ALDOT letting results, July 28, 2023
17 contracts let by Alabama DOT on July 28, 2023, $41,608,957 in low bids, a median of 2 bidders per contract.
- Owner
- Alabama DOT
- Contracts
- 17
- Low bids, total
- $41,608,957
- Data through
- 28 AUG 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Source |
|---|---|---|---|---|---|---|---|---|
| 20230728001 | BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE) ON SR-14 OVER LUBBUB CREEK SOUTH OF ALICEVILLE | 1003 | 3 | Ikaros, LLC | $12,255,000 | $14,099,935 | +15% | ALDOT |
| 20230728018 | BRIDGE WIDENING ON I-85 (NORTHBOUND AND SOUTHBOUND ROADWAYS) OVER HALAWAKEE CREEK SOUTHWEST OF THE CHAMBERS COUNTY LINE | 0606 | 2 | McInnis Construction, LLC | $6,331,271 | $7,496,329 | +18% | ALDOT |
| 20230728032 | BRIDGE REPLACEMENT ON CR-47 OVER TWO MILE CREEK FROM THE JUNCTION OF RED BIRD DRIVE TO THE JUNCTION OF PARK COURT | 0502 | 3 | GFC Construction, Inc. | $4,785,872 | $4,850,000 | +1.0% | ALDOT |
| 20230728029 | SAFETY WIDEN, PLANE, RESURFACE, GUARDRAIL INSTALL, & STRIPE ON SR-8 (US-80) FROM THE MONTGOMERY COUNTY LINE TO THE JUNCTION OF CR-40 IN SHORTER | 0602 | 3 | Wiregrass Construction Company, Inc. | $3,359,021 | $3,422,701 | +2.0% | ALDOT |
| 20230728021 | RESURFACING, SAFETY STEEL BLOCKOUT REPLACEMENT, AND STRIPE ON SR-8 (US-80) FROM THE JUNCTION OF SR-1 (US-431) TO A POINT NEAR THE WEST END OF THE CHATTAHOOCHEE | 0606 | 1 | Whitaker Contracting Corporation | $2,421,558 | ALDOT | ||
| 20230728031 | ROADWAY AND SIDEWALK IMPROVEMENTS (RESURFACING & STRIPE) ON CR-47 (WATERMELON ROAD) FROM THE JUNCTION OF SR-6 (US-82/MCFARLAND BLVD) TO THE JUNCTION OF UNION CH | 0502 | 3 | S. T. Bunn Construction Company, Inc. | $1,892,932 | $2,487,054 | +31% | ALDOT |
| 20230728028 | RESURFACING AND TRAFFIC STRIPE ON CR-35 (JOHN JOHNSTON ROAD) FROM THE JUNCTION OF CR-4 TO THE JUNCTION OF RIVERS ROAD SOUTHWEST OF MCINTOSH. | 0803 | 2 | Mobile Asphalt Company, LLC | $1,813,037 | $1,984,834 | +9.0% | ALDOT |
| 20230728015 | ACCESS MANAGEMENT ON SR-9 (US-231) FROM THE JUNCTION OF OLD MONTGOMERY HIGHWAY TO THE JUNCTION OF CHARLES AVENUE IN WETUMPKA | 0701 | 2 | Wiregrass Construction Company, Inc. | $1,597,117 | $2,190,043 | +37% | ALDOT |
| 20230728005 | INTERSECTION IMPROVEMENTS (GRADE, DRAIN, PAVE, AND SIGNALS) ON SR-25 (US-411) AT CR-10 (PARK AVENUE) IN MOODY | 0302 | 3 | Taylor Corporation | $1,521,539 | $1,698,493 | +12% | ALDOT |
| 20230728025 | PLANING, RESURFACING, AND TRAFFIC STRIPE ON CR-40/CR-101 FROM THE INTERSECTION OF SR-6 (US-82) TO THE JUNCTION OF CR-85 (OLD CARTER HILL ROAD) EAST OF PIKE ROAD | 0603 | 3 | Asphalt Contractors, Inc. | $1,494,073 | $1,497,867 | 0.0% | ALDOT |
| 20230728002 | BRIDGE REPLACEMENT (GRADE, DRAIN, PAVE, BRIDGE CULVERT) ON SR-27 OVER DEAL CREEK | 0704 | 2 | H & L Construction, Inc. | $1,353,798 | $1,538,936 | +14% | ALDOT |
| 20230728038 | INTERCHANGE MODIFICATIONS ON I-20 (EASTBOUND) AT EXIT 130 IN WOODLAWN | 0301 | 2 | Abramson, LLC | $1,065,831 | $1,074,060 | +1.0% | ALDOT |
| 20230728009 | RESURFACING AND TRAFFIC STRIPE ON CR-18 FROM CR-38 TO CR-56 (SITE 1) AND ON CR-56 FROM CR-18 TO FREEDOM WALK (SITE 2) | 0606 | 1 | East Alabama Paving Company, Inc. | $614,616 | ALDOT | ||
| 20230728041 | BRIDGE REPLACEMENT ON CR-1009 (THOMAS LANE) OVER LITTLE PAINT CREEK SOUTHEAST OF WOODVILLE | 0104 | 2 | The Bridge Builders of Alabama, LLC | $359,515 | $377,408 | +5.0% | ALDOT |
| 20230728024 | PLANING, RESURFACING, AND TRAFFIC STRIPE ON WILLOW SPRINGS ROAD FROM THE JUNCTION OF JASMINE HILL ROAD TO THE JUNCTION OF REDLAND ROAD SOUTHEAST OF WETUMPKA | 0601 | 4 | Wiregrass Construction Company, Inc. | $277,891 | $297,711 | +7.0% | ALDOT |
| 20230728011 | SAFETY IMPROVEMENTS (SAFETY WIDENING, GUARDRAIL, AND STRIPE) ON CR-379 FROM THE JUNCTION OF CR-798 TO THE JUNCTION OF CR-372 | 0606 | 1 | East Alabama Paving Company, Inc. | $266,897 | ALDOT | ||
| 20230728040 | ROADWAY LIGHTING INSTALLATION ON SR-2 (US-72) FROM THE JUNCTION OF ADAMS STREET TO THE INTERSECTION OF CR-85 (BANK STREET) IN STEVENSON | 0103 | 2 | Shoals Electric Company, Inc. | $198,990 | $223,469 | +12% | ALDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ALDOT received, the others did not match their published totals and are left out.