Wright Brothers Construction Company, Inc. submitted 21 bids on Alabama DOT contracts in the data, from 25 MAR 2022 to 30 JAN 2026, and was the low bidder on 2 of them (10%). When it was not low, its total sat a median +24% above the low bid.
- Owner
- Alabama DOT
- Low bid volume
- $12,135,866
- Latest bid
- 30 JAN 2026
- Data through
- 28 AUG 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 5 | 1 | 20% |
| 2023 | 9 | 1 | 11% |
| 2024 | 4 | 0 | 0% |
| 2025 | 1 | 0 | 0% |
| 2026 | 2 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| 0301 | 4 | 1 | 25% |
| 0302 | 4 | 0 | 0% |
| 1008 | 2 | 0 | 0% |
| 0202 | 2 | 0 | 0% |
| 0504 | 2 | 0 | 0% |
| 0201 | 1 | 0 | 0% |
| 0103 | 1 | 0 | 0% |
| 05 | 1 | 1 | 100% |
| 1003 | 1 | 0 | 0% |
| 0502 | 1 | 0 | 0% |
| 0305 | 1 | 0 | 0% |
| 0105 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Trainee hours at 80 cents per hour | 999 000 | HR | 12 | 12 (100%) | $0.80 | $0.80 |
| Minor structure concrete | 620A000 | CY | 13 | 9 (69%) | $2,500.00 | $2,279.07 |
| Channelizing drums | 740D000 | EACH | 20 | 8 (40%) | $42.25 | $33.00 |
| Right of way markers | 602A000 | EACH | 18 | 8 (44%) | $590.00 | $687.50 |
| Grooving concrete bridge decks | 510E000 | SY | 15 | 7 (47%) | $3.30 | $5.92 |
| Silt fence | 665J002 | LF | 21 | 6 (29%) | $5.70 | $5.00 |
| Silt fence removal | 665O001 | LF | 21 | 6 (29%) | $1.30 | $1.45 |
| Barricades, type III | 740F002 | EACH | 20 | 6 (30%) | $260.50 | $252.14 |
| Steel reinforcement | 502A000 | LB | 19 | 6 (32%) | $1.46 | $2.00 |
| Wattle | 665Q002 | LF | 19 | 5 (26%) | $11.75 | $10.75 |
| Guardrail end anchor, type 20 series (MASH) | 630C080 | EACH | 18 | 5 (28%) | $3,860.00 | $3,785.66 |
| Cones (36 inches high) | 740E000 | EACH | 15 | 5 (33%) | $25.50 | $20.47 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| The Bridge Builders of Alabama, LLC | 7 | 7 of 7 |
| McInnis Construction, LLC | 7 | 6 of 7 |
| Ikaros, LLC | 6 | 6 of 6 |
| Dement Construction Company, LLC | 5 | 1 of 5 |
| Riley Bridge Company, Inc. | 4 | 4 of 4 |
| Miller & Miller, Inc. | 4 | 4 of 4 |
| Chilton Contractors, Inc. | 4 | 3 of 4 |
| Russo Corporation | 3 | 1 of 3 |
| Whitaker Contracting Corporation | 3 | 2 of 3 |
| Wiregrass Construction Company, Inc. | 3 | 2 of 3 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 30 JAN 2026 | 20260130001 | 0105 | BRIDGE REPLACEMENT TO INCLUDE ROADAWAY RE-ALIGNMENT ON SR-205 OVER THE ALABAMA AND TENNESSEE RIVER RAILWAY, LLC (ATN) AND OLD GUNTERSVILLE G | 6 of 6 | $7,453,351 | +53% |
| 30 JAN 2026 | 20260130003 | 0504 | BRIDGE REPLACEMENT (GRADE, DRAIN, PAVE, ITS, AND BRIDGE) ON I-65 (DUAL BRIDGES) OVER WALNUT CREEK IN CLANTON | 3 of 3 | $23,904,776 | +8.0% |
| 25 JUL 2025 | 20250725001 | 0301 | INTERCHANGE MODIFICATIONS ON SR-149 (LAKESHORE PARKWAY) AT THE I-65 INTERCHANGE IN HOMEWOOD | 3 of 7 | $25,278,002 | +8.0% |
| 30 AUG 2024 | 20240830002 | 0202 | BRIDGE REPLACEMENT AND APPROACHES ON SR-247 OVER LITTLE BEAR CREEK NORTHEAST OF RED BAY | 4 of 4 | $3,917,254 | +18% |
| 28 JUN 2024 | 20240628021 | 0305 | BRIDGE REPLACEMENT BRIDGE REPLACEMENT ON CR-55 OVER THE CENTRAL OF GEORGIA RAILWAY SOUTH OF STERRETT | 2 of 2 | $3,879,200 | +20% |
| 29 MAR 2024 | 20240329001 | 0301 | BASE, PAVE, AND BRIDGES ON THE BIRMINGHAM NORTHERN BELTLINE FROM THE JUNCTION OF SR-79 TO THE JUNCTION OF SR-75 (PARTIAL), EXCLUDING RAMP C | 2 of 3 | $71,999,830 | +11% |
| 26 JAN 2024 | 20240126001 | 0302 | BRIDGE REPLACEMENT (GRADE, DRAIN, PAVE, AND BRIDGE) ON SR-79 OVER BLACKBURN FORK OF THE LITTLE WARRIOR RIVER NORTHEAST OF LOCUST FORK | 4 of 5 | $11,938,653 | +30% |
| 25 AUG 2023 | 20230825028 | 0302 | INTERSECTION IMPROVEMENTS (GRADE, DRAIN, PAVEMENT & SIGNAL) ON SR-7 (US-11) AT SR-174 AND CR-9 TO INCLUDE TURN LANE INSTALLATIONS AT ALL FOU | 3 of 4 | $3,144,560 | +30% |
| 28 JUL 2023 | 20230728001 | 1003 | BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE) ON SR-14 OVER LUBBUB CREEK SOUTH OF ALICEVILLE | 2 of 3 | $14,099,935 | +15% |
| 28 JUL 2023 | 20230728005 | 0302 | INTERSECTION IMPROVEMENTS (GRADE, DRAIN, PAVE, AND SIGNALS) ON SR-25 (US-411) AT CR-10 (PARK AVENUE) IN MOODY | 3 of 3 | $1,717,848 | +13% |
| 28 JUL 2023 | 20230728032 | 0502 | BRIDGE REPLACEMENT ON CR-47 OVER TWO MILE CREEK FROM THE JUNCTION OF RED BIRD DRIVE TO THE JUNCTION OF PARK COURT | 3 of 3 | $5,774,811 | +21% |
| 30 JUN 2023 | 20230630001 | 05 | BRIDGE REPLACEMENT AND INTERSECTION IMPROVEMENTS ON SR-5 OVER THE SR-69 (US-78A) UNDERPASS IN JASPER | 1 of 2 | $8,802,655 | Low, 4.0% under the second |
| 30 JUN 2023 | 20230630008 | 0302 | INTERSECTION IMPROVEMENTS ON SR-160 AT THE I-65 INTERCHANGE RAMPS AND AT SR-3 (US-31) IN SMOKE RISE | 3 of 4 | $11,667,001 | +34% |
| 07 APR 2023 | 20230407002 | 0103 | BRIDGE REPLACEMENT AND APPROACHES ON SR-75 OVER TOWN CREEK IN LAKEVIEW | 3 of 4 | $15,693,951 | +15% |
| 27 JAN 2023 | 20230127005 | 1008 | BRIDGE REPLACEMENT AND APPROACHES ON SMITH CHAPEL ROAD OVER MILL CREEK EAST OF CARBON HILL | 3 of 3 | $2,520,933 | +43% |
| 27 JAN 2023 | 20230127008 | 0504 | BRIDGE REPLACEMENTS ON SR-5 OVER BLUE GIRTH CREEK AND BLUE GIRTH CREEK RELIEF | 4 of 4 | $10,799,914 | +29% |
| 29 JUL 2022 | 20220729001 | 0202 | BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE) ON SR-247 OVER CEDAR CREEK | 4 of 6 | $5,623,047 | +27% |
| 29 APR 2022 | 20220429036 | 0301 | ROADWAY IMPROVEMENTS (GRADE, DRAIN, PAVE, SIDEWALK, CULVERT) ON POLLY REED ROAD FROM THE JUNCTION OF SR-75 TO THE JUNCTION OF REED ROAD NORT | 4 of 5 | $12,141,527 | +36% |
| 25 MAR 2022 | 20220325001 | 1008 | BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE) ON CR-64 (BROWNS BRIDGE ROAD) OVER LOST CREEK | 7 of 7 | $2,985,034 | +34% |
| 25 MAR 2022 | 20220325004 | 0301 | PEDESTRIAN BRIDGE (GRADING, BRIDGE, AND LIGHTING) OVER SR-150 BETWEEN BERKLEY AVENUE AND CLARENDON AVENUE IN BESSEMER | 1 of 2 | $3,333,211 | Low, 3.0% under the second |
| 25 MAR 2022 | 20220325055 | 0201 | BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE) ON CR-16 OVER CYPRESS CREEK NORTHWEST OF FLORENCE | 7 of 8 | $6,145,339 | +24% |
How this record was read
ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
- Every bid counted here matched its published total to within one dollar; ALDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.