ALDOT contract 20250131001 bid tabulation
GRADE, DRAIN, PAVE, BRIDGE REMOVAL, AND BRIDGE REPLACEMENT ON I-65 FROM A POINT 0.560 MILE SOUTH OF BUCK CREEK TO A POINT 1.000 MILE NORTH OF THE SR-3 (US-31) INTERCHANGE. Let by Alabama DOT on January 31, 2025, Shelby, 0305. 2 bids received; low bid $66,962,022 by McInnis Construction, LLC.
- Owner
- Alabama DOT
- Letting
- 31 JAN 2025
- Pay items
- 213
- Data through
- 28 AUG 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | McInnis Construction, LLC | $66,962,022 | Low |
| 2 | Jones Bros. Contractors, LLC | $81,356,110 | +21% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. McInnis Construction, LLC | 2. Jones Bros. Contractors, LLC |
|---|---|---|---|---|---|
| 0010 | Clearing and grubbing (maximum allowable bid $ 8,000.00 per acre) (approximately 13 acres) (201A002) | LS | 1 | $104,000 | $104,000 |
| 0020 | Removal of old bridge, station 536+72.060 (206A000) | LS | 1 | $146,516 | $750,000 |
| 0030 | Removal of old bridge, station 536+06.560 (206A001) | LS | 1 | $146,516 | $750,000 |
| 0040 | Removal of old bridge, station 546+72.740 (206A002) | LS | 1 | $105,809 | $700,000 |
| 0050 | Removal of old bridge, station 546+62.750 (206A003) | LS | 1 | $105,809 | $700,000 |
| 0060 | Removal of old bridge, station 564+27.960 (206A004) | LS | 1 | $140,835 | $975,000 |
| 0070 | Removal of old bridge, station 565+29.320 (206A005) | LS | 1 | $140,835 | $975,000 |
| 0080 | Removing concrete flumes (206C003) | SY | 202 | $44.82 | $54.67 |
| 0090 | Removing bridge end slab (206C013) | SY | 1,058 | $92.22 | $105.00 |
| 0100 | Removing pipe (206D000) | LF | 9 | $50.71 | $75.00 |
| 0110 | Removing guardrail (206D001) | LF | 15,220 | $3.52 | $3.58 |
| 0120 | Removing safety barrier (206D010) | LF | 916 | $11.74 | $40.68 |
| 0130 | Removing headwalls (206E000) | EACH | 8 | $810.17 | $500.00 |
| 0140 | Removing inlets (206E001) | EACH | 14 | $1,633.81 | $500.00 |
| 0150 | Removing guardrail end anchor (all type) (206E008) | EACH | 31 | $352.24 | $357.97 |
| 0160 | Removing guardrail end anchor (type 2A) (206E014) | EACH | 3 | $1,408.96 | $1,431.86 |
| 0170 | Removing inlets (partial) (206E042) | EACH | 1 | $2,268.75 | $1,000.00 |
| 0180 | Unclassified excavation (210A000) | CY | 14,564 | $34.81 | $71.00 |
| 0190 | Borrow excavation (loose truckbed measurement) (210D001) | CY | 2,582 | $50.43 | $58.30 |
| 0200 | Borrow excavation (sand fill, complete in place) (210D101) | CY | 1,557 | $71.69 | $75.00 |
| 0210 | Borrow excavation (underwater backfill) (aldot #57) (210F002) | TON | 559 | $78.64 | $85.38 |
| 0220 | Structure excavation (214A000) | CY | 4,139 | $30.79 | $20.00 |
| 0230 | Foundation backfill, commercial (214B001) | CY | 1,097 | $95.60 | $100.00 |
| 0235 | Unclassified bridge excavation (215A000) | CY | 587 | $95.02 | $42.00 |
| 0240 | Cofferdams or sheeting and shoring, station 536+05.121 (215B000) | LS | 1 | $396,937 | $1,785,000 |
| 0250 | Cofferdams or sheeting and shoring, station 546+40.718 (215B001) | LS | 1 | $396,937 | $105,000 |
| 0260 | Cofferdams or sheeting and shoring, station 564+52.035 (215B002) | LS | 1 | $396,937 | $787,500 |
| 0270 | Cement mortar flowable backfill, mix 4 (260A003) | CY | 34 | $2,231.96 | $500.00 |
| 0280 | Crushed aggregate base course, type B, plant mixed, 6" compacted thickness (301A012) | SY | 37,240 | $17.74 | $18.75 |
| 0290 | Crushed aggregate, section 825, type B, for miscellaneous use (305B078) | TON | 42,168 | $50.25 | $45.60 |
| 0300 | Bituminous treatment AE (401A043) | SY | 63,916 | $3.70 | $3.76 |
| 0310 | Tack coat (405A000) | GAL | 27,540 | $5.87 | $5.96 |
| 0320 | Micro-milling existing pavement (approximately 0.00" thru 1.00" thick) (408B000) | SY | 130,187 | $3.05 | $3.10 |
| 0330 | Micro-milling existing pavement (approximately 1.10" thru 2.00" thick) (408B001) | SY | 18,123 | $4.11 | $4.18 |
| 0340 | Material remixing device (410H000) | EACH | 1 | $88,060 | $119,322 |
| 0350 | Smoothness testing, certified inertial profiler (410I000) | EACH | 1 | $4,696.54 | $4,772.88 |
| 0360 | Polymer modified open graded friction course (420A015) | TON | 7,711 | $175.53 | $178.38 |
| 0370 | Open graded friction course tack coat (420B000) | GAL | 28,040 | $6.46 | $6.56 |
| 0380 | Stone matrix asphalt wearing layer, 1/2" maximum aggregate size (423A003) | TON | 8,317 | $137.37 | $139.61 |
| 0390 | Stone matrix asphalt binder layer, 3/4" maximum aggregate size (423B002) | TON | 8,398 | $129.74 | $131.85 |
| 0400 | Superpave bituminous concrete wearing surface layer, leveling, 1/2" maximum aggregate size mix, esal range E (424A286) | TON | 5,860 | $129.15 | $131.25 |
| 0410 | Superpave bituminous concrete upper binder layer, patching, 3/4" maximum aggregate size mix, esal range E (424B284) | TON | 500 | $158.51 | $161.08 |
| 0420 | Superpave bituminous concrete upper binder layer, leveling, 3/4" maximum aggregate size mix, esal range E (424B288) | TON | 500 | $111.54 | $113.36 |
| 0430 | Superpave bituminous concrete lower binder layer, 1" maximum aggregate size mix, esal range E (424B581) | TON | 32,668 | $95.69 | $97.25 |
| 0440 | Superpave bituminous concrete lower binder layer, leveling, 1" maximum aggregate size mix, esal range E (424B589) | TON | 8,018 | $93.34 | $94.86 |
| 0450 | Scoring bituminous pavement surface (428A001) | MI | 11 | $585.10 | $2,625.00 |
| 0460 | Aggregate surfacing (1" down, crusher run) (430B043) | TON | 53,877 | $45.53 | $53.36 |
| 0470 | High density mineral bond (432A000) | SY | 53,921 | $5.75 | $5.85 |
| 0480 | Reinforced cement concrete bridge end slab (450B000) | SY | 2,102 | $129.09 | $332.46 |
| 0490 | Patching (460A000) | LB | 9,556 | $5.87 | $5.96 |
| 0500 | Steel reinforcement (502A000) | LB | 1,608,645 | $1.13 | $1.33 |
| 0510 | Steel reinforcement for bridge superstructure, station 536+05.121, approximately 241,500 pounds (502B000) | LS | 1 | $171,578 | $557,000 |
| 0520 | Steel reinforcement for bridge superstructure, station 546+40.718, approximately 235,500 pounds (502B001) | LS | 1 | $164,831 | $557,000 |
| 0530 | Steel reinforcement for bridge superstructure, station 564+52.035, approximately 370,200 pounds (502B002) | LS | 1 | $316,307 | $767,000 |
| 0540 | Pile points (type A, 12") (505G003) | EACH | 204 | $571.39 | $178.50 |
| 0550 | Steel piling furnished and driven (HP 12X53) (505M002) | LF | 7,080 | $128.81 | $90.30 |
| 0560 | Drilled shaft excavation, 7'-0" diameter (506A002) | LF | 590 | $616.42 | $551.25 |
| 0570 | Drilled shaft excavation, 3'-6" diameter (506A005) | LF | 559 | $463.78 | $414.75 |
| 0580 | Drilled shaft excavation, 5'-6" diameter (506A006) | LF | 290 | $528.36 | $472.50 |
| 0590 | Special drilled shaft excavation, 3'-6" diameter (506B002) | LF | 91 | $2,054.74 | $1,837.50 |
| 0600 | Special drilled shaft excavation, 5'-6" diameter (506B006) | LF | 360 | $2,612.45 | $2,336.25 |
| 0610 | Special drilled shaft excavation, 7'-0" diameter (506B009) | LF | 602 | $3,140.81 | $2,808.75 |
| 0620 | Drilled shaft construction, 3'-6" diameter, class DS2 concrete (506C021) | LF | 650 | $234.83 | $210.00 |
| 0630 | Drilled shaft construction, 5'-6" diameter, class DS2 concrete (506C025) | LF | 650 | $293.53 | $262.50 |
| 0640 | Drilled shaft construction, 7'-0" diameter, class DS2 concrete (506C028) | LF | 589 | $352.24 | $315.00 |
| 0650 | Drilled shaft construction, 7'-0" diameter, class DS1 concrete (506C048) | LF | 630 | $176.12 | $157.50 |
| 0660 | Exploration below drilled shaft (506D000) | LF | 860 | $463.78 | $414.75 |
| 0670 | Crosshole sonic logging, 3'-6" diameter (506G001) | EACH | 13 | $117.41 | $105.00 |
| 0680 | Crosshole sonic logging, 5'-6" diameter (506G005) | EACH | 30 | $117.41 | $105.00 |
| 0690 | Crosshole sonic logging, 7'-0" diameter (506G008) | EACH | 43 | $117.41 | $105.00 |
| 0700 | Structural steel (508A000) | LB | 62,390 | $7.61 | $8.40 |
| 0710 | Bridge substructure concrete (510A007) | CY | 4,621 | $1,048.76 | $1,050.00 |
| 0720 | Bridge concrete superstructure, station 536+05.121, approximately 1,040 cubic yards (510C051) | LS | 1 | $1,113,391 | $2,314,000 |
| 0730 | Bridge concrete superstructure, station 546+40.718, approximately 772 cubic yards (510C052) | LS | 1 | $1,033,845 | $2,051,500 |
| 0740 | Bridge concrete superstructure, station 564+52.035, approximately 1,600 cubic yards (510C053) | LS | 1 | $1,932,312 | $3,154,000 |
| 0750 | Grooving concrete bridge decks (510E000) | SY | 11,443 | $3.16 | $2.82 |
| 0760 | Bridge barrier rail, type 36” single slope (510J000) | LF | 1,720 | $84.07 | $85.44 |
| 0770 | Bridge barrier rail, type 54” CSF median (510J001) | LF | 1,010 | $136.20 | $138.41 |
| 0780 | Elastomeric bearing type 4 (511A004) | EACH | 32 | $2,097.88 | $2,625.00 |
| 0790 | Elastomeric bearing type 2 (mark B2) (511A051) | EACH | 64 | $419.40 | $1,155.00 |
| 0800 | Elastomeric bearing type 2 (mark B4) (511A053) | EACH | 32 | $748.76 | $1,365.00 |
