ALDOT contract 20260227004 bid tabulation
INTERSTATE LIGHTING INSTALLATION AND UPGRADES ON I-20 AT THE CR-207 (EXIT 165) INTERCHANGE EAST OF RIVERSIDE. Let by Alabama DOT on February 27, 2026, Talladega, 0405. 4 bids received; low bid $1,171,084 by Temple J Electric, LLC.
- Owner
- Alabama DOT
- Letting
- 27 FEB 2026
- Pay items
- 30
- Data through
- 28 AUG 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Temple J Electric, LLC | $1,171,084 | Low |
| 2 | Stone & Sons Electrical Contractors, Inc. | $1,484,402 | +27% |
| 3 | Stone Electric Company, Inc. | $1,571,725 | +34% |
| 4 | Williams Power & Signal, LLC | $1,645,638 | +41% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Temple J Electric, LLC | 2. Stone & Sons Electrical Contractors, Inc. | 3. Stone Electric Company, Inc. | 4. Williams Power & Signal, LLC |
|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (600A000) | LS | 1 | $14,000 | $130,000 | $91,250 | $72,284 |
| 0020 | Filter blanket, geotextile (610D003) | SY | 150 | $10.00 | $7.30 | $30.00 | $5.46 |
| 0030 | Temporary seeding (665A000) | ACRE | 1 | $1,800.00 | $2,125.00 | $2,000.00 | $682.82 |
| 0040 | Temporary mulching (665B001) | TON | 3 | $2,700.00 | $1,045.00 | $1,000.00 | $1,138.04 |
| 0050 | Sand bags (665G000) | EACH | 450 | $8.00 | $10.15 | $8.00 | $2.73 |
| 0060 | Silt fence (665J002) | LF | 500 | $3.50 | $3.40 | $3.00 | $6.83 |
| 0070 | Silt fence removal (665O001) | LF | 500 | $1.55 | $1.40 | $1.10 | $1.37 |
| 0080 | Wattle (665Q002) | LF | 780 | $12.00 | $14.45 | $12.00 | $5.00 |
| 0090 | Geometric controls (680A001) | LS | 1 | $15,000 | $6,280.00 | $10,000 | $4,096.92 |
| 0100 | Construction fuel (maximum bid limited to $ 40,000.00) (698A000) | LS | 1 | $5,000.00 | $12,500 | $100.00 | $27,313 |
| 0110 | Construction signs (740B000) | SF | 1,563 | $7.00 | $7.20 | $10.00 | $11.82 |
| 0120 | Channelizing drums (740D000) | EACH | 150 | $35.00 | $153.00 | $30.00 | $50.00 |
| 0130 | Portable sequential arrow and chevron sign unit (741C010) | EACH | 1 | $2,400.00 | $2,900.00 | $1,500.00 | $4,118.00 |
| 0140 | High mast luminaire assembly with three, LED, 400 watt equivalent luminaires (750A261) | EACH | 9 | $45,748 | $56,980 | $60,000 | $70,052 |
| 0150 | High mast luminaire assembly with four, LED, 400 watt equivalent luminaires (750A262) | EACH | 3 | $45,748 | $59,035 | $61,000 | $70,243 |
| 0165 | Roadway luminaire assembly with one, LED low profile underpass surface mount, 150 watt equivalent luminaire (750B581) | EACH | 2 | $3,800.00 | $2,445.00 | $2,500.00 | $1,824.79 |
| 0170 | Roadway luminaire assembly with one, LED, 400 watt equivalent luminaire (750B602) | EACH | 18 | $8,749.00 | $7,410.00 | $8,000.00 | $8,672.53 |
| 0180 | Pole foundation,roadway (750C010) | EACH | 18 | $4,000.00 | $3,885.00 | $5,500.00 | $2,228.00 |
| 0190 | Pole foundation, high mast (750C011) | EACH | 12 | $8,800.00 | $9,230.00 | $15,500 | $14,257 |
| 0200 | Electrical junction box,type 1 (750D200) | EACH | 9 | $750.00 | $1,600.00 | $1,500.00 | $1,112.00 |
| 0220 | Conduit, 3/4 inch, rigid metallic (750E123) | LF | 160 | $15.00 | $11.50 | $6.00 | $23.00 |
| 0230 | Conduit, 2 inch, rigid metallic (750E127) | LF | 150 | $15.00 | $23.30 | $16.50 | $25.00 |
| 0240 | Conductor, #10 AWG (750F022) | LF | 500 | $5.00 | $1.65 | $1.10 | $1.00 |
| 0250 | Conductor, #6 AWG (750F024) | LF | 350 | $5.00 | $3.60 | $2.00 | $2.60 |
| 0260 | Conductor, #2 AWG (750F026) | LF | 150 | $8.00 | $5.45 | $4.50 | $5.71 |
| 0270 | Combined duct and cable,2 #6 AWG/ 1 #6 AWG GND (750G010) | LF | 12,000 | $9.00 | $11.60 | $12.00 | $12.59 |
| 0280 | Combined duct and cable, 4 #2 AWG/ 1 #2 AWG GND (750G112) | LF | 800 | $12.00 | $23.75 | $30.00 | $19.63 |
| 0290 | Service pole (750H005) | EACH | 1 | $5,000.00 | $3,540.00 | $3,500.00 | $3,442.00 |
| 0300 | Lighting control center (750I015) | EACH | 1 | $35,000 | $52,825 | $45,000 | $43,786 |
| 0310 | 6" electrical conduit, 1 line, type 5 installation (756A028) | LF | 425 | $60.00 | $65.50 | $75.00 | $122.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ALDOT's tabulation for this contract. ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
Every contract let that day: ALDOT letting of February 27, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.