ALDOT letting results, November 7, 2025
27 contracts let by Alabama DOT on November 7, 2025, $83,370,381 in low bids, a median of 2 bidders per contract.
- Owner
- Alabama DOT
- Contracts
- 27
- Low bids, total
- $83,370,381
- Data through
- 28 AUG 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Source |
|---|---|---|---|---|---|---|---|---|
| 20251107022 | BRIDGE RAISING, RESURFACE, GUARDRAIL INSTALL, AND STRIPE ON I-10 FROM A POINT EAST OF THE CR-64 (WILCOX ROAD) INTERCHANGE (MP 53.301) TO THE FLORIDA STATE LINE | 0901 | 2 | Apac-Alabama, Inc. | $17,779,025 | $18,640,085 | +5.0% | ALDOT |
| 20251107020 | RESURFACE, BRIDGE RAIL RETROFIT, & WELCOME CENTER REPAIRS ON I-20/I-59 FROM THE MISSISSIPPI STATE LINE TO THE NORTHWEST CITY LIMITS OF CUBA | 0506 | 1 | S. T. Bunn Construction Company, Inc. | $9,045,328 | ALDOT | ||
| 20251107023 | RESURFACE, BRIDGE GUARDRAIL RETRO, WIM, AND BRIDGE RAISING ON I-10 FROM THE MISSISSIPPI STATE LINE TO THE CR-39 (MCDONALD ROAD) INTERCHANGE; EBR WEIGH STATION; | 0901 | 2 | Apac-Alabama, Inc. | $7,651,084 | $8,547,760 | +12% | ALDOT |
| 20251107002 | BIRDGE REPAIR (CABLE CONNECTION REPAIRS) ON SR-16 (US-90) ON THE COCHRANE/AFRICATOWN BRIDGE OVER THE MOBILE RIVER IN MOBILE. | 0901 | 1 | Southern Road & Bridge, LLC | $7,593,015 | ALDOT | ||
| 20251107026 | MICRO-FINE MILL, RESURFACING, GUARDRAIL INSTALL, AND STRIPE ON I-22 FROM A POINT 0.800 MILE EAST OF THE CR-61 OVERPASS SOUTHEAST OF CORDOVA TO THE JEFFERSON COU | 1008 | 3 | Wiregrass Construction Company, Inc. | $4,866,200 | $5,290,978 | +9.0% | ALDOT |
| 20251107053 | BRIDGE REPLACEMENT AND BRIDGE REHABILITATION ON OLD BROOK TRAIL OVER LITTLE SHADES CREEK (SITE 1) AND ON CANTERBURY ROAD OVER WATKINS CREEK (SITE 2) | 0301 | 2 | McInnis Construction, LLC | $3,989,333 | $4,100,000 | +3.0% | ALDOT |
| 20251107037 | RESURFACING, BRIDGE GUARDRAIL RETRO, AND TRAFFIC STRIPE ON SR-13 FROM THE INTERSECTION OF SR-18 TO THE INTERSECTION OF SR-102 NORTHWEST OF BERRY | 1001 | 1 | S. T. Bunn Construction Company, Inc. | $3,424,497 | ALDOT | ||
| 20251107038 | MICRO-MILLING, RESURFACING, GUARDRAIL INSTALL, AND STRIPE ON SR-38 (US-280) FROM THE JUNCTION OF DEPOT AVENUE IN JACKSON GAP TO THE JUNCTION OF SR-49 IN DADEVIL | 0404 | 1 | Gary Ingram Grading & Paving, Inc. | $3,374,672 | ALDOT | ||
| 20251107036 | RESURFACING, GUARDRAIL INSTALLATION, AND TRAFFIC STRIPE ON SR-8 (US-80) FROM THE LEE COUNTY LINE TO THE JUNCTION OF OLD CRAWFORD HIGHWAY EAST OF PHENIX CITY | 0606 | 3 | Asphalt Paving Systems Inc | $2,860,827 | $3,617,754 | +26% | ALDOT |
| 20251107027 | PLANING, RESURFACING, GUARDRAIL INSTALLATION, AND STRIPE ON I-20/I-59 FROM THE JUNCTION OF THE JOE MALLISHAM PARKWAY INTERCHANGE TO THE JUNCTION OF THE I-359 IN | 0502 | 2 | S. T. Bunn Construction Company, Inc. | $2,680,496 | $2,820,628 | +5.0% | ALDOT |
| 20251107047 | MICRO-MILLING, RESURFACING, AND TRAFFIC STRIPE ON SR-106 FROM A POINT EAST OF THE PATSALIGA CREEK BRIDGE (MP 33.103) TO THE JUNCTION OF SR-15 (US-29) WEST OF BR | 0703 | 2 | Wiregrass Construction Company, Inc. | $2,090,592 | $2,199,990 | +5.0% | ALDOT |
| 20251107009 | INSTALATION OF ITS DEVICES AND NETWORK INFRASTRUCTURE ON I-65 FROM THE CR-42 INTERCHANGE TO THE SHELBY COUNTY LINE | 0504 | 3 | Stansell Electric Co., Inc. | $1,927,018 | $1,987,957 | +3.0% | ALDOT |
| 20251107049 | MICRO-MILLING, RESURFACING, AND TRAFFIC STRIPE ON SR-219 FROM THE DALLAS COUNTY LINE TO A POINT 0.300 MILE NORTH OF THE JUNCTION OF CR-32 | 0505 | 1 | Asphalt Contractors, Inc. | $1,790,995 | ALDOT | ||
| 20251107050 | RESURFACE (MICRO-SURFACE SEAL COAT AND SCRUB SEAL), & STRIPE ON SR-103 FROM THE FLORIDA STATE LINE TO INTERSECTION OF SR-52 IN SLOCOMB | 0704 | 3 | Wiregrass Construction Company, Inc. | $1,649,950 | $1,671,503 | +1.0% | ALDOT |
| 20251107039 | RESURFACING, GUARDRAIL INSTALLATION , AND TRAFFIC STRIPE ON THE SR-225 SERVICE ROADS FROM A POINT 0.587 MILE NORTH OF SR-2 (US-72) TO A POINT 0.580 NORTH OF SR- | 0102 | 4 | Rogers Group, Inc. | $1,619,720 | $1,684,180 | +4.0% | ALDOT |
| 20251107034 | PLANING, RESURFACING, GUARDRAIL INSTALLATION, AND STRIPE ON SR-158 FROM THE JUNCTION OF DOGWOOD TRAIL TO THE SR- 17 (US-45) INTERCHANGE IN PRICHARD | 0901 | 2 | Apac-Alabama, Inc. | $1,413,157 | $1,644,169 | +16% | ALDOT |
| 20251107006 | NORWOOD NEIGHBORHOOD STREETSCAPE PROJECT ON 12TH AVENUE NORTH FROM THE INTERSECTION OF 24TH STREET NORTH TO THE INTERSECTION OF 31ST STREET NORTH IN BIRMINGHAM | 0301 | 3 | Bulls Construction Group, LLC | $1,328,785 | $1,411,125 | +6.0% | ALDOT |
| 20251107045 | MICRO-MILLING, RESURFACING, AND TRAFFIC STRIPE ON SR-207 FROM A POINT 0.230 MILE SOUTH OF THE ANDERSON CREEK BRIDGE TO THE TENNESSEE STATE LINE | 0201 | 3 | Grayson Carter & Son Contracting, Inc. | $1,293,947 | $1,372,561 | +6.0% | ALDOT |
| 20251107057 | INTERSECTION IMPROVEMENTS TO INCLUDE LEFT TURN LANE ADDITION ON SR-57 (US-45) AT CR-1 TO INCLUDE LEFT TURN LANES ON SR-57 (US-45) IN FRUITDALE | 0804 | 8 | Pine City Contracting, LLC | $1,206,325 | $1,356,508 | +12% | ALDOT |
| 20251107042 | MICRO-MILLNG, RESURFACING, AND TRAFFIC STRIPE ON SR-12 (US-84) FROM THE TOMBIGBEE RIVER BRIDGE TO A POINT 0.500 MILE WEST OF CR-3 (WINN ROAD) IN COFFEEVILLE | 0804 | 2 | Wiregrass Construction Company, Inc. | $1,182,076 | $1,294,896 | +10% | ALDOT |
| 20251107012 | ROADWAY IMPROVEMENTS (ACCESS MANAGEMENT) ON SR-9 (US-231) FROM THE INTERSECTION OF CHARLES AVENUE TO THE JUNCTION OF MAIN STREET IN WETUMPKA | 0601 | 5 | Wiregrass Construction Company, Inc. | $1,151,403 | $1,173,042 | +2.0% | ALDOT |
| 20251107041 | MICRO-MILLING, RESURFACING, AND TRAFFIC STRIPE ON SR-12 (US-84) FROM THE JUNCTION OF BELLINGRATH CIRCLE (MP 36.201) TO A POINT 0.340 MILE WEST OF CR-22 (COBB ST | 0804 | 2 | Apac-Alabama, Inc. | $993,660 | $1,222,424 | +23% | ALDOT |
| 20251107033 | MICRO-MILLING, RESURFACING, AND TRAFFIC STRIPE ON SR-17 FROM THE INTERSECTION OF HERMITAGE DRIVE TO THE JUNCTION OF COX CREEK PARKWAY IN FLORENCE | 0201 | 3 | Rogers Group, Inc. | $845,000 | $883,342 | +5.0% | ALDOT |
| 20251107015 | SAFETY IMPROVEMENTS (BRIDGE RAIL RETRO & GUARDRAIL INSTALL) ON VARIOUS ROUTES AT VARIOUS LOCATIONS IN THE EAST CENTRAL REGION (ALEXANDER CITY AREA) AS INDICATED | 04 | 1 | Gillespie Construction, LLC | $645,305 | ALDOT | ||
| 20251107030 | SAFETY IMPROVEMENTS (SLOPE FLATTENING AND GUARDRAIL INSTALL) ON CR-54 FROM THE JUNCTION OF BATCH PLANT DRIVE TO THE JUNCTION OF CR-191 (RENFROE ROAD) NORTHEAST | 0405 | 3 | Waites Construction Company, Inc. | $494,970 | $569,799 | +15% | ALDOT |
| 20251107200 | HORIZONTAL CURVE PROJECT ON I-22 AT VARIOUS LOCATIONS IN THE WEST CENTRAL REGION (FAYETTE AREA) AS INDICATED IN THE PLANS | 10 | 3 | Bulls Construction Group, LLC | $273,000 | $299,112 | +10% | ALDOT |
| 20251107017 | TRAFFIC SIGNAL UPGRADES (DETECTION SYSTEM UPGRADES) ON VARIOUS ROUTES AT VARIOUS LOCATIONS IN MOBILE AS INDICATED IN THE PLANS | 0901 | 2 | Bagby & Russell Electric Company, Inc. | $200,000 | $534,310 | +167% | ALDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ALDOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.