| 0810 | Elastomeric bearing type 4 (mark VB4) (511A073) | EACH | 64 | $1,064.81 | $1,680.00 |
| 0820 | Elastomeric bearing type 4 (mark VB5) (511A074) | EACH | 64 | $1,168.13 | $1,785.00 |
| 0830 | Elastomeric bearing type 4 (mark VB6) (511A076) | EACH | 64 | $2,068.11 | $2,520.00 |
| 0840 | Pretensioned-prestressed concrete girders, type II (specialty item) (513B004) | LF | 1,861 | $236.39 | $420.00 |
| 0850 | Pretensioned-prestressed concrete girders,type III modified (specialty item) (513B012) | LF | 2,416 | $371.91 | $525.00 |
| 0860 | Pretensioned-prestressed concrete girders, type BT-63 (specialty item) (513B019) | LF | 1,588 | $379.04 | $525.00 |
| 0870 | Pretensioned-prestressed concrete girders, type BT-56 modified (speciality item) (513B036) | LF | 3,959 | $431.25 | $525.00 |
| 0880 | Pretensioned-prestressed concrete girders, type fib-36 (specialty item) (513B100) | LF | 3,670 | $461.29 | $577.50 |
| 0890 | Retaining wall # 1 (529A020) | SF | 390 | $59.88 | $52.50 |
| 0900 | Retaining wall # 2 (529A021) | SF | 391 | $59.90 | $52.50 |
| 0910 | Retaining wall # 3 (529A022) | SF | 2,961 | $59.90 | $52.50 |
| 0920 | Retaining wall # 4 (529A023) | SF | 3,386 | $59.90 | $52.50 |
| 0930 | Retaining wall # 5 (529A024) | SF | 540 | $59.90 | $52.50 |
| 0940 | Retaining wall # 6 (529A025) | SF | 479 | $59.90 | $52.50 |
| 0950 | Retaining wall # 7 (529A026) | SF | 1,030 | $59.90 | $52.50 |
| 0960 | Retaining wall # 8 (529A027) | SF | 889 | $59.90 | $52.50 |
| 0970 | Retaining wall # 9 (529A028) | SF | 2,350 | $59.90 | $52.50 |
| 0980 | Retaining wall # 10 (529A029) | SF | 2,493 | $59.90 | $52.50 |
| 1020 | 24" roadway pipe (class 3 R.C.) (530A002) | LF | 2,863 | $144.95 | $78.69 |
| 1030 | 24" roadway pipe, jacked installation (smooth steel) (530C002) | LF | 556 | $1,588.15 | $1,535.03 |
| 1040 | 30" roadway pipe, jacked installation (smooth steel) (530C003) | LF | 85 | $1,787.63 | $1,842.72 |
| 1050 | 18" slotted drain pipe (with variable height grate) (532A042) | LF | 2,737 | $478.35 | $471.32 |
| 1060 | Cleanout box for slotted drain (18") (532E002) | EACH | 18 | $8,571.18 | $8,710.51 |
| 1070 | 12" storm sewer pipe (class 3 R.C.) (533A096) | LF | 259 | $108.70 | $75.81 |
| 1080 | 30" storm sewer pipe (class 3 R.C.) (533A100) | LF | 4 | $524.85 | $439.96 |
| 1090 | 18" storm sewer pipe(14 gauge CS spiral-rib) (533A870) | LF | 156 | $804.28 | $817.35 |
| 1100 | 30" roadway pipe rehabilitation (538A005) | LF | 189 | $415.80 | $352.00 |
| 1110 | 36" roadway pipe rehabilitation (538A006) | LF | 556 | $491.61 | $423.59 |
| 1113 | Soil nail wall (570A000) | SY | 2,204 | $1,162.39 | $1,050.00 |
| 1117 | Excavation for soil nail wall (570B000) | CY | 19,028 | $36.76 | $34.65 |
| 1120 | Mobilization (600A000) | LS | 1 | $7,757,758 | $9,730,000 |
| 1130 | Separation geotextile (608A000) | SY | 1,145 | $9.71 | $3.44 |
| 1140 | Loose riprap, class 1 (610C000) | TON | 358 | $95.27 | $85.56 |
| 1150 | Loose riprap, class 2 (610C001) | TON | 57 | $128.71 | $85.53 |
| 1160 | Loose riprap, class 3 (610C002) | TON | 461 | $124.61 | $95.29 |
| 1170 | Filter blanket, geotextile (610D003) | SY | 8,412 | $5.20 | $4.82 |
| 1180 | Slope paving (under bridges) (614A001) | CY | 636 | $1,796.43 | $1,825.62 |
| 1190 | 24" roadway pipe end treatment, class 1 (619A003) | EACH | 6 | $2,483.30 | $2,523.66 |
| 1200 | 30" roadway pipe end treatment, class 1 (619A004) | EACH | 1 | $3,269.97 | $3,323.11 |
| 1210 | Minor structure concrete (620A000) | CY | 10 | $5,988.09 | $6,085.42 |
| 1220 | Junction boxes, type 1 or 1P (621A011) | EACH | 2 | $5,459.73 | $6,197.19 |
| 1230 | Inlets, type E3 (621C069) | EACH | 5 | $15,029 | $17,638 |
| 1240 | Inlets, type E4 (621C070) | EACH | 21 | $18,023 | $22,397 |
| 1250 | Inlets, type E3 (partial) (621C158) | EACH | 2 | $14,853 | $23,323 |
| 1260 | Inlets, type E4 (partial) (621C159) | EACH | 1 | $16,262 | $19,958 |
| 1270 | Inlet units, type E3 (621D046) | EACH | 8 | $1,232.84 | $1,577.24 |
| 1280 | Inlet units, type E4 (621D047) | EACH | 32 | $1,209.36 | $1,877.74 |
| 1290 | Concrete median or safety barrier, type tes (629A012) | LF | 21 | $610.55 | $620.48 |
| 1300 | Concrete median or safety barrier, type CSF-54 (629A103) | LF | 2,891 | $164.38 | $167.06 |
| 1310 | Concrete median or safety barrier, type CSF-54 (SE) (629A104) | LF | 3,985 | $269.59 | $268.47 |
| 1320 | Concrete median or safety barrier, type CSF-54 (FO) (629A105) | LF | 80 | $998.01 | $1,014.24 |
| 1330 | Steel beam guardrail, class A, type 2 (8'-0" post) (630A034) | LF | 9,466 | $24.66 | $25.05 |
| 1340 | Guardrail end anchor, type 8 (MASH) (630C077) | EACH | 3 | $1,761.20 | $1,789.83 |
| 1350 | Guardrail end anchor, type 13 (MASH) (630C079) | EACH | 7 | $4,109.47 | $4,176.27 |
| 1360 | Guardrail end anchor, type 20 series (MASH) (630C080) | EACH | 4 | $3,757.23 | $3,818.30 |
| 1370 | Industrial fence, 7.33 feet high, special mounting (634E003) | LF | 1,280 | $97.07 | $106.20 |
| 1380 | Topsoil (650A000) | CY | 851 | $44.59 | $54.93 |
| 1390 | Seeding (652A100) | ACRE | 13 | $1,585.08 | $2,147.80 |
| 1400 | Seeding(wetland mix) (652A110) | ACRE | 1 | $3,287.58 | $3,579.66 |
| 1410 | Mowing (652C000) | ACRE | 49 | $223.09 | $119.32 |
| 1420 | Solid sodding (bermuda) (654A001) | SY | 2,027 | $10.27 | $23.87 |
| 1430 | Mulching (656A010) | ACRE | 13 | $1,467.67 | $2,267.12 |
| 1440 | Temporary seeding (665A000) | ACRE | 5 | $998.01 | $477.29 |
| 1450 | Temporary mulching (665B001) | TON | 45 | $792.54 | $596.61 |
| 1460 | Temporary pipe (665C010) | LF | 312 | $46.97 | $77.23 |
| 1470 | Polyethylene (665E000) | SY | 1,000 | $5.28 | $4.64 |
| 1480 | Sand bags (665G000) | EACH | 622 | $5.87 | $22.52 |
| 1490 | Flow baffle (665H005) | LF | 313 | $9.98 | $9.54 |
| 1500 | Temporary riprap, class 2 (665I000) | TON | 480 | $129.10 | $90.78 |
| 1510 | Silt fence (665J002) | LF | 29,563 | $4.87 | $5.96 |
| 1520 | Drainage sump excavation (665K000) | CY | 156 | $110.43 | $31.07 |
| 1530 | Temporary coarse aggregate,aldot number 1 (665N000) | TON | 1,700 | $86.59 | $71.17 |
| 1540 | Temporary coarse aggregate,aldot number 4 (665N001) | TON | 96 | $124.54 | $102.59 |
| 1550 | Silt fence removal (665O001) | LF | 29,563 | $1.47 | $1.20 |
| 1560 | Inlet protection, stage 3 or 4 (665P005) | EACH | 31 | $675.13 | $894.92 |
| 1570 | Wattle (665Q002) | LF | 2,290 | $7.93 | $13.13 |
| 1580 | Basin dewatering device (665X000) | EACH | 5 | $1,761.20 | $15,000 |
| 1590 | Pest control treatment (666A001) | ACRE | 13 | $234.83 | $89.49 |
| 1600 | Flocculant application, ditch check (672C100) | EACH | 192 | $17.61 | $23.87 |
| 1610 | Flocculant application, sedimentation basin (672C102) | EACH | 240 | $258.31 | $268.47 |
| 1620 | Construction safety fence (674A000) | LF | 1,000 | $3.52 | $4.76 |
| 1630 | Geometric controls (680A001) | LS | 1 | $720,057 | $750,000 |
| 1640 | Construction fuel (maximum bid limited to $ 4,796,440.00) (698A000) | LS | 1 | $335,342 | $25,000 |
| 1650 | Broken white, class W, type A traffic stripe (5" wide) (701A087) | MI | 1 | $15,851 | $16,108 |
| 1660 | Solid white, class 2, type A traffic stripe (5" wide) (701A227) | MI | 6 | $5,312.96 | $5,399.32 |
| 1670 | Solid yellow, class 2, type A traffic stripe (5" wide) (701A230) | MI | 6 | $5,312.96 | $5,399.32 |
| 1680 | Broken white, class 2, type A traffic stripe (5" wide) (701A239) | MI | 13 | $3,199.52 | $3,251.52 |
| 1690 | Solid white, class 2 type A traffic stripe (10" wide) (701A270) | MI | 1 | $23,483 | $23,864 |
| 1700 | Dotted, class 2, type A traffic stripe(lane drop 10" wide) (701B063) | LF | 3,918 | $4.40 | $4.47 |
| 1710 | Dotted, class 2, type A traffic stripe (5" wide) (701B207) | LF | 10,078 | $2.35 | $2.38 |
| 1720 | Broken temporary traffic stripe (701C000) | MI | 17 | $1,203.49 | $1,223.05 |
| 1730 | Solid temporary traffic stripe (701C001) | MI | 29 | $1,262.19 | $1,282.71 |
| 1740 | Solid temporary traffic stripe (removable tape) (701C006) | MI | 3 | $13,503 | $13,722 |
| 1750 | Broken temporary traffic stripe (removable tape) (701C009) | MI | 1 | $9,393.08 | $9,545.76 |
| 1760 | Solid traffic stripe removed (paint) (701D007) | MI | 15 | $3,228.87 | $3,281.36 |
| 1770 | Solid traffic stripe removed (tape) (701D009) | MI | 3 | $7,631.87 | $7,755.93 |
| 1780 | Broken traffic stripe removed (paint) (701D014) | MI | 5 | $2,935.34 | $2,983.05 |
| 1790 | Broken traffic stripe removed (tape) (701D016) | MI | 2 | $5,283.61 | $5,369.49 |
| 1800 | Dotted temporary traffic stripe (701F000) | LF | 14,812 | $0.23 | $0.24 |
| 1810 | Solid white, class W, type A traffic stripe (5"wide) (701G146) | LF | 2,013 | $5.87 | $5.96 |
| 1820 | Solid yellow, class W, type A traffic stripe (5" wide) (701G154) | LF | 2,013 | $5.87 | $5.96 |
| 1830 | Dotted traffic stripe removed (paint) (701H010) | LF | 815 | $1.17 | $1.20 |
| 1840 | Traffic control markings, class 2, type A (703A002) | SF | 3,295 | $6.46 | $6.56 |
| 1850 | Traffic control legends, class 2, type A (703B002) | SF | 492 | $7.34 | $7.46 |
| 1860 | Pavement markers, class C, type 1- A (705A011) | EACH | 8,049 | $6.46 | $6.56 |
| 1870 | Pavement markers, class C, type 1- B (705A012) | EACH | 2,578 | $6.46 | $6.56 |
| 1880 | Pavement markers, class A-H, type 2-C (705A030) | EACH | 2,394 | $6.46 | $6.56 |
| 1890 | Pavement markers, class A-H, type 1-A (705A031) | EACH | 653 | $6.46 | $6.56 |
| 1900 | Pavement markers, class A-H, type 1-B (705A032) | EACH | 454 | $6.46 | $6.56 |
| 1910 | Barrier rail mounted delineator (mono-directional) (707G000) | EACH | 354 | $23.48 | $17.90 |
| 1920 | Class 4, aluminum flat sign panels (type IV background) (710A171) | SF | 106 | $34.05 | $26.25 |
| 1930 | Class 6 aluminum flat sign panels (type IV or XI background) (710A186) | SF | 28 | $57.53 | $41.76 |
| 1940 | Class 6 aluminum multiple flat sign panels (type IV or XI background) (710A188) | SF | 142 | $57.53 | $41.76 |
| 1950 | Roadway sign post (3" O.D. steel uniform diameter) (710B004) | LF | 26 | $311.15 | $238.64 |
| 1960 | Roadway sign post (#3 U channel, galvanized steel or 2 ", 14 GA square tubular steel) (710B021) | LF | 50 | $20.55 | $26.25 |
| 1970 | Roadway sign relocation (711A000) | LS | 1 | $29,353 | $14,319 |
| 1980 | Overhead roadway sign structure no. 1 (715A000) | LS | 1 | $90,408 | $110,405 |
| 1990 | Vehicular impact attenuator assembly (BI-directional,TL-3) (720A026) | EACH | 2 | $42,269 | $48,413 |
| 2000 | Portable concrete safety barriers, type 6 (726A000) | LF | 23,204 | $59.75 | $67.90 |
| 2010 | Portable concrete safety barriers, type 6-A (726A001) | LF | 250 | $58.71 | $56.82 |
| 2020 | Portable concrete safety barriers,type 6(bridge bolted) (726A005) | LF | 3,440 | $70.15 | $67.90 |
| 2030 | Portable impact attenuator assembly (unidirectional,TL-3) (726D025) | EACH | 25 | $17,677 | $14,205 |
| 2040 | Truck mounted impact attenuator unit (728A000) | EACH | 2 | $88,060 | $70,000 |
| 2050 | Pole for mounting traffic detection equipment (731B000) | EACH | 1 | $31,986 | $32,506 |
| 2060 | Construction signs (740B000) | SF | 3,313 | $7.04 | $8.35 |
| 2070 | Special construction signs (740C000) | SF | 132 | $8.22 | $8.65 |
| 2080 | Channelizing drums (740D000) | EACH | 1,000 | $46.97 | $34.61 |
| 2090 | Cones (36 inches high) (740E000) | EACH | 100 | $1.17 | $26.25 |
| 2100 | Barricades, type III (740F002) | EACH | 10 | $264.18 | $267.05 |
| 2110 | Portable sequential arrow and chevron sign unit (741C010) | EACH | 4 | $2,583.10 | $4,677.42 |
| 2120 | Portable changeable message sign, type 2 (742A001) | EACH | 6 | $11,741 | $15,214 |
| 2130 | Trainee hours at 80 cents per hour (999 000) | HR | 5,600 | $0.80 | $0.80 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ALDOT's tabulation for this contract. ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
Every contract let that day: ALDOT letting of January 31, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.