McInnis Construction, LLC: ALDOT bid record

McInnis Construction, LLC submitted 28 bids on Alabama DOT contracts in the data, from 25 MAR 2022 to 27 MAR 2026, and was the low bidder on 11 of them (39%). When it was not low, its total sat a median +17% above the low bid.

Owner
Alabama DOT
Low bid volume
$271,789,750
Latest bid
27 MAR 2026
Data through
28 AUG 2026
28Bids
11Low bids
39Win rate, percent
+17%Median gap to the low bid when not low, 17 bids

By year

YearBidsLow bidsWin rate
20227229%
20235240%
20248225%
20256467%
20262150%
McInnis Construction, LLC, ALDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
06023267%
03013267%
0202200%
09012150%
06062150%
1008100%
0201100%
0802100%
090311100%
05100%
0502100%
0605100%
McInnis Construction, LLC, ALDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Steel reinforcement502A000LB2717 (63%)$1.39$2.00
Trainee hours at 80 cents per hour999 000HR1515 (100%)$0.80$0.80
Reinforced cement concrete bridge end slab450B000SY2712 (44%)$260.65$264.40
Grooving concrete bridge decks510E000SY2611 (42%)$5.93$5.92
Cones (36 inches high)740E000EACH2311 (48%)$22.61$20.47
Topsoil650A000CY2510 (40%)$34.65$45.00
Bridge barrier rail, type 36” single slope510J000LF2110 (48%)$106.09$105.00
Bridge substructure concrete510A007CY289 (32%)$1,664.93$1,377.50
Removing guardrail206D001LF229 (41%)$4.11$4.37
Construction signs740B000SF288 (29%)$7.67$7.00
Structural steel508A000LB287 (25%)$10.12$8.00
Barricades, type III740F002EACH237 (30%)$258.30$252.14
McInnis Construction, LLC, ALDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

FirmContracts in commonThat firm ranked ahead
The Bridge Builders of Alabama, LLC118 of 11
Murphree Bridge Corporation96 of 9
Wright Brothers Construction Company, Inc.71 of 7
Scott Bridge Company, Inc.60 of 6
Newell & Bush, Inc.65 of 6
Miller & Miller, Inc.44 of 4
Ikaros, LLC40 of 4
Riley Bridge Company, Inc.33 of 3
Dement Construction Company, LLC30 of 3
Century Construction Group, Inc.21 of 2
McInnis Construction, LLC, ALDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
27 MAR 2026202603270010606BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE REMOVAL) ON I-85 OVER CHOCTAFAULA CREEK SOUTHWEST OF AUBURN2 of 2$22,676,768+22%
30 JAN 2026202601300030504BRIDGE REPLACEMENT (GRADE, DRAIN, PAVE, ITS, AND BRIDGE) ON I-65 (DUAL BRIDGES) OVER WALNUT CREEK IN CLANTON1 of 3$22,203,640Low, 3.0% under the second
05 DEC 2025202512050030901BRIDGE REPLACEMENT ON SR-13 (US-43) OVER COLD CREEK NORTH OF CREOLA1 of 4$8,628,811Low, 14% under the second
07 NOV 2025202511070530301BRIDGE REPLACEMENT AND BRIDGE REHABILITATION ON OLD BROOK TRAIL OVER LITTLE SHADES CREEK (SITE 1) AND ON CANTERBURY ROAD OVER WATKINS CREEK 1 of 2$3,989,333Low, 3.0% under the second
26 SEP 2025202509260051003BRIDGE REPLACEMENT (GRADE, DRAIN, PAVE, AND BRIDGE REMOVAL) ON SR-14 OVER THE SIPSEY RIVER1 of 3$8,191,559Low, 2.0% under the second
27 JUN 20252025062700103BRIDGE REPLACEMENT AND APPROACHES (GRADE, DRAIN, PAVE) ON SR-53 OVER THE BLACKBURN FORK OF THE LITTLE WARRIOR RIVER4 of 4$4,323,204+17%
28 MAR 2025202503280010301BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE) ON SR-119 OVER SHEPHARD BRANCH4 of 4$5,905,723+57%
31 JAN 2025202501310010305GRADE, DRAIN, PAVE, BRIDGE REMOVAL, AND BRIDGE REPLACEMENT ON I-65 FROM A POINT 0.560 MILE SOUTH OF BUCK CREEK TO A POINT 1.000 MILE NORTH O1 of 2$66,962,022Low, 21% under the second
08 NOV 2024202411080040404BRIDGE REPLACEMENT (GRADE, DRAIN, PAVE, AND BRIDGE REMOVAL) ON SR-1 (US-431) OVER CORNHOUSE CREEK SOUTHEAST OF WEDOWEE2 of 2$4,420,534+6.0%
08 NOV 2024202411080070105BRIDGE REPLACEMENT AND APPROACHES ON SR-273 OVER DANIEL'S BRANCH NORTHEAST OF LEESBURG1 of 2$5,677,704Low, 7.0% under the second
08 NOV 2024202411080130405BRIDGE REPLACEMENT AND APPROACHES ON CR-303 (BERNEY STATION ROAD) OVER DRY CREEK SOUTH OF TALLADEGA4 of 4$2,939,221+46%
27 SEP 2024202409270030602BRIDGE WIDENING ON I-85 (SOUTHBOUND ROADWAY) OVER MILES CREEK TO ACCOMMODATE THE DECELERATION LANE EXTENSION AT SR-1862 of 3$3,118,322+15%
30 AUG 2024202408300020202BRIDGE REPLACEMENT AND APPROACHES ON SR-247 OVER LITTLE BEAR CREEK NORTHEAST OF RED BAY2 of 4$3,548,080+7.0%
31 MAY 2024202405310380902NEW ROADWAY CONSTRUCTION OF THE SR-161 CONNECTOR FROM A POINT NORTH OF THE JUNCTION OF CR-4 TO THE JUNCTION OF THE FOLEY BEACH EXPRESS2 of 4$30,670,264+2.0%
29 MAR 2024202403290010301BASE, PAVE, AND BRIDGES ON THE BIRMINGHAM NORTHERN BELTLINE FROM THE JUNCTION OF SR-79 TO THE JUNCTION OF SR-75 (PARTIAL), EXCLUDING RAMP C1 of 3$64,777,597Low, 11% under the second
29 MAR 2024202403290040401BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE) ON SR-50 OVER WIND CREEK NORTHWEST OF REELTOWN3 of 3$4,168,063+23%
03 NOV 2023202311030010605BRIDGE REPLACEMENT ON SR-14 AT BLUE GURTH SWAP EAST OF SELMA4 of 4$4,957,757+46%
29 SEP 2023202309290010502BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE) ON SR-7 (US-11) OVER THE NORFOLK SOUTHERN RAILWAY IN COTTONDALE2 of 3$8,679,781+40%
28 JUL 2023202307280180606BRIDGE WIDENING ON I-85 (NORTHBOUND AND SOUTHBOUND ROADWAYS) OVER HALAWAKEE CREEK SOUTHWEST OF THE CHAMBERS COUNTY LINE1 of 2$6,331,271Low, 18% under the second
30 JUN 20232023063000105BRIDGE REPLACEMENT AND INTERSECTION IMPROVEMENTS ON SR-5 OVER THE SR-69 (US-78A) UNDERPASS IN JASPER2 of 2$9,166,442+4.0%
27 JAN 2023202301270180602BRIDGE WIDENING ON I-85 (NORTHBOUND AND SOUTHBOUND) OVER LINE CREEK AND RELIEF BRIDGES1 of 2$33,757,712Low, 54% under the second
30 SEP 2022202209300250903BRIDGE REPLACEMENTS (GRADE, DRAIN, PAVE, AND BRIDGE) ON I-65 OVER THE SEPULGA RIVER AND RELIEF NORTHEAST OF EVERGREEN1 of 2$40,870,428Low, 15% under the second
26 AUG 2022202208260040602BRIDGE REPLACEMENT ON SR-81 OVER UPHAPEE CREEK NORTH OF TUSKEGEE1 of 4$10,399,673Low, 16% under the second
29 JUL 2022202207290010202BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE) ON SR-247 OVER CEDAR CREEK3 of 6$5,590,569+26%
29 JUL 2022202207290030901BRIDGE REPLACEMENT ON SR-217 OVER BIG CREEK SOUTHWEST OF CITRONELLE2 of 2$3,877,459+5.0%
McInnis Construction, LLC: latest ALDOT bids in the data

How this record was read

ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.

  • Every bid counted here matched its published total to within one dollar; ALDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy