Ikaros, LLC: ALDOT bid record

Ikaros, LLC submitted 23 bids on Alabama DOT contracts in the data, from 25 FEB 2022 to 31 JUL 2026, and was the low bidder on 6 of them (26%). When it was not low, its total sat a median +19% above the low bid.

Owner
Alabama DOT
Low bid volume
$28,586,500
Latest bid
31 JUL 2026
Data through
28 AUG 2026
23Bids
6Low bids
26Win rate, percent
+19%Median gap to the low bid when not low, 17 bids

By year

YearBidsLow bidsWin rate
2022500%
20236233%
2024200%
20257229%
20263267%
Ikaros, LLC, ALDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
050210440%
03016117%
10032150%
1008100%
0802100%
0505100%
0504100%
0105100%
Ikaros, LLC, ALDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Unclassified excavation210A000CY238 (35%)$25.00$32.97
Right of way markers602A000EACH198 (42%)$600.00$687.50
Trainee hours at 80 cents per hour999 000HR77 (100%)$0.80$0.80
Silt fence665J002LF226 (27%)$4.69$5.00
Silt fence removal665O001LF216 (29%)$1.24$1.45
Foundation backfill, commercial214B001CY146 (43%)$60.00$86.75
Borrow excavation (A4 or better)210D011CY146 (43%)$19.00$23.71
Roadway sign post (#3 U channel, galvanized steel or 2 ", 14 GA square tubular steel)710B021LF155 (33%)$18.91$20.21
Polyethylene665E000SY145 (36%)$3.42$3.56
Pest control treatment666A001ACRE125 (42%)$45.64$115.00
Scoring bituminous pavement surface428A001MI115 (45%)$400.00$486.51
Filter blanket, geotextile610D003SY234 (17%)$6.00$5.47
Ikaros, LLC, ALDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

FirmContracts in commonThat firm ranked ahead
GFC Construction, Inc.85 of 8
Gillespie Construction, LLC73 of 7
Carcel & G. Construction, LLC76 of 7
Wright Brothers Construction Company, Inc.60 of 6
John Plott Company, Inc.42 of 4
The Bridge Builders of Alabama, LLC42 of 4
McInnis Construction, LLC44 of 4
Glasgow Construction Co., Inc.32 of 3
Bulls Construction Group, LLC31 of 3
Cornerstone Civil Contractors, LLC31 of 3
Ikaros, LLC, ALDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
31 JUL 2026202607310010301ROADWAY AND DRAINAGE IMPROVEMENTS (GRADING, DRAINAGE, PAVEMENT (RESURFACING), AND TRAFFIC STRIPE) ON CR-337 (MCCALLA ROAD) FROM THE JUNCTION1 of 6$1,678,000Low, 1.0% under the second
24 APR 2026202604240190502STRUCTURAL REMOVAL ON SR-216 AT THE I-20/I-59 INTERCHANGE (EXIT 100) EAST OF LAKEVIEW1 of 2$191,500Low, 15% under the second
30 JAN 2026202601300010105BRIDGE REPLACEMENT TO INCLUDE ROADAWAY RE-ALIGNMENT ON SR-205 OVER THE ALABAMA AND TENNESSEE RIVER RAILWAY, LLC (ATN) AND OLD GUNTERSVILLE G5 of 6$6,050,000+24%
05 DEC 2025202512050650502INTERSECTION IMPROVEMENTS ON SR-13 (US-43) AT ROSE BOULEVARD/MITT LARY ROAD IN NORTHPORT5 of 7$2,222,000+20%
26 SEP 2025202509260051003BRIDGE REPLACEMENT (GRADE, DRAIN, PAVE, AND BRIDGE REMOVAL) ON SR-14 OVER THE SIPSEY RIVER3 of 3$8,400,000+3.0%
29 AUG 2025202508290090301DRAINAGE IMPROVEMENTS AND PIPE REHABILITATION ON I-459 FROM A POINT NEAR MP 19.280 TO A POINT NEAR MP 19.394 SOUTHEAST OF VESTAVIA HILLS5 of 5$850,000+39%
29 AUG 2025202508290220301RELOACTION AND INTERSECTION IMPROVEMENTS ON LAKESHORE PARKWAY AND MORGAN ROAD FROM CUMBERLAND ROAD TO TURNIN DRIVE IN BESSEMER3 of 6$21,710,000+15%
25 JUL 2025202507250290502INTERSECTION IMPROVEMENTS AND ADDITIONAL THRU LANES ON I-20/I-59 AT THE DAIMLER BENZ BOULEVARD INTERCHANGE (EXIT 89) IN VANCE1 of 4$2,300,000Low, 13% under the second
31 JAN 2025202501310040502BRIDGE REPLACEMENT ON SR-6 (US-82) OVER BIG CREEK IN COKER1 of 2$9,900,000Low, 21% under the second
31 JAN 2025202501310090301REPAIR AND REPLACEMENT OF ENTRANCE AND EXIT RAMPS ON I-20/I-59 AT MCASHAN DRIVE (EXIT 104) AND THE NORTHBOUND AND SOUTHBOUND RAMPS SOUTHWEST2 of 2$19,500,000+10%
30 AUG 2024202408300010502BRIDGE REMOVAL (GRADING, DRAINAGE, BASE, AND PAVEMENT) ON SR-7 (US-11) OVER THE ABANDONED L AND N RAILROAD NEAR CHAMBLEE AVENUE NORTHEAST OF2 of 6$2,430,000+14%
30 AUG 2024202408300250502ROADWAY IMPROVEMENTS (ADDITIONAL CENTER TURN LANE) ON CR-47 (MARTIN LUTHER KING, JR. BOULEVARD) FROM THE JUNCTION OF BRIDGE AVENUE TO THE JU5 of 5$19,000,000+34%
29 SEP 2023202309290010502BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE) ON SR-7 (US-11) OVER THE NORFOLK SOUTHERN RAILWAY IN COTTONDALE3 of 3$9,876,500+59%
28 JUL 2023202307280011003BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE) ON SR-14 OVER LUBBUB CREEK SOUTH OF ALICEVILLE1 of 3$12,255,000Low, 15% under the second
28 JUL 2023202307280320502BRIDGE REPLACEMENT ON CR-47 OVER TWO MILE CREEK FROM THE JUNCTION OF RED BIRD DRIVE TO THE JUNCTION OF PARK COURT2 of 3$4,850,000+1.0%
07 APR 2023202304070170502BRIDGE REPLACEMENTS AND APPROACHES ON CR-124 (OLD FAYETTE ROAD) OVER BARBEE CREEK AND OVER AN UNNAMED TRIBUTARY TO BINION CREEK WEST OF SAMA1 of 4$2,262,000Low, 5.0% under the second
27 JAN 2023202301270040505BRIDGE REPLACMENTS AND APPROACHES ON CR-40 (GREER CREEK ROAD) OVER GREER CREEK AND A TRIBUTARY TO GREER CREEK3 of 5$1,555,000+18%
27 JAN 2023202301270080504BRIDGE REPLACEMENTS ON SR-5 OVER BLUE GIRTH CREEK AND BLUE GIRTH CREEK RELIEF3 of 4$10,700,000+28%
27 MAY 2022202205270010802BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE) ON SR-5 OVER MUD CREEK3 of 4$5,432,100+10%
29 APR 2022202204290010301SAFETY IMPROVEMENTS (CURB & GUTTER, DRAINAGE, SIDEWALK) ON CR-1142 (CHAPEL ROAD) FROM THE INTERSECTION OF PARK AVENUE TO THE JUNCTION OF STO2 of 3$1,950,0000.0%
29 APR 2022202204290360301ROADWAY IMPROVEMENTS (GRADE, DRAIN, PAVE, SIDEWALK, CULVERT) ON POLLY REED ROAD FROM THE JUNCTION OF SR-75 TO THE JUNCTION OF REED ROAD NORT3 of 5$12,000,000+34%
25 MAR 2022202203250011008BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE) ON CR-64 (BROWNS BRIDGE ROAD) OVER LOST CREEK6 of 7$2,660,000+19%
25 FEB 2022202202250010502WIDENING, RESURFACING, AND TRAFFIC STRIPE ON FOSTERS FERRY ROAD FROM THE JUNCTION OF JOE MALLISHAM PARKWAY TO THE JUNCTION OF 29TH STREET IN2 of 3$5,800,000+25%
Ikaros, LLC: latest ALDOT bids in the data

How this record was read

ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.

  • Every bid counted here matched its published total to within one dollar; ALDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy