723 | +57% |
| 31 JAN 2025 | 20250131001 | 0305 | GRADE, DRAIN, PAVE, BRIDGE REMOVAL, AND BRIDGE REPLACEMENT ON I-65 FROM A POINT 0.560 MILE SOUTH OF BUCK CREEK TO A POINT 1.000 MILE NORTH O | 1 of 2 | $66,962,022 | Low, 21% under the second |
| 08 NOV 2024 | 20241108004 | 0404 | BRIDGE REPLACEMENT (GRADE, DRAIN, PAVE, AND BRIDGE REMOVAL) ON SR-1 (US-431) OVER CORNHOUSE CREEK SOUTHEAST OF WEDOWEE | 2 of 2 | $4,420,534 | +6.0% |
| 08 NOV 2024 | 20241108007 | 0105 | BRIDGE REPLACEMENT AND APPROACHES ON SR-273 OVER DANIEL'S BRANCH NORTHEAST OF LEESBURG | 1 of 2 | $5,677,704 | Low, 7.0% under the second |
| 08 NOV 2024 | 20241108013 | 0405 | BRIDGE REPLACEMENT AND APPROACHES ON CR-303 (BERNEY STATION ROAD) OVER DRY CREEK SOUTH OF TALLADEGA | 4 of 4 | $2,939,221 | +46% |
| 27 SEP 2024 | 20240927003 | 0602 | BRIDGE WIDENING ON I-85 (SOUTHBOUND ROADWAY) OVER MILES CREEK TO ACCOMMODATE THE DECELERATION LANE EXTENSION AT SR-186 | 2 of 3 | $3,118,322 | +15% |
| 30 AUG 2024 | 20240830002 | 0202 | BRIDGE REPLACEMENT AND APPROACHES ON SR-247 OVER LITTLE BEAR CREEK NORTHEAST OF RED BAY | 2 of 4 | $3,548,080 | +7.0% |
| 31 MAY 2024 | 20240531038 | 0902 | NEW ROADWAY CONSTRUCTION OF THE SR-161 CONNECTOR FROM A POINT NORTH OF THE JUNCTION OF CR-4 TO THE JUNCTION OF THE FOLEY BEACH EXPRESS | 2 of 4 | $30,670,264 | +2.0% |
| 29 MAR 2024 | 20240329001 | 0301 | BASE, PAVE, AND BRIDGES ON THE BIRMINGHAM NORTHERN BELTLINE FROM THE JUNCTION OF SR-79 TO THE JUNCTION OF SR-75 (PARTIAL), EXCLUDING RAMP C | 1 of 3 | $64,777,597 | Low, 11% under the second |
| 29 MAR 2024 | 20240329004 | 0401 | BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE) ON SR-50 OVER WIND CREEK NORTHWEST OF REELTOWN | 3 of 3 | $4,168,063 | +23% |
| 03 NOV 2023 | 20231103001 | 0605 | BRIDGE REPLACEMENT ON SR-14 AT BLUE GURTH SWAP EAST OF SELMA | 4 of 4 | $4,957,757 | +46% |
| 29 SEP 2023 | 20230929001 | 0502 | BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE) ON SR-7 (US-11) OVER THE NORFOLK SOUTHERN RAILWAY IN COTTONDALE | 2 of 3 | $8,679,781 | +40% |
| 28 JUL 2023 | 20230728018 | 0606 | BRIDGE WIDENING ON I-85 (NORTHBOUND AND SOUTHBOUND ROADWAYS) OVER HALAWAKEE CREEK SOUTHWEST OF THE CHAMBERS COUNTY LINE | 1 of 2 | $6,331,271 | Low, 18% under the second |
| 30 JUN 2023 | 20230630001 | 05 | BRIDGE REPLACEMENT AND INTERSECTION IMPROVEMENTS ON SR-5 OVER THE SR-69 (US-78A) UNDERPASS IN JASPER | 2 of 2 | $9,166,442 | +4.0% |
| 27 JAN 2023 | 20230127018 | 0602 | BRIDGE WIDENING ON I-85 (NORTHBOUND AND SOUTHBOUND) OVER LINE CREEK AND RELIEF BRIDGES | 1 of 2 | $33,757,712 | Low, 54% under the second |
| 30 SEP 2022 | 20220930025 | 0903 | BRIDGE REPLACEMENTS (GRADE, DRAIN, PAVE, AND BRIDGE) ON I-65 OVER THE SEPULGA RIVER AND RELIEF NORTHEAST OF EVERGREEN | 1 of 2 | $40,870,428 | Low, 15% under the second |
| 26 AUG 2022 | 20220826004 | 0602 | BRIDGE REPLACEMENT ON SR-81 OVER UPHAPEE CREEK NORTH OF TUSKEGEE | 1 of 4 | $10,399,673 | Low, 16% under the second |
| 29 JUL 2022 | 20220729001 | 0202 | BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE) ON SR-247 OVER CEDAR CREEK | 3 of 6 | $5,590,569 | +26% |
| 29 JUL 2022 | 20220729003 | 0901 | BRIDGE REPLACEMENT ON SR-217 OVER BIG CREEK SOUTHWEST OF CITRONELLE | 2 of 2 | $3,877,459 | +5.0% |
How this record was read
ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
- Every bid counted here matched its published total to within one dollar; ALDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